A garment factory manufactures men's shirts and women's blouses. The production process includes cutting, sewing, and packaging. The factory employs 25 workers in the cutting department, 35 workers in the sewing department, and 5 workers in the packaging department. Each employee works an 8-hour shift per day for 5 days a week. The following table gives the time requirements and profit per unit for the two garments: Minutes per unit Garment Cutting Sewing Packaging Profit/unit Shirts 20 70 12 Php 80.00 Blouses 60 60 Php 120.00 4 Determine the optimal weekly production schedule for the garment factory.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question

Can you please answer this for me.

Practice Exercise 9 – 1:
My Score:
A garment factory manufactures men's shirts and women's blouses. The
production process includes cutting, sewing, and packaging. The factory employs 25
workers in the cutting department, 35 workers in the sewing department, and 5 workers
in the packaging department. Each employee works an 8-hour shift per day for 5 days a
week. The following table gives the time requirements and profit per unit for the two
garments:
Minutes per unit
Garment
Cutting
Sewing
Packaging
Profit/unit
Shirts
20
70
12
Php 80.00
Blouses
60
60
Php 120.00
4
Determine the optimal weekly production schedule for the garment factory.
Transcribed Image Text:Practice Exercise 9 – 1: My Score: A garment factory manufactures men's shirts and women's blouses. The production process includes cutting, sewing, and packaging. The factory employs 25 workers in the cutting department, 35 workers in the sewing department, and 5 workers in the packaging department. Each employee works an 8-hour shift per day for 5 days a week. The following table gives the time requirements and profit per unit for the two garments: Minutes per unit Garment Cutting Sewing Packaging Profit/unit Shirts 20 70 12 Php 80.00 Blouses 60 60 Php 120.00 4 Determine the optimal weekly production schedule for the garment factory.
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 2 steps with 8 images

Blurred answer
Knowledge Booster
Process selection
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,