A company specializing in custom-engineered equipment is planning to submit a proposal to the National Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? e f 8 h Activity Immediate predecessor b i j a b c, d d e, f f, g h, i a a a 15 20 5 Optimistic time (weeks) Most likely time (weeks) Pessimistic time (weeks) 10 17 4 10 24 16 10 14 26 23 12 8 39 24 19 24 32 35 13 10 20 PERT network diagram. 15,24,39 10,1424 5,8,11 8,1624 202632 10,12.20 f 7,1013 i 7,10,19 17,2335 (a) PERT network analysis: Activity T. Critical ES EF LS LF S a 7.11 11 15 5.44 f 26 24 1.78 2.78 What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? weeks.

Computer Networking: A Top-Down Approach (7th Edition)
7th Edition
ISBN:9780133594140
Author:James Kurose, Keith Ross
Publisher:James Kurose, Keith Ross
Chapter1: Computer Networks And The Internet
Section: Chapter Questions
Problem R1RQ: What is the difference between a host and an end system? List several different types of end...
icon
Related questions
Question
A company specializing in custom-engineered equipment is planning to submit a proposal to the National
5.
Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to
launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a
penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required
to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time
estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion
time should the company specify in its proposal in order to be 85% sure that it will complete the project on time?
ij
Activity
Immediate predecessor
Optimistic time (weeks)
a
b
d.
h
b
e, d
d e,f f,g
h, i
a
a
a
15
8
10
20
17
4
10
Most likely time (weeks)
24
16
10
14
26
23
7
12
Pessimistic time (weeks)
39
24
19
24
32
35
13
10
20
PERT network diagram.
15,24,39
10,1424
5,913
h
5,8,11
8,1624
20.2632
10.12.20
j
7,1013
7,10,19
17,2335
(a) PERT network analysis:
Activity
T.
Critical
ES
EF
LS
LF
a
7.11
11
15
5.44
f
26
24
h
1.78
i
2.78
What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time?
Tmp=
weeks.
Transcribed Image Text:A company specializing in custom-engineered equipment is planning to submit a proposal to the National 5. Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? ij Activity Immediate predecessor Optimistic time (weeks) a b d. h b e, d d e,f f,g h, i a a a 15 8 10 20 17 4 10 Most likely time (weeks) 24 16 10 14 26 23 7 12 Pessimistic time (weeks) 39 24 19 24 32 35 13 10 20 PERT network diagram. 15,24,39 10,1424 5,913 h 5,8,11 8,1624 20.2632 10.12.20 j 7,1013 7,10,19 17,2335 (a) PERT network analysis: Activity T. Critical ES EF LS LF a 7.11 11 15 5.44 f 26 24 h 1.78 i 2.78 What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? Tmp= weeks.
Expert Solution
Step 1

here is the expected times forproject completion.

expected time=Te=To+Tp+4Tm/6.

Te=expected time.

To=optimistic time.

Tp=pessimistic time.

Tm= most likely time.

expected time for A=15+11+4*8/6=8.

expeced time for B=15+39+4*24/6=25

expected time for C=8+24+4*16/6=16.

expected time for D=7+19+4*10/6=11.

expected time for E=10+24+4*14/6=15.

expected time for F=20+32+4*26/6=26.

expected time for G=17+35+4*23/6=24.

expected time for H=5+13+4*9/6=9

expected time for I=7+13+4*10/6=10.

expected time for J=10+20+4*12/6=13.

trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 2 images

Blurred answer
Recommended textbooks for you
Computer Networking: A Top-Down Approach (7th Edi…
Computer Networking: A Top-Down Approach (7th Edi…
Computer Engineering
ISBN:
9780133594140
Author:
James Kurose, Keith Ross
Publisher:
PEARSON
Computer Organization and Design MIPS Edition, Fi…
Computer Organization and Design MIPS Edition, Fi…
Computer Engineering
ISBN:
9780124077263
Author:
David A. Patterson, John L. Hennessy
Publisher:
Elsevier Science
Network+ Guide to Networks (MindTap Course List)
Network+ Guide to Networks (MindTap Course List)
Computer Engineering
ISBN:
9781337569330
Author:
Jill West, Tamara Dean, Jean Andrews
Publisher:
Cengage Learning
Concepts of Database Management
Concepts of Database Management
Computer Engineering
ISBN:
9781337093422
Author:
Joy L. Starks, Philip J. Pratt, Mary Z. Last
Publisher:
Cengage Learning
Prelude to Programming
Prelude to Programming
Computer Engineering
ISBN:
9780133750423
Author:
VENIT, Stewart
Publisher:
Pearson Education
Sc Business Data Communications and Networking, T…
Sc Business Data Communications and Networking, T…
Computer Engineering
ISBN:
9781119368830
Author:
FITZGERALD
Publisher:
WILEY