A public works project has an initial cost of P1 000 000, benefits with a present worth of P 1 500 000, and disbenefits worth of P 400 000. What is the benefit cost ratio? Answer:
Q: Should benefit and cost estimates be adjusted for the greater influences and impacts of inflation,…
A: The Central Artery/Tunnel Project was the largest and most difficult transportation project in…
Q: A large sewer system will cost P180,000 annually. There will be favorable consequence to the general…
A: * SOLUTION :- * Given that , Annual cost = P180000 Annual benifits = P520000 Annual disbenifits =…
Q: Locations under consideration for a border patrol station have their costs estimated by the federal…
A: We are going to use incremental benefit cost ratio to answer this question.
Q: Determine which of the following alternatives is the most efficient and which is the most profitable…
A: Given information about the 4 projects Where interest rate=5% per year Project Construction cost…
Q: QUESTION NO.13 Two relatively inexpensive alternatives are available to reduce potential earthquake…
A: Given: Interest rate=8% Study period=20 years
Q: Which of the following would be considered noneconomic factors in deciding which type of power plant…
A: The economic factor is those which have a monetary/financial value attached to them, whereas…
Q: Consider four alternatives A, B, C, and D with their respective annual benefits, disbenefits, costs…
A: B = Benefit -Disbenefits C = Costs -Savings There are two criteria. 1) Absolute criteria (B-C) = We…
Q: The Ecology Group wishes to purchase a piece of equipment for recycling of various metals. Machine 1…
A: Otherwise called break-even amount, break-even of units is where the business hopes to create…
Q: The following data is provided for a PPP project. To the People To the Government $1.8 million now…
A: Given; Benefits= $95000 per year Cost= $1.8 million now and $200000 every 3 year Disbenefit= $35000…
Q: Required information The following data is provided for a PPP project. To the People To the…
A: In financial economics, the ratio of modified B/C takes the maintenance and project operating costs…
Q: A professional photographer who specializes in wedding-related activities paid $50,000 for equipment…
A: Given the equipment cost = $50000 Salvage value, S = $2000 Years = 5 Per day cost = $80 Receives…
Q: For each of the following problems, (a) draw the cash flow diagram; (b) present clean and clear…
A: Projects BEF Cent First Cost 2,00,000 4,00,000 Operating Cost Per year 80,000 1,20,000…
Q: A state is planning to construct a stretch of highway extending to 60 Kilometer. The state signed a…
A: Cost/km = 1,000,000 total km of highway. = 60km Number of cars using highway = 500,000 and increased…
Q: A municipal landfill and incineration facility is planned. (a) Name at least three benefits, three…
A: Environmental economics: It refers to the policies which are being made by the government due to…
Q: QUESTION 1 A local goverment is considering promoting tourism in the city. It will cost $5,000 to…
A: a) A. The project is justifiable based on the benefit-cost analysis.
Q: Locations under consideration for a border patrol station have their costs estimated by the federal…
A: The cost-benefit ratio is an important factor that determines the investment and its revenue over…
Q: Use AW method to calculate the benefit/cost ratio at i = 6% for a new library. The first cost is…
A: Economics is the analysis of how individuals and society determine, with or without the benefit of…
Q: A benefit-cost ratio greater than one implies that the benefits outweigh the costs which makes the…
A: Answer to the question is as follows:
Q: What is the Benefit/cost ratio of a project if the PW benefits is equal to $100,000 and the PW costs…
A: Benefit-cost ratio:- In a cost-benefit analysis, a benefit-cost ratio is used to summarize the…
Q: A financial services consulting company bought an office building for $900,000. The company has 10…
A:
Q: The following estimates (in $1000 units) have been developed for a security system upgrade at…
A: Benefit cost ratio shows the relation among relative cost and the benefit or advantage of the…
Q: Galaxy Satellite Co. is attempting to select the best group of independent projects competing for…
A: Here we have calculated the NPV of every project.
Q: Which of the following statements is not one of the four fundamental principles of engineering…
A: Economic engineering is used to explain the distribution of income in banking and financial sectors,…
Q: From the PW, AW, and FW values shown, the conventional B/C ratio is closest to: Ка) 1. 27 (b) 1. 33…
A: B/C analysis i.e. benefit-cost analysis gives the ratio of benefits and costs in the same period. It…
Q: 1. If all individual B/C ratios of MEAS are less than 1.00, then the preferred option is to “Do…
A: B/C ratio is used for benefit and cost analysis for the given projects. Under long life span…
Q: For each of the following problems, (a) draw the cash flow diagram; (b) present clean and clear…
A: Projects BEF Cent First Cost 2,00,000 4,00,000 Operating Cost Per year 80,000 1,20,000…
Q: The Adams Construction Company is bidding on a project to install a large flood drainage culvert…
A: Cash earned in the long run isn't really valued much as today's comparable value is present worth of…
Q: nas the largest should be chosen? emental B-C fatio (based 1 dilfferences between altermatives)?…
A: A) Benifit Cost Ratio = PW benifits expected from project / PW of cost of a project (PW = present…
Q: The benefit-cost ratio of a project represents its time-valued benefit per unit investment (first…
A: In economics, when people invest their money, they make different types of analyses to analyze the…
Q: Calculate the modified B/C ratio for the followin Initial Cost 600,000 125,000 Annual Benefits…
A: The formula used to solve this equation is given below: PW = (Annual benefits - Annual O&M…
Q: Your employer is trying to select from a list of possible capital projects. The projects, along with…
A: * ANSWER:-
Q: The general city population is set to experience a benefit expressed in present worth of $35,500,000…
A: In the mentioned question we have been asked about the benefit-cost ratio of the project.
Q: he benefits associated with a nuclear power plant cooling water filtration project located on the…
A: Answer in step 2.
Q: the factors that affect the decision making in engineering projects are economic factors only Select…
A: Economic decision-making refers to the method of executing business decisions including money. All…
Q: If the present worth of costs exceeds that of the benefits, PW for the project is: Select one: a.…
A: Present worth of a project is its present value. Benefits are the profits received from an…
Q: Which is true? Prevention costs are $116,000 Appraisal costs total $72.000 Intenal failure costs…
A: Economics is a branch of social science that describes and analyzes the behaviors and decisions…
Q: yst, list
A: The use of the compensation principle in cost-benefit analysis as a means of separation of the…
Q: 4. (Chapter 10) A town in northern Colorado is planning on investing in a water purification system.…
A: A cash flow diagram is a monetary instrument used to address the sources of income related with a…
Q: The city of Oakmont is interested in developing some lake front property into a sports park (picnic…
A: Answer - Given in the question - Total investment = $3 million return = $500,000 per year Interest…
Q: MKBIC Systems is evaluating four projects A, B, C and D that have risks associated with the…
A: To find the best project we will add all the events of prob. Project EUAW = EUAW * Prob. Project A…
Q: A library shelving system has a first cost of $24,000 and a useful life of 9 years. The annual…
A: INTRODUCTION: BENEFIT TO COST RATIO: The benefit to cost ratio shows the connection among the fee…
Q: Blue Whale Moving and Storage recently purchased a warehouse building in Santiago. The manager has…
A: Given, Capacity = 4000-pound Electricforklift P = $−30,000 n = 12 years AOC =$−1000 per year; S =…
Q: Project informatio Fyped Answers only In the table below presented the data on the investment in the…
A: Answer
Q: A construction company has to sell at least X1 from one type of equipment(E1) and can be sold…
A: Given Total Working Hours = 960 hours E1 requires 3 hours of workmanship E2 requires 2 hours of…
Q: Initial Cost: ($300,000) The Study Period: 15 years Salvage (Market) Value of the Project: 12% of…
A: Given: Cost = $300,000 Total years = 15 Salvage value = 12% of cost Operating cost in first year =…
Q: Q)1.The benefit-cost ratio of a project represents its time-valued benefit per unit investment…
A: A benefit-cost analysis is one of the financial analysis tool to be used by the market participants…
Q: Select the BEST cost and benefit analysis technique if the time to obtain the profit is long while…
A: In the investment market, there are various methods to make an economic analysis of a specfiic…
Trending now
This is a popular solution!
Learn your way
Includes step-by-step video
Step by step
Solved in 2 steps
- A public work project has an initial cost of P50,000,000, benefits with a present worth of P75,000,000 and disbenefits with a present worth of P15,000,000. (a) what is the benefit-cost ratio? (b) what is the excess of benefits over costs?The Cash flow diagram for any project represents summary of benefits and costs. Select one: O True FalseWhy are benefit cost ratios inappropriate for evaluating alternative projects?
- A civil engineer has 2 alternative designs for a house. a. Design 1 calls for a workforce consisting of 5 men each costing P400/day. This design will be finished in 4 months. b. Design 2 calls for a workforce consisting of 10 men each costing P370/day and is expected to be finished in 3 months. In addition, there will be a project engineer who will supervise the work and will be paid P800/day. Disregarding material cost, how much is the total salary expenses for Design 1 and for Design 2? Assume that there are 24 working days in a month.Using an Engineering Economics FormulaList the four principles of engineering economics?
- Answer the c and d optionsN5 The following data is provided for a PPP project. To the People To the Government Benefits $130,000 per year beginning now Cost $1.8 million now and $200,000 every 3 years Disbenefits $45,000 per year Savings $90,000 per year Calculate the conventional benefit/cost ratios using an interest rate of 6% per year and an infinite project period.SITUATION3: Under the data collected from the office of Department of Transportation and DPWH over the last 5 years indicate that for each fatality, there are 40 non-fatal injury accidents ($1500 present cost each) and 300 property damage accidents ($2000 present cost each). What is the breakeven value of statistical Me (VSL) needed to justify a highway project if i is 8%? The death rate on a particular three-lane road is 8 per 100 million vehicle-miles. Adding a lane would reduce this to 5 per million, and other accidents would cost $1.5M per mile to build, and annual maintenance would be 3% of the first cost. Assume that the lane would last 40 years. The road carries 10000 vehicle per day. Use reduction factor of 3/8 for all accidents. (Non-CE students no need to answer this item).
- Describe the Fundamental Principles in Engineering Economics?Match the concepts in Column A to the definitions in Column BA certain masonry dam requires 500,000 cu.m. of gravel for its construction. The contractor found two possible sources for the gravel with the following data: Source A Source B 1.0 km Average distance, gravel pit to dam 4.0 km site Gravel cost/cu.m. at pit Purchase price of pit Road construction necessary Overburden to be removed at P50.00/cu.m. Hauling cost per cu.m. per km P415.00 ------- P800,000.00 P450,000.00 None 80,000 cu.m. P7.00 P7.00 Which of the two sites will give lesser cost?