1. Use Johnson's rule to obtain the optimum sequence for
processing the jobs shown through work centers A and B.
Construct a chart.
JOB TIMES (HOURS)
JOB
WORK CENTER WORK CENTER
A
2.50
3.80
2.20
5.80
B
4.20
1.50
3.00
4.00
2.00
A
B
C
4.50
loloDE
Transcribed Image Text:1. Use Johnson's rule to obtain the optimum sequence for processing the jobs shown through work centers A and B. Construct a chart. JOB TIMES (HOURS) JOB WORK CENTER WORK CENTER A 2.50 3.80 2.20 5.80 B 4.20 1.50 3.00 4.00 2.00 A B C 4.50 loloDE
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,