Activity A B C D E F G H Time (Weeks) a 4 5 1 7 12 9 4 1 m 4 11 7 8 15 12 7 4 b 10 11 13 9 18 15 10 7 Precedence A A C,D с B,F E,G a. Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram
Q: a What is the expected time for activity 1? b. What is the variance for activity 1? C Based on the…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: List two properties that a heuristic should have if it is to be useful in a production system.
A: A heuristic is a problem-solving strategy or technique that is used when a systematic or algorithmic…
Q: Below you will find the LP code for the Dakota furniture company making tables, desks, and chairs…
A: answer) The given linear programming problem is as follows: Given variables are as follows: X1 =…
Q: Which specifics need your focus? For what reasons is it important for a firm to ensure that all…
A: The business conducts everyday operations so that it is properly ensured that productivity and…
Q: Find the value of X in the following Flow Shop data consisting of 5 jobs which are to be processed…
A: Jobs M1 M2 A 3 8 B 12 9 C 11 1 D 6 4 E 10 12
Q: Given the project network information, complete the forward and backward pass. What is the…
A: Here, for each activity, I have been given the duration data, predecessor data, and variance data, I…
Q: A furniture company is producing two types of furniture. Product A requires 8 board feet of wood and…
A: Types of furniture = Product A and B For Product A: Board feet required = 8 feet Wicker required = 2…
Q: Refer to the Process Flow Diagram for Making a Shirt. Consider only the task of preparing the front,…
A: Process Flow Diagram for Making a Shirt:
Q: Operation management The following set of six jobs is to be processed through two work centers at…
A: answer) (1). The table below shows the given data. Job Printing (hrs) binding(hrs) A 10 5 B…
Q: Please enumerate and briefly define each of the five methods of risk control.
A: The term "risk control" refers to the processes by which businesses assess their vulnerability to…
Q: Case Study 2: Quality Management Your line manager has become increasingly concerned about the…
A: *As per guidline first three parts are answerable please repost the remaining parts. Mean x =…
Q: How do overlapping and disjoint constraints differ?
A: Below is the differences between overlapping and disjoint constraints.
Q: Sales activity variance Market share variance Industry volume variance
A: Actual Units Sold = 422,000 Actual Market = 2,960,000 Budgeted Units = 458,500 Budgeted Selling…
Q: True or False: Engineering Technologist study the design process because 85% of problem of new…
A: Product design is defined as a process that results in the creation of a new product or improvement…
Q: Macomb Inc. used Excel to run a least-squares regression analysis on the production cost data…
A: Coefficients Standard Error T Stat P-Value Intercept 174,980 61,580 2.84 0.021 Production…
Q: The president of Hill Enterprises, Terri Hill, projects the firm's aggregate demand requirements…
A: Cost is the amount that is incurred by the company on producing goods and services. The cost of…
Q: Apple Self-Driving Cars Want to Rid of Human Interaction, Plan for 2025 Launch - Bloomberg Apple is…
A: Apple, the technology behemoth recognised for its creativity and design, is purportedly working on…
Q: What are the key elements of a legally enforceable contract?
A: A contract is a formal, written agreement between at least two parties outlining their respective…
Q: How can businesses effectively utilize the push-pull strategy in their supply chain management to…
A: Effective supply chain management is crucial for any firm to achieve optimal operating efficiency,…
Q: Salad Daze maintains an inventory of produce worth $380. Its total bill for produce over the course…
A: Inventory maintained = $380Total yearly bill = $71,000Working days in a year = 365 days
Q: a. what is the critical path? b. how many weeks will it take to complete the project? c. how much…
A: A network diagram shows the link of each task with the duration taken by each activity with respect…
Q: Ideas and thoughts about design should be discussed in detail. What is the difference between a…
A: Design is a fundamental aspect of our lives, from the products we use to the spaces we inhabit. It…
Q: Paul Bergey is in charge of loading cargo ships for International Cargo Company (ICC) at the port in…
A: Linear Programming is a mathematical and statistical tool that is used in operations management to…
Q: Assumes employee B gets daily wage of $400. By May 1, 2021, He has worked for his company for 12…
A: Labors are essential elements for any organization as they carry out the tasks of different business…
Q: a. Select the Run chart for the above data. Use five-minute intervals (i.e., count the calls…
A: A run chart shows how well a process performs within specifications. If there is any variation in…
Q: ormation about the requirements for production of legs for a chair. Develop the MRP schedule for the…
A: Material requirements planning is the method of managing the inventory, which helps to create the…
Q: How can startbucks company use multiple regression? Please provide an example and identify dependent…
A: Here, I would state how a company like Starbucks could use multiple regression, I would also include…
Q: Prepare a graph of the monthly forecasts and average forecast demand for Chicago Paint Corp., a…
A: Forecasting is one of the techniques to know some future figures on the basis of past data. This…
Q: What is the expected average number of snowplows in the garage (waiting for repair and being…
A: Arrival rate is Poisson distribution and service rate is exponential. Arrival rate λ = 5 per…
Q: You'll read about "Adhesion Contracts" which are a type of contracts that are challenged more often…
A: Business ethics involves a wide range of issues, including corporate social responsibility,…
Q: Embassy Motorcycles (EM) manufactures two lightweight motorcycles designed for easy handling and…
A: LPP using graphical model is developing the graph for identifying the cornor points of feasible…
Q: Thomas has four assignments due in class tomorrow, and his class times are as follows. Class…
A: Scheduling refers to planning and organizing how to allocate the resources and time to complete a…
Q: Eight activities A,B,C,D,E,F,G and H with their preceeding activities and duration times are given…
A: A network diagram also known as a project network, is a graphical representation of the sequence of…
Q: Jantel Mitchell's bakery prepares all its cakes between 4 A.M.and 6 A.M.so they will be fresh when…
A: Optimal stocking level is determined with following formula: Optimal stocking level = Mean demand…
Q: Smith Productions manufactures its hand-tools in-house. Maintenance and repair costs are increasing…
A: Here, the annual fixed cost is 500000, and the variable cost per part is 12, the annual fixed cost…
Q: Please show work so I can understand it. Given this information: •Expected demand during lead time =…
A: Given, Expected demand during lead time = 800 units The standard deviation of lead time demand = 40…
Q: What are the most important benefits of managing projects? What would it be like without project…
A: Here, for this Q, first, I would discuss the most important benefits of managing projects, and what…
Q: Develop an aggregate production schedule for the year using a constant workforce. For simplicity,…
A: An aggregate production plan is the operation management method that helps determine the…
Q: Describe the profit potential for the following industry: Low entry barriers, suppliers and buyers…
A: The question is based on Porter's five forces of the market: Power of suppliers Power of customers…
Q: Pepsi-Cola was incorporated in Delaware in 1919 and reincorporated in North Carolina in 1986.…
A: Find the Given details below: Stockouts: Pepsi Co Jamaica 8% in comparison to Pepsi Cola’s global…
Q: Explain how can firms use supply chain management to differentiate their products?
A: The process of creating, planning, executing, and overseeing the flow of products, services, and…
Q: A manufacturer's average WIP inventory for Part #762 is 882 parts. The workstation produces parts at…
A: (1) Given that: WIP Inventory 882 Work station parts 275 Remember the formula, Avg. WIP…
Q: 16. Complete the following schedule and then answer Problems 16 and 17. Period 3 45 On Hand 1 35 50…
A: Given details: Calculation methods: Ending inventory = Planned order receipts + ending inventory…
Q: A crew of mechanics at the Department of Transportation garage make minor repairs to snowplows…
A: Queuing theory is the study of waiting for lines/queues. This model helps to determine the length…
Q: Identify and discuss four distinct risks that negotiators face if they lack knowledge of the rules…
A: Negotiation is an important skill in both business and everyday life. However, a lack of…
Q: 40 - A hospital is evaluating whether to outsource or perform in-house a large set of blood and…
A:
Q: Wood County Hospital consumes 1,000 boxes of bandages per week. The price of bandages is $36 per…
A: The annual demand is 1000×52 The annual demand is 52000 The price per box is 36 The ordering cost…
Q: When conducting a study on business process reengineering in order to identify business processes…
A: When conducting study on business process reengineering in order to identify business processes that…
Q: Question 3 Singapore Airlines Cargo (SIA Cargo) operates a dedicated fleet of freighters as well as…
A: SIA Cargo is the cargo division of Singapore Airlines and operates a dedicated fleet of freighters…
Q: O D Depot C1 C2 C3 C4 C5 C6 Depot 0 8 12 5 9 8 15 C1 7 0 13 11 8 7 13 C2 4 11 0 6 15 4 14 C3 5 12 7…
A: Seeing at the table we know he has to go to 6 different stations for the deliveries so we will…
Operation management
Step by step
Solved in 5 steps with 7 images
- ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St FBy using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Bquetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?
- Due to complexity of the project, there is the need to use ‘network analysis’, what is it?How is Project Planning, Scheduling, and Controlling is managed by the OM manager?Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Immediate Predecessor(s) Activity ABCDEFG This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B A, D C E, F Time (days) 4 5 3 10 4 6 10
- O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4
- Project Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processEvaluate the below statement according to the project management terminologies and choose the correct answer: It is the process of making a forecast or precise approximation Choose... of time and cost associated with a work package or activity. Graphically describes a project consisting of well-defined Choose.. activities, the completion of which marks its end. One of the Perform Quantitative Risk Analysis process has a Choose.. Tools and Techniques. Useful for building accountability through assigning specific Choose.. tasks to team members. It is the standard format each path through the network must be continuous with no gaps, discontinuities, or dangling Choose... activities. Organizational Assets, Project Scope Statement, Cost Management Plan and Schedule Management Plan are inputs Choose.. of: Choose... Work Breakdown Structure Expert Judgment Bar chart Estimating A horizontal diagram format Plan Risk ManagementProject Managers must demonstrate (4) activities: Project planning: ◦Project scheduling:◦Project monitoring:Project reporting: Please pick one activity, define it in your words and give a specific example how you would demonstrate and achieve that activity.