a) Draw the network diagram showing ES, EF, LS, LF, and the critical path. b) Perform CPM calculations and complete the table below. c) Crash the schedule one day at time and show the effect of crashing each activity on the network by crossing out values and writing the new ones immediately above or below it. d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. e) Draw the graph of the total cost corresponding to the crashing exercise:

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
a) Draw the network diagram showing ES, EF, LS, LF, and the critical path.
b) Perform CPM calculations and complete the table below.
c) Crash the schedule one day at time and show the effect of crashing each activity on the network by
crossing out values and writing the new ones immediately above or below it.
d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated
with each duration. Indirect cost (overhead) is $100 per day.
e) Draw the graph of the total cost corresponding to the crashing exercise:
Activity IPA
A
B
H
Activity
A
B
с
D
E
F
G
A
B
B, C
C
D, F
E, F
G, H
IPA
A
A
B
B, C
C
D, F
Duration
Normal
7
6
18
10
6
+
7
Duration
7
6
10
6
4
4
Crash
5
7
4
3
2
14
2
ES
Cost $
Normal
$500
$550
$800
$1,200
$600
$500
$700
$650
$300
EF
Crash
$640
$630
$935
$1,440
$700
$590
$1,000
$950
$300
LS
LF
TF
FF
Transcribed Image Text:a) Draw the network diagram showing ES, EF, LS, LF, and the critical path. b) Perform CPM calculations and complete the table below. c) Crash the schedule one day at time and show the effect of crashing each activity on the network by crossing out values and writing the new ones immediately above or below it. d) Calculate the normal, least-cost, and crash duration for the project. Then calculate the cost associated with each duration. Indirect cost (overhead) is $100 per day. e) Draw the graph of the total cost corresponding to the crashing exercise: Activity IPA A B H Activity A B с D E F G A B B, C C D, F E, F G, H IPA A A B B, C C D, F Duration Normal 7 6 18 10 6 + 7 Duration 7 6 10 6 4 4 Crash 5 7 4 3 2 14 2 ES Cost $ Normal $500 $550 $800 $1,200 $600 $500 $700 $650 $300 EF Crash $640 $630 $935 $1,440 $700 $590 $1,000 $950 $300 LS LF TF FF
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 7 steps with 10 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.