ACTIVITY PREDECESSOR(S) (WEEKS) A 4. D. B. C,D E,F 2. AA
Q: Discuss the Projects without private counterparts?
A: The process of managing, organizing, and planning the efforts for achieving the goal of the project…
Q: An entrepreneur is starting a new business. The activi-ties and times required are given below:a.…
A: Formula:
Q: Organisations manage more and more projects as a result of global competition influenced by rapid…
A: Scrum is an agile development methodology employed in the event of code-supported associate degree…
Q: Describe what is meant by the pessimistic time in critical path method
A: It is a method based on the critical path and probabilistic time estimates. Activity times are…
Q: Prepare a schedule based on resources. There are only 3 resources available for each period.…
A: 1. Possible path Duration Maximum duration Critical path 1-2-7 = 2+6+2 = 10 No No 1-3-5-7 =…
Q: Compare and contrast the PM life cycle with the SDLC. Why is project management different from…
A: Project management life cycle - It is used to describe the whole journey of the project it starts…
Q: Organisations manage more and more projects as a result of global competition influenced by rapid…
A: Below is the solution;-
Q: Project monitoring and control involves activity tracking, identifying weaknesses and putting in…
A: Project management is described as a process or a means through which a project is driven from a…
Q: Organisations manage more and more projects as a result of global competition influenced by rapid…
A: Scrum methodology can be defined as the agile development methodology. Scrum is flexible and…
Q: Answer only question 2 1)List and explain the phases that mark the life of a project. 2) For…
A: Project management is usually accomplished in stages to further develop control and quality. This…
Q: c. What is the significance of project monitoring and control? What are the various dimensions of…
A: The project monitoring & control process seeks at tracking & checking the project and is…
Q: Explain why a project can have multiple critical paths. Give a brief example to illustrate your…
A: Below is the solution:-
Q: Mother and Carlene, my big sister, planned and booked a trip to Beijing, China. Three days before…
A: Travel management can be stated as the approach to a multitude of tasks such as understanding and…
Q: Hi, I am trying to apply for a Platform Manager position and Development Manager position relating…
A: Manager is a person who has the responsibility of managing something. It can be an organization, any…
Q: How can you identify project risks? (list 1 way) - What is a (risk transfer) response strategy? -…
A: The risks are the by- products of the success in business management.
Q: 1) The total time to complete this project is? 2) What is the critical path
A: The project network is the graphical representation of project tasks as well as their duration to…
Q: Give an example of a situation in which project management is needed.
A: Organization is a place where different tasks are done by many people to achieve some objective or…
Q: In what way does the position of a project manager resemble that of a general manager, including a…
A: Functional Organization: It revolves around what functions an organization needs to perform like…
Q: Using Airbnb as an organization, can you please help me with three different project objectives…
A: Airbnb: It is a vacational rental company , and tourism services It comes under hospitality…
Q: 2) For each project phase identified in 1(a) above, describe at least four (4) project…
A: Here we are discussing four project phases that mark the life of a project. Initiation phasePlanning…
Q: Which of these is NOT an example of a project? Select one: a. Developing a new vaccine to combat a…
A: Which of these is NOT an example of a project? Developing a new vaccine to combat a disease…
Q: The Chief Executive Officer of Dar Al Herfya (World of Handicrafts) spends her days contacting…
A: An entrepreneur is a person who starts a business by conceiving an innovative idea, bears all the…
Q: Prepare a list of the specific activities that need to be performed to achieve the project…
A: Many people involved in project management and project objectives face the same problem as…
Q: What is the critical path of this activity table?
A: The project network is the diagram that shows the order of completion of project network activities…
Q: 2- A project consists the activities shown bellow, all links are Finish to Start ( F-S) with Zero…
A: Given: Activity Immediate Predecessors Duration A - 4 B - 3 C A,B 6 D B 1 E D 7 F C 2…
Q: A PERSONAL CRUSADE The senior leaders of DM Bicycle Company filed into the conference room, their…
A: Mr. G's idea about CSR program is ethical, socially responsible and genuine. But the profit margin…
Q: The critical path is A-C-E-G-I-J. Activity G HIJ A B C D E Variance 0.25 0.15 0.25 0.69 | 2.25 0.69…
A: Given data is
Q: Demonstrate why a trained project manager is required for difficult tasks.
A: Project management is the management in which different kinds of skills and knowledge are required…
Q: You are the marketing manager of a cold drink company. The company has around 25 main distributors…
A: LETTER FROM THE MARKETING MANAGER OF THE COMPANY To The Distributors Cold Drinks Company Dear…
Q: A PERSONAL CRUSADE The senior leaders of DM Bicycle Company filed into the conference room, their…
A: Each company ought to be socially accountable because it makes profits from the society and in a way…
Q: Hilal prepares policies, rules and procedures to implement the project. Hilal's function can be…
A: Hilal prepares policies, rules and procedures to implement the project. Hilal's function can be…
Q: What is Project Closure?
A: Project closure is the last phase of the project management lifecycle. In this phase, all the…
Q: A PERSONAL CRUSADE The senior leaders of DM Bicycle Company filed into the conference room, their…
A: Some of the moral principles that might have driven man. G's call of part square measure universal…
Q: A PERSONAL CRUSADE The senior leaders of DM Bicycle Company filed into the conference room, their…
A: According to Carroll the corporate social responsibility pyramid includes four levels. From the…
Q: the HBR article by Antonio Nieto-Rodriguez and analyse the main qualities that leaders need to excel…
A: The main qualities that leaders need to excel in a project driven world are as follows, 1.…
Q: 7. A project has the following network and costs (1 in days, A H. Start C End E G Normal Crash…
A: All possible paths are 1) A-D-H 2) A-C-F-H 3) A-C-E-G 4) B-F-H 5) B-E-G
Q: Discuss International Project Management Standards, Compare and Contrast PMBOK and APM standard with…
A: Project management is the task of managing processes, methods, skills, knowledge, and experience to…
Q: Sumaia. In this situation who is the first person, Fatema has to report to?
A: Whistleblowing is the act of reporting any wrongful or unethical act by an employee within the…
Q: What strategy will you use as Project Manager to ensure that all stakeholders are informed of the…
A: The Project Manager is a key role in ensuring the success of a project. The Project Manager is…
Q: List down per paragraph 4 strategies to mitigate the major reasons why Project Companies Fail
A: A project becomes a failure when it does not deliver what was required within the agreed-upon budget…
Q: As project manager you have been asked to complete a project in the shortest time possible. Draw a…
A: Task Duration Predecerrors A 4 None B 8 None C 5 A D 11 B E 7 A,B F 10 C,E G 16 D H…
Q: Explain the different types of Project Management Skills? Elaborate the following with the help of…
A: Project management skills refers to the core abilities that are required to bring a project to its…
Hello, Can you help me? Please provide how to solve the problem, It's really a big help for me.
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 2 images
- Project Managers must demonstrate (4) activities: Project planning: ◦Project scheduling:◦Project monitoring:Project reporting: Please pick one activity, define it in your words and give a specific example how you would demonstrate and achieve that activity.O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,ces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St F
- Q1. Using a suitable example each, describe what the following project planning process activities involve: a. Establish project objective; b. Define scope; c. Create a Work Breakdown Structure (WBS); d. Estimate activity durations; e. Sequencing activities.a) Explain the purposes of a dummy activity in a network diagram. (b) Table 1 shows the activities of a project and their durations. Table 1Activity Preceding Activity Duration (Days)A – 9B – 3C A 8D A 2E A 3F C 2G C 6H C 1J B,D 4K F,J 1L E,H,G,K 2M E,H 3N L,M 4 i. Draw the project network.ii. Determine its critical path and completion time.iii. Calculate the total float for the non-critical chains. 2. a) Outline FOUR different types of stockholding casts. b) i) Explain the periodic review system of inventory control.ii) State TWO disadvantages of the periodic review system. c) Explain FOUR major functions of an office. d) A common trend in the office management in many large manufacturing organizations today is to set up an ‘organization and method’ (O&M) team, which is normally directly answerable to the Chief Executive Officer. Highlight FOUR responsibilities of such a team. 3. a) State FOUR objectives of maintenance in a manufacturing plant. b) Explain the purpose of the…Q1. Project Planning and Quality Management: a) Develop a comprehensive project plan that includes the scope, objectives, timeline, and resource requirements for the development and production of the product related to Central Cable Berhad (CCB). b) Identify key quality management principles that will be crucial in ensuring the product meets industry standards and customer expectations. c) Propose a quality control plan outlining methods, tools, and checkpoints to ensure the consistent quality of the electric wires.
- quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?Q1. Using a suitable example each, describe what the following project planningprocess activities involve:a. Establish project objective;b. Define scope;c. Create a Work Breakdown Structure (WBS);d. Estimate activity durations;e. Sequencing activities.(2) Cables By Us is bringing a new product on line to be manufactured in their current facility in existing space. The owners have identified 11 activities and their precedence relationships. (a) Draw the network diagram of this project (b) Calculate the project completion time (c) Identify the critical path Immediate Duration Activity Description Predecessar (weeks) A Develop product specifications Designmanufacturing process Source & purchase materials D None 4 B 3 Source & purchase tooling & equipment Receive &install tooling & equipment F 6 E D 14 Receive materials G Filot production run H E&F 2 Evaluate product design Evaluate process performance Wite documentation report Transition to manufacturing G 2 G J H&I 4 K J 2 AAB
- The prime objectives of project management are cost, time andA. ScheduleB. QualityC. Customer satisfactionD. Performance.Part 1: The 5 project management groups have wide industry application in modern day project management. By using practical examples of your choice, demonstrate the practical application of the project management processes in bringing a project to a successful end (Detailed response required, also acknowledge information sources). Part 2: A gantt chart is widely applied in project management as a project scheduling tool,whose format is in bar chart form. Critically examine a gantt chart as a project scheduling tool and practically demonstrate how it can also be used as a project planning and control technique (Detailed response required, also acknowledge information sources).You are the manager of a project to improve a billing processat your firm. Table 7.7 contains the data you will need toconduct a cost analysis of the project. Indirect costs are $1,600per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the ear-liest completion time of the project using “normal” timesand the minimum-cost schedule you derived in part (a)?