Code A B C D E F G NT 12 16 9 9 20 8 3 CT 10 12 6 4 20 8 1 NC 50 70 45 80 30 50 20 CC 100 100 84 200 30 65 100 Prec. A A B, C C B, C D Please enter the information below. Do not include commas in your answer and enter percentages as decimal points. For example enter 1,402 as 1402 and 67.5% as 0.675. Do not include $ signs. Be sure to upload all your process notes and calculations for partial credit. What is the "all crash" project's duration? 22 What is the normal times project duration? 165 What is the total cost assuming the normal times? 883. What is the project's cost after the first crash? What is the project's cost after the second crash?
Code A B C D E F G NT 12 16 9 9 20 8 3 CT 10 12 6 4 20 8 1 NC 50 70 45 80 30 50 20 CC 100 100 84 200 30 65 100 Prec. A A B, C C B, C D Please enter the information below. Do not include commas in your answer and enter percentages as decimal points. For example enter 1,402 as 1402 and 67.5% as 0.675. Do not include $ signs. Be sure to upload all your process notes and calculations for partial credit. What is the "all crash" project's duration? 22 What is the normal times project duration? 165 What is the total cost assuming the normal times? 883. What is the project's cost after the first crash? What is the project's cost after the second crash?
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter14: Data Mining
Section14.2: Classification Methods
Problem 7P
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps with 3 images
Recommended textbooks for you
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,