As a Project Leader, you have to organize the steps of the development of a new product: The first activity is to define detailed specifications before starting the prototype. In this phase, we will create a preliminary design, made by William and Louis, two engineers, in twenty-five days. Once the design is made, Louis and Peter (a new engineer) will determine the functional characteristics and specifications. They need for this task seven days. When the specifications are defined, we will create the prototype. The first operation to do is to construct the basic structure in 13 days, made by Peter and Susan, his assistant. At the same time, we have to design an electronic system, independent to the structure. For this task we will need John and he will spend 10 days. Once we finish both activities, we have to assembly the prototype. This task is for Peter and John and they will take two days. When the designs and prototype are made, we start the tests. The first test will be made by Mary, a Quality Department technician, in five days. William and Susan will work in the second test, and they will spend other five days. After these two test, John and Susan will make a simulation. For this new test, we need to work in the laboratory for twelve days. Finally, the product will be accepted (milestone). Once we know the project is valid, we must write the project report. To do this document, Robert, after the second test, writes a draft in two days. This preliminary document is the base for the final report, written by two assistants in two weeks. The report is corrected, and the final version is available in three weeks. With this report we can start the training program for all the employees. The responsible of this training are Susan and Mary. This activity can start when the report is corrected. The first session is for Top Management (we need only one day) and then, the rest of workers (in a week). Finally, the company must launch the new product. After the training program, Joseph, the Marketing Manager will develop the Marketing Plan in seven days. After this, Tom and George, the sellers, will study in fifteen days the specifications and the Marketing Plan to guarantee the success of the product in the market. At the same time we prepare the launch, Victor, the Production Manager, starts to organize the production. He says that in twenty-five days the first units will be available. Question: Draw the Project Timing with a Gantt Chart and a PERT or Network Diagram. What is the total project completion time?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

As a Project Leader, you have to organize the steps of the development of a new product:

The first activity is to define detailed specifications before starting the prototype. In this phase, we will create a preliminary design, made by William and Louis, two engineers, in twenty-five days.
Once the design is made, Louis and Peter (a new engineer) will determine the functional characteristics and specifications. They need for this task seven days.

When the specifications are defined, we will create the prototype. The first operation to do is to construct the basic structure in 13 days, made by Peter and Susan, his assistant. At the same time, we have to design an electronic system, independent to the structure. For this task we will need John and he will spend 10 days. Once we finish both activities, we have to assembly the prototype. This task is for Peter and John and they will take two days.

When the designs and prototype are made, we start the tests. The first test will be made by Mary, a Quality Department technician, in five days. William and Susan will work in the second test, and they will spend other five days. After these two test, John and Susan will make a simulation. For this new test, we need to work in the laboratory for twelve days. Finally, the product will be accepted (milestone).

Once we know the project is valid, we must write the project report. To do this document, Robert, after the second test, writes a draft in two days. This preliminary document is the base for the final report, written by two assistants in two weeks. The report is corrected, and the final version is available in three weeks.

With this report we can start the training program for all the employees. The responsible of this training are Susan and Mary. This activity can start when the report is corrected. The first session is for Top Management (we need only one day) and then, the rest of workers (in a week).

Finally, the company must launch the new product. After the training program, Joseph, the Marketing Manager will develop the Marketing Plan in seven days. After this, Tom and George, the sellers, will study in fifteen days the specifications and the Marketing Plan to guarantee the success of the product in the market.

At the same time we prepare the launch, Victor, the Production Manager, starts to organize the production. He says that in twenty-five days the first units will be available.

Question:

  1. Draw the Project Timing with a Gantt Chart and a PERT or Network Diagram. What is the total project completion time?

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.