(a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen This answer has not been graded yet. (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter14: Data Mining
Section14.2: Classification Methods
Problem 8P
icon
Related questions
Question
Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS
has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of
websites and then automatically generates a report for management on a daily basis.
Activity
A
B
C
Description
Report generation
Web scraping
Testing
Immediate
Predecessor
This answer has not been graded yet.
A, B
Optimistic
1
(d) Should you use the estimate in (b) or (c)?
5
1
Time (Weeks)
(a) Construct the project network. (Submit a file with a maximum size of 1 MB.)
Choose File No file chosen
Most Probable
8
9
1
Pessimistic
12
The probability estimate from (b) based on the critical path is more accurate.
O The probability estimate from (c) based on both paths is more accurate.
The probability estimates from (b) and (c) are equal.
11
(b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (You may need to use
the appropriate technology to answer this question. Round your answer to four decimal places.)
1
(c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (You may
need to use the appropriate technology to answer this question. Round your answer to four decimal places.)
Transcribed Image Text:Management Decision Systems (MDS) is a consulting company that specializes in the development of decision support systems. MDS has a four-person team working on a current project with a small company to set up a system that scrapes data from a collection of websites and then automatically generates a report for management on a daily basis. Activity A B C Description Report generation Web scraping Testing Immediate Predecessor This answer has not been graded yet. A, B Optimistic 1 (d) Should you use the estimate in (b) or (c)? 5 1 Time (Weeks) (a) Construct the project network. (Submit a file with a maximum size of 1 MB.) Choose File No file chosen Most Probable 8 9 1 Pessimistic 12 The probability estimate from (b) based on the critical path is more accurate. O The probability estimate from (c) based on both paths is more accurate. The probability estimates from (b) and (c) are equal. 11 (b) Based solely on the critical path, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.) 1 (c) Using all paths through the project network, estimate the probability that the project will be complete within 11 weeks. (You may need to use the appropriate technology to answer this question. Round your answer to four decimal places.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,