a) Identify the critical path. b) What is the expected time to complete the project? c) What is the variance of the project completion time?
a) Identify the critical path. b) What is the expected time to complete the project? c) What is the variance of the project completion time?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
Consider the following list of activities with time (in months)
Activity |
A |
B |
C |
D |
E |
F |
G |
H |
Immediate Predecessor |
----- |
----- |
A |
A,B |
A,B |
C |
D,F |
E,G |
Activity |
Optimistic |
Most Probable |
Pessimistic |
A |
3.5 |
4.0 |
4.5 |
B |
2.0 |
3.0 |
7.0 |
C |
6.5 |
7.5 |
10.0 |
D |
5.0 |
5.5 |
6.0 |
E |
5.0 |
6.5 |
8.0 |
F |
8.0 |
9.5 |
11 |
G |
6.0 |
7.0 |
9.5 |
H |
4.0 |
5.0 |
6.0 |
a) Identify the critical path.
b) What is the expected time to complete the project?
c) What is the variance of the project completion time?
d) What is the probability of completing in 32 months?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 6 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.