a. The profit using Operation 1 is $ 4,237 per day. (Round to the nearest dollar.) The profit using Operation 2 is $ per day. (Round to the nearest dollar.) CO
Q: Explain control Analysis Control , ABC, VED ,FSN in terms of Production Management.
A: ABC ANALYSIS: ABC (Always better control) analysis is used to exercise effective control over the…
Q: et, timeline, and goal objectives, according to a recent IBM survey of 585 managers and developers…
A: More and more mobile applications are becoming huge successes, as we can see. More businesses that…
Q: How is the organisation of Sizanani Community funded?
A: Sizanani's response to the community's concerns for OVC is thorough. The program aims to provide…
Q: ABC Inc produces a product known as product A that is made up of a number of different components.…
A: Onhand Lead time (weeks) Schedule receipt Lot criteria A 1 25 B 30 3 25 C 40 2…
Q: Which of the following consists of real-time collaborative technology capabilities that enable…
A: In order to achieve supply chain excellence, there are four enablers. These enablers are capable…
Q: Consider the following LP problem: Maximum utility: 8x + 9y 4x + 3y 0 1. What is the optimal…
A: Given data is Objective function: Max Z=8x+9y Subject to constraints: 1.) 4x+3y<1502.)…
Q: a. Using these data, set up a c-chart with z = 3. b. Suppose that the next five samples had 15, 18,…
A: Control charts are also known as process-behaviour charts. It is a statistical process that helps in…
Q: The project network along with normal and crash data are provided below. Crash the project network…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Assume that each unit demanded of a company's product generates 66 USD in revenue and that each unit…
A: Profit or loss can be calculated by identifying the difference between total revenue and total…
Q: which one would be the optimal production plan for part b?
A: As indicated in Part (A): Decision Variables- P1 - Units of PT-100 made in Phillippines P2 -…
Q: (c) If Cabinetmaker 1 has additional hours available, would the optimal solution change? Explain. O…
A: Decision Variables: Suppose-O1 & C1 be the % of oak and cherry respectively by cabinetmaker…
Q: A local supermarket wants to determine how many cashier stations should be open to accommodate…
A: Observation Cashier Idle 1 3 2 0 3 1 4 4 5 2 6 0 7 2 8 2 9 0 10 3 11 3 12 1…
Q: A linear programming computer package is needed. The Westchester Chamber of Commerce periodically…
A: Given data is Constraints/Advertisement Television Radio Online Audience per ad 200,000 36,000…
Q: Café Michigan's manager, Gary Stark, suspects that demand for mocha latte coffees depends on the…
A: Formulae used: Linear regression forecast: Y= a+bxwhere,b= slope of the line a= Value of Ywhere…
Q: A linear programming computer package is needed. The Westchester Chamber of Commerce periodically…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: The Manvi Motors of Malaysia produces cars under an agreement with Suzuki of Japan and trucks under…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Gamers Company develops gaming software. Software programmers are paid $32 per hour for…
A: Software programmera paid rate(S) = $32 Overtime(O) = $16 Overtime hour(H) = 7 Productive hour(P) =…
Q: Cachora Dynamics Corp (CDC) has designed a new integrated circuit that will allow it to enter, if it…
A: Two decision alternatives: Sell rights, Build computers Two states of nature: Demand will be low or…
Q: An engineering plant has developed the accompanying supply, demand, cost and inventory data. The…
A: Find the given details below: Given details: Period 1 2 3 Demand 650 700 900 Regular time…
Q: 10. A manufacturer of lawn care equipment has introduced a new product. The anticipated demand is…
A: Optimal service level is a service level which is calculated by following formula Optimal service…
Q: Draw BOTH the arrow and node networks for the project given in the table. Activity IPA H C, D I D J…
A: The path with the longest duration is the critical path.
Q: A business wants to decide whether to launch a new product. If the product is launched there are two…
A: Decision tree helps in taking the right decision which can reduce costs and increase profits.
Q: The function whose main link with the supply management function lies within the development of…
A: Digital and automated coordination of supply chain components has fast replaced traditional supply…
Q: 2. Solve the LP using isocost method. Min Z = 2x + y s.t. x + y ≥5 2x + 6y ≥ 18 3x - y ≥ 3 x-2y ≤4…
A: Linear Programming Problems (LPP): To find the optimal answer to a mathematical model, linear…
Q: O A.2 B. 3 G. 2 C, 1 D. 3 H. 5 E, 4 F. 3 I, 3 C Given the diagram above, please answer the…
A: Note: - As we can answer up to three subparts, we will answer the first three (1, 2, and 3) here. If…
Q: If an assembly line with 11 tasks has a cycle time of 40 seconds per unit and the total task time is…
A: Cycle time is the time which worker actually spend in producing the item or providing the service to…
Q: Wolfgang Kersten Mfg. intends to increase capacity through the addition of new equipment. Two…
A: For the proposal X Fixed cost(FC)= 150,000 Variable cost(VC) = 120 For the…
Q: 18. You're a new hire in operations of a large laundry soap product firm. Which of the following can…
A: Inventory turnover refers to the ratio of cost of goods sold to the average inventory level
Q: Company Ajax has the following information from its financial statements in 2021. The annual sales…
A: Account receivable is the amount that receivable from outstanding at the end of the each business…
Q: Non-binding constraints have values that have not met their extreme value. O True O False
A: Non Binding Constraints: A constraint in linear programming is considered to be binding, if any…
Q: Find the assignment which minimizes total cost of the project. Each contractor has to be assigned…
A: An assignment problem is a technique to find the combinations of the optimal solution to the…
Q: A retail catalog operation employs a bank of six telephone operators who process orders using…
A:
Q: Consider the following linear programming formulation. Maximize z = 10x₁ + 20x₂ subject to 2.x₂ +…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: - Planning Technical Activities Please explain each of the content of Production Plan The production…
A: Production Plan:- The production plan contains a description of what needs to happen for the company…
Q: Which of these are key attributes of a project? Choose two. Answer instructions It is…
A: A Project can be defined as a series of tasks that are needed to be accomplished to reach a…
Q: The term for safety time added to chains other than the critical chain is: Feeding buffer, first…
A: Feeding Buffer: It is a safety added to the places where chains of tasks which are non critical…
Q: A company is planning to manufacture snowboards. The fixed costs are $128 per day and the total…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: 5. If the business strategy is to offer innovative products for consumer care, what operations…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Zan Azlett and Angela Zesiger have joined forces to start A&Z Lettuce Products, a processor of…
A: For the manual process Fixed cost(F) = 37,500 Variable cost(V) = 1.60 Price(P) = 2.50 Contribution…
Q: Direction: Solve the LP models using Graphical Solution. A dietitian has been asked by the athletic…
A: Linear programming is a mathematical technique that is also used in operations management…
Q: The manager of travel agency has been using a seasonally adjusted forecast to predict demand for…
A: MAD is the proportion between absolute errors and the number of periods. MAPE is the average value…
Q: Explain this: Goal 6: Clean Water and Sanitation. Water scarcity affects more than 40 percent of…
A: The Sustainable Development Goals often called SDG can be stated as the blueprint to obtain the…
Q: Calculate the inventory carrying cost if weekly demand is 150 units, the value of the item is $70…
A: Inventory carrying cost identify the all unsold expense of the company. Weekly demand = 150 units…
Q: Draw a diagram by showing factories, warehouses, and connecting arcs. Define variables, write the…
A: The transportation model is used to calculate the minimum cost of the route by selecting different…
Q: 1. From the following table, draw the precedence network, calculations, and complete the table…
A: Precedence Network is said to be the graphical presentation of all the activities that are…
Q: (5000 S) Assume that the initial forecast for February is 30.0 (in $ thousands) and the initial…
A: Ft = alpha*actual of previous period +(1-alpha)*previous forecast trend = beta*(Ft of same - Ft of…
Q: ght increase EVA quickl
A: Entrepreneurs seeking a way to gauge the effectiveness of their company frequently look to their…
Q: Which is the most challenging dimension in terms of operations strategy
A: To be determined: The most challenging dimension in terms of operations strategy. Introduction: The…
Q: What are the basic issues that you can address to them in order to reduce or avoid customer…
A: Customer complaints are a huge concern & critical part of running a business & must be…
Q: Daniel is planning to earn money over the summer mowing lawns in the neighborhood to buy a scooter.…
A: Given: fixed cost 2200 SP 19.1 variable cost 2.7
Please answer all with each process, Thank you!
Step by step
Solved in 4 steps
- For the production of part R-193, two operations are being considered. The capital investment associated with each operation is identical. Operation 1 produces 2,100 parts per hour. After each hour, the tooling must be adjusted by the machine operator. This adjustment takes 15 minutes. The machine operator for Operation 1 is paid $24 per hour (this includes fringe benefits). Operation 2 produces 2,350 parts per hour, but the tooling needs to be adjusted by the operator only once every two hours. This adjustment takes 45 minutes. The machine operator for Operation 2 is paid $13 per hour (this includes fringe benefits). Assume an 8-hour workday. Further assume that all parts produced can be sold for $0.35 each. a. Should Operation 1 or Operation 2 be recommended? b. What is the basic tradeoff in this problem?A recurring maintenance job in a factory is being done by a three-man crew. Due to the nature of the job and space limitations, it was observed that two of the men were idle 37% of the time; one of the men was also idle an additional of the time, and at any given time only one man was required. The men were each paid P24.00 per hour. Each time the job was performed a set of tools and equipment with a value equivalent to P36.00 per hour was used. If the three-men crew could complete the work in 5 hours, which crew size would be the most economicalA startup company is considering making a part by injection molding. The part is moderately complex and the volume of the part is about 10 cubic centimeters. Assume that the part is designed for injection molding and can be made with a two part mold. The company needs to make 250,000 parts made from ABS plastic. Once the mold is made it will take a worker 1 minute to make one part using the injection molding machine. The company will use contract manufacturing to produce the parts. Estimate the cost per part and explain how you came up with the number. (If you are stuck look at the Contract Manufacturing Cost per Unit section. Also keep in mind that there is no exact right answer, the goal is to come up with a reasonable estimate.) Contract Manufacturing Cost per Unit: It’s not uncommon to hire another company to perform some or all the manufacturing for a product. To estimate the cost use ((Cost of Parts and Materials) + (man hours) × $40)/.75
- A process has seven elements composed of combination of worker and machine. Elements A, B, D, and F are worker-controlled while elements C and E are machine controlled. Element G is a worker-controlled irregular element performed every five cycles Machines are idle during elements A, D, and G. Two units are produced every cycle. Below are the observed time (in minutes) and performance rating of each element. Work Element Observed Time (in minutes) Performance Rating A 0.75 115% B 1.20 120% C 1.40 N.A. D 1.05 90% E 1.25 N.A. F 1.20 105% G 1.60 85% Worker's allowance is 20% a) Determine Normal Time . Answer in 4 decimal placesb) What is the standard time? Round up answer in 2 decimal places.c) If the worker's performance during actual production is 125% on all manual elements for seven hours worked on an eight-hour shift, how many units will be produced? Round up answer in integer value.d) Determine the worker's efficiency (in percentage). Answer in 2 decimal placesABC Manufacturing is evaluating the desirability of implementing process improvements and is seeking your help in determining whether it should proceed with the proposed improvements. One area of focus is how the improvements will affect processing time (manufacturing cycle time efficiency). Estimated activities and associated times for these activities under both the current process and after process improvements are as follows: Process Activity Current Process After Process Improvements Wait time 4 hours 1 hour Inspection 40 minutes 5 minutes Moving 80 minutes 20 minutes Processing (manufacturing) 2 hours 75 minutes Required: 1. Determine the manufacturing (production) lead time (in minutes) for each of the two decision alternatives. 2. Determine the manufacturing cycle efficiency (MCE) for each decision alternative.A company that operated 10 hours a day manufactures two products on three sequential processes. The following table summarizes the data for the problem: Which of the following is the most appropriate representation for variables x and y for the given situation? a.) x is the # of units of Product 1 to be procured; y is the # of units of Product 2 to be procured. b.) x is the # of units of Product 1 to be produced; y is the # of units of Product 2 to be produced. c.) x is the # of units of Product 1 to be stored; y is the # of units of Product 2 to be stored d.) x is the # of units of Product 1 to be delivered; y is the # of units of Product 2 to be delivered.
- A loan processing operation at a local bank processes an average of 7 loans per day. The operation has a design capacity of 10 loans per day and an effective capacity of 8 loans per day. What is the utilization of the processing operation? Select one: a. 100.0% b. 87.5% c. 70.0% d. 80.0% Warranty expense, the cost that a business incurs for the repair or replacement of goods that has sold, is an example of which of the following? Select one: a. Internal failure cost b. Appraisal cost c. Prevention cost d. External failure costConsider the two stage process depicted below: Stage 1 Stage 2 The first stage of the process requires 6 minutes of work for a single employee to complete. There are 8 employees working at this process stage - each for a total of 5 hours per day. This stage includes an inspection where 14% of WIP is rejected and exits the system after completing Stage 1. The remaining WIP continues to Stage 2 of the process. At this stage, 7 employees work - each for a total of 4 hours per day. WIP is processed at Stage 2 in 10 minutes by a single employee. What is the daily process capacity? Round your answer to the nearest first decimal place. Your Answer: AnswerConsider the following four-step assembly operation with quality problems: The first resource has a processing time of 5 minutes per unit and one employee doing the operation. The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 80% of all products have to be scrapped after this step. Two workers are staffed for the third resource. No quality problems occur at this resource and the processing time is 20 minutes per unit. At the fourth and final resource, one operator handles the product. No quality problems exist at this step and the processing time is 12 minutes per unit. For every unit of demand, how many units have to flow through the second step in the process?
- Consider the following four-step assembly operation with quality problems: The first resource has a processing time of 5 minutes per unit and one employee doing the operation. The second resource has a processing time of 4 minutes per unit. It also has one employee doing the operation. However, this is a very delicate task and 80% of all products have to be scrapped after this step. Two workers are staffed for the third resource. No quality problems occur at this resource and the processing time is 20 minutes per unit. At the fourth and final resource, one operator handles the product. No quality problems exist at this step and the processing time is 12 minutes per unit. Where in the process is the bottleneck?1) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes, Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C₁=40 TL/Hour, cost of a machine is C₂-200 TL/Hour. What is the cost per unit of production if optimum number of machines is assigned to the operator? (Note: Times are given in minutes and costs are per hour) a) 231 TL/unit b) 6930 TL/unit c) 115.5 TL/unit d) 240 TL/unit e) 132 TL/unit 2) An operator is used for loading and unloading of parts to automated machines. Loading time is 1 minute; unloading time is 2 minutes, machining time is 30 minutes; Operator travel time between the machines including the inspection time is 4 minutes. Cost of operator is C1=40 TL/Hour; cost of a machine is C₂=200 TL/Hour. How many machines (integer number) should be assigned to the operator so that the total operator and machine costs…Two vital stages in a production process are assembly I and assembly II. The unit load for the assembly I stage is 7.0 ( 50% higher for high skill) minutes, while it is 10.0 (30 % higher for high skill) minutes for assembly II. There are 7 employees working in assembly I and 8 employees working in assembly II. 65% of low skill labor and 35% of high skill labor are required at both stages. . On average 18% of the operating time is wasted, what's the theoretical unit load for Assembly II? answer is 9.06 please explain