3.13. Given the following data, can an order for 40 more units for delivery in week 5 be accepted? If not, what do you suggest can be done? There are zero units on hand. Week 1 3 4 6 7 8. Customer Orders 70 10 50 40 10 15 20 15 MPS 100 100 100 ATP
Q: An end item’s demand forecasts for the next 10 weeks are 30,20, 35, 50, 25, 25, 0, 40, 0, and 50…
A: Given that, Quantity on hand = 80 Demand forecast for 6 weeks is 3 unit For 7 weeks is 25 units…
Q: 11. A manager must decide which type of machine to buy, A, B, or C. Machine costs are as follows:…
A: The period of time between a client placing an order and the firm fulfilling it is known as the…
Q: QUESTION 1 A master production schedule shows the following information MPS Week Week Week Week…
A: Find the Given details below: Weeks 1 2 3 4 Forecasted Demand 1000 1200 1300 1200 Actual…
Q: What is a precedence diagramand what are its various components? Briefly explain.
A: A strategy for scheduling activities in a very project plan, the precedence diagramming technique…
Q: Eastman Publishing Company is considering publishing an electronic textbook on spreadsheet…
A: Given Information: Fixed Cost = $ 160,000 Variable cost = $ 6 per unit Selling Price = $ 46 per…
Q: Chuck's Custom Boats (CCB) customizes speedboats to each customer's order. CCB has landed a contract…
A: Given- Activity ImmediatePredecessor Normal Time (weeks) CRASHING COSTS 1st Week 2nd Week…
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: A time based production chart and Product structure chart are helps to identify the correct…
Q: 1) Table below is for a product with 150 unit lot size. The current on-hand inventory is 110 units.…
A: given,
Q: The following table lists the components needed to assemble an end item, lead times (in weeks), and…
A: A product chart helps to identify the parental relationship between each materials based on the…
Q: Solve the attached problem
A: Solution As per the given information, the lead time is 2 weeks, and the anticipated on-hand stock…
Q: Task 2: A small Tennessee company makes fused magnesia and silica. To prepare input for the planning…
A: Given data is Production quantity = 40000 pounds Safety stock = 30000 pounds
Q: Question: How can the Quality Circle concept be applied to this situation
A: The Government Medical College and hospital is facing lots of problems and issues in XYZcity. The…
Q: WEEK 9 & 10: INTRODUCTION TO CAPACITY PLANNING AND SUPPLY CHAIN MANAGEMENT 1. Determine the…
A: Ans 1: Given: Actual output = 7 loans/day Design capacity = 10 loans/day Effective capacity = 8…
Q: Choose either the 4-star option or the 5-star option and evaluate your choice of option based on a…
A: At first, the above case study should be written in different headings. It's very long to read.
Q: Choose either the 4-star option or the 5-star option and evaluate your choice of option based on a…
A: The SWOT analysis was evolved in 1960 at Stanford Research Institute with the motive to help…
Q: a. Write the product structure diagram as an indented bill-of-materials list.
A: Indented bill-of-materials list is following:
Q: Identify the competitive advantage of the hotel (for your option) would be and whether it would be…
A: Hotel Competitive Advantage Simply put, a hotel (or any company really) has a competitive advantage…
Q: Problem 4 A. Complete the following Table for Product A MPS Record for Product A Demand time fence:…
A: As per the given data, the lead time is 2 weeks and projected on hand inventory was 34. Fixed order…
Q: 8. When will the manager need to place their Second order? write the week number example: 1
A: I have created the table based on the given information in the question,
Q: Product X is made of two units of Y and three of Z. Y is made of one unit of A and two units of B. Z…
A: A Small Introduction about MRP Material necessities arranging (MRP) is a PC based stock…
Q: it was seconds ag9 + BIUA co E D - E E E = 1E E- E- E E X Consumer Behaviour Course Code: MKT 344…
A: In cross-cultural analysis data collected from the consumers to test the developed hypothesis…
Q: Given the following data, can an order for 40 more units for delivery in week 5 beaccepted? If not,…
A: Solution The following table shows the ATP for each week - Week 1 2 3 4 5 6 7 8 Customer…
Q: Peppers Lockdown produces keys for homes and cars. As Peppers planned for next year’s production,the…
A: Formula:
Q: company that produces golf carts has just received an order for 200 carts, which must be ready for…
A: Material Resource Planning (MRP) is a data framework that converts ace timetable necessities for the…
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: Network:
Q: Problem 4 A. Complete the following Table for Product A MPS Record for Product A Demand time fence:…
A: The given data is
Q: The following table lists the components needed to assemble an end item, lead times (in weeks),and…
A: Material Requirement Planning refers to the quantification of the basic components that are required…
Q: How many tickets must Star Symphony sell to break even? 2. How many tickets must the symphony sell…
A: Facts of the question. Fixed cost = 5000 Selling price = 15 per person Variable cost = 2 per…
Q: What are the important long-term issues relevant for managing capacity, revenue, and customer…
A: The variable that defines the operational efficiency of a project is called operational metrics. It…
Q: Q2: Six processes are to be laid out in six areas along a long corridor at Linda Babat Accounting…
A: Every pair of connected nodes in the network is associated with a specific demand. The demand will…
Q: d. Sales has requested that you add an MPS of 200 in period 9 to cover their needs for a sales…
A: The estimated level of inventory that a manufacturer has in stock which can be readily sold is…
Q: A company that produces golf carts has just received an order for 200 carts, which must be ready for…
A: An assembly time chart shows when production or procurement should be done as per the lead time for…
Q: The following table lists the components needed to assemble an end item, lead times, and quantities…
A: (a): Units of end item required = 17. Thus 17*2 = 34 units of B, 17 units of C and 17*3 = 51 units…
Q: 2. CREATE A NETWORK DIAGRAM FOR FOLLOWING ACTIVITIES GIVEN IN THE TABLE.' S. NO АCTIVITY PRECEDESSOR…
A: A network diagram refers to the graphical representation which is made of series of connected arrows…
Q: Problem 4 A. Complete the following Table for Product A MPS Record for Product A Demand time fence:…
A: Given data is
Q: Problem 4 A. Complete the following Table for Product A MPS Record for Product A Demand time fence:…
A: Given information Period 1 2 3 4 5 6 7 8 Forecast 10 10 10 10 10 10 15 15 Customer order…
Q: 14. 5 11 1 12 source sink 10 7. What is the maximum flow in the above network diagram? (A) 9 (В) 10…
A:
Q: 6.10. NanoTech is ready to begin production of its exciting new tech- nology. The company is…
A: Given data The amount using the first production technique is $200000+40x The amount using the…
Q: Problem 4 A. Complete the following Table for Product A MPS Record for Product A Demand time fence:…
A: Given information Period 1 2 3 4 5 6 7 8 Forecast 10 10 10 10 10 10 15 15 Customer order…
Q: Quantity on Hand 60 1 Forecast 50 Customer orders (booked) 60 Projected on Hand MPS quantity MPS…
A: Find the Given details below: Weeks 1 2 3 4 5 6 7 8 Forecast 50 40 40 40 40 40 35 35 Customer…
Q: Problem #2- Brown Manufacturing-Modified, from textbook page #198 If the annual demand is reduced to…
A: Given:Annual demand = 8,000 unitsDaily demand=60 unitsProduction per day= 80 unitsOrdering cost=$120…
Q: Star Symphony would like to perform for a neighbouring city. Fixed costs for the performance total…
A: Given - Selling price = $15 Fixed costs = $5000 Variable cost = $2 Sales = 500 units
Q: 1'. find the critical Path for the following business network activity pre-Act Duration activity…
A: Given data is
Q: What aggregate planning difficulty that might confront an organization offering a variety of…
A: Aggregate planning assumes that all the items that are being manufactured or being delivered AS…
How do I solve the attached warehouse management question?
Given data-
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- K The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V, 1 unit of W, and 1 unit of X. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U, 2 weeks to make V, 3 weeks to make W, 1 week to make X, 2 weeks to make Y, and 1 week to make Z. Click the icon to view the product structure and the time-phased product structure. Click the icon to view the on-hand inventory. Suppose that in addition to 130 units of S, there is also a demand for 20 units of U, which is a component of S. The 20 units of U are needed for maintenance purposes. These units are needed in week 6. Additionally, a new order has been received for 80 units of S due in week 8. Modify the net material requirements plan to reflect these changes. Construct a new net material requirements plan (enter your responses as whole numbers).…Calculate customer life time value for the data below. (Show Work) Purchase Occasion Transition Probability Average Basket Size 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 ΝΑ 55% 75% 78% 83% 81% 81% 86% 82% 85% 90% 93% 85% 89% 85% 91% 97% 97% 96% 85% 83% 89% 82% 79% 82% 89% 88% 86% 67% 75% $46.71 $56.71 $57.93 $56.87 $58.26 $66.90 $63.62 $70.27 $63.03 $62.60 $71.81 $76.76 $78.14 $65.65 $74.84 $81.11 $72.08 $87.30 $71.94 $75.44 $70.35 $72.86 $66.68 $79.90 $93.91 $61.08 $94.16 $100.40 $77.89 $99.70Q4) A manufacturer provides specialized microchips. During the next 3 months its sales, costs, and available time are shown in the table. Month 1 Month 2 Month 3 There are no chips in stock at the beginning of the first month. It takes 1.5 hr of production time to produce a chip and costs $5 to store a chip from one month to the next. Determine a production schedule that meets the demand requirements, does not exceed the monthly production time limitations, and minimizes cost. Note that no chips should be in stock at the end of the 3 months. Use fmincon. Chips required Cost regular time ($/chip) Cost overtime ($/chip) Regular operation time (hr) Overtime (hr) 1000 100 110 2500 100 120 2200 120 130 2400 2400 720 2400 720 720
- Q3: FIND INITIAL FEASIRLE SOLUTION COST FOR GIVEN PROBLEM by using A north-west oomer rule Bleast cost method e-Vogels approvimation method D1 D2 D3 D4 SUPPLE P1 2. 11 P2 1. 1. Pa 8. 15 6. 10 Demand 2. A* JIS O 11600 O 11300 O 11200 O 11000Table 1. Demand of Hairdryer from January to July [Jadual 1. Permintaan Pengering Rambut dari Januari 2021 hingga Julai 2021] Month Demand January February 2800 2870 March 2968 April Мay 3000 3100 Jun 3150 July 3400 a) Calculate forecast future demand for May, June, July and August by using 3 months simple moving average.[hitung ramalan permintaan masa depan untuk bulan Mei, Jun, Julai dan Ogos dengan menggunakan purata bergerak sederhana 3 bulan.] *4. Identify the Order-winners and Order qualifiers for the following business: A mobile manufacturing company Car Renting company
- Figure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7Name four important items of information that should be ona typical purchase order.|Product D is stocked only at the AMC Chemical Company's Dallas warehouse and at the company's plant warehouse in Akron. The sales director has forecast product sales from the Dallas warehouse to be 40 units per week for the next 8 weeks. Product D is manufactured at the firm's Akron plant using 2 units of ingredient X per unit of product D. Information: Ingredient X Projected available balance: 4 Units Schedule receipt in week 1: 320 units Safety stock quantity: 2 Product D in Dallas Product D in Plant Warehouse Warehouse Projected available balance: 85 Units Safety stock quantity: 5 units Lead time: 2 weeks Lot for lot size quantity Projected available balance: 2 Units Schedule receipt in week 1: 46 units Safety stock quantity: 8 units units Lead time: 1 week Lead time: 4 weeks Lot for lot size quantity Lot size quantity: 320 units Prepare the DRP records for product D at the Dallas warehouse and the plant warehouse as well as the MRP record for ingredient X (Assume ingredient X is…
- c. Compute and tabulate the daily demand for each month in the table below (round off to the nearest whole number). MONTH PRODUCTION DAYS DEMAND FORECAST DEMAND PER DAY JAN 2022 16 150 ? FEB 2022 16 150 ? MAR 2022 23 250 ? APR 2022 21 250 ? MAY 2022 22 400 ? JUN 2022 22 500 ? JUL 2022 21 600 ? AUG 2022 20 750 ? SEP 2022 20 450 ? OCT 2022 20 250 ? NOV 2022 16 150 ? DEC 2022 16 150 ? TOTAL ? ? d. Assuming that MPQ Limited had adopted a level strategy for the year ended 31 December 2022, compute the average daily demand for the year (round off to the nearest whole number). e. Prepare a graph showing the monthly forecasts and average daily forecast (in units per day) for MPQ Limited.Problem 2: Week Forecast Customer Orders Projected On-Hand Inventory MPS Available-to-Promise On-hand Inventory schedule production whenever projected on-hand inventory drops below MPS lot size Complete the master production schedule based on the following information 160 160 30 300 1 120 110 2 100 100 3 130 75 4 110 50 5 140 32 6 140 11 7 170 5 8 180 0ssume you are the manager of a shop that assembles power tools. You have just received an order for 50 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Components Saw 2 15 A(2), B(1), C(4) A 1 10 E(3), D(1) B 2 5 D(2), F(3) C 2 65 E(2), D(2) D 1 20 E 1 10 F 2 30 Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.)