8. The following information (in AOA format) concerns progress at day 40 of an Internet marketing project. Deter- mine if the project is in control based on time and cost to date. If not, what is the cost overage or underage? Actual % Days Duration Budget Cost Activity Completed 1-2: Contact 10 300 250 100 sites 2–3: Solicit 8 400 450 100 costs 2-4: Design 12 350 380 100 ads 4-3: Evaluate budget 3-5: Shoot 18 405 400 70 ads 5–6: Place 16 450 ads
8. The following information (in AOA format) concerns progress at day 40 of an Internet marketing project. Deter- mine if the project is in control based on time and cost to date. If not, what is the cost overage or underage? Actual % Days Duration Budget Cost Activity Completed 1-2: Contact 10 300 250 100 sites 2–3: Solicit 8 400 450 100 costs 2-4: Design 12 350 380 100 ads 4-3: Evaluate budget 3-5: Shoot 18 405 400 70 ads 5–6: Place 16 450 ads
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
Related questions
Question
need the answer using excel. thanks
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,