Companies A, B, and C supply components to three plants (F, G, and H) via two crossdocking facilities (D and E). It costs $4 to ship from D regardless of final destination and $3 to ship to E regardless of supplier. Shipping to D from A, B, and C costs $3, $4, and $5, respectively, and shipping from E to F, G, and H costs $10, $9, and $8, respectively. Suppliers A, B, and C can provide 200, 300 and 500 units respectively and plants F, G, and H need 350, 450, and 200 units respectively. Crossdock facilities D andE can handle 600 and 700 units, respectively. Logistics Manager, Aretha Franklin, had previously used "Chain of Fools" as her supply chain consulting company, but now turns to you for some solid advice. Set up the solution in Excel and solve with Solver. What are total

Purchasing and Supply Chain Management
6th Edition
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
ChapterC: Cases
Section: Chapter Questions
Problem 5.1SC: Scenario 3 Ben Gibson, the purchasing manager at Coastal Products, was reviewing purchasing...
icon
Related questions
Question
Companies A, B, and C supply components to three plants (F, G,
and H) via two crossdocking facilities (D and E). It costs $4 to ship
from D regardless of final destination and $3 to ship to E
regardless of supplier. Shipping to D from A, B, and C costs $3, $4,
and $5, respectively, and shipping from E to F, G, and H costs $10,
$9, and $8, respectively. Suppliers A, B, and C can provide 200,
300 and 500 units respectively and plants F, G, and H need 350,
450, and 200 units respectively. Crossdock facilities D and E can
handle 600 and 700 units, respectively. Logistics Manager, Aretha
Franklin, had previously used "Chain of Fools" as her supply chain
consulting company, but now turns to you for some solid advice.
Set up the solution in Excel and solve with Solver. What are total
costs?
Transcribed Image Text:Companies A, B, and C supply components to three plants (F, G, and H) via two crossdocking facilities (D and E). It costs $4 to ship from D regardless of final destination and $3 to ship to E regardless of supplier. Shipping to D from A, B, and C costs $3, $4, and $5, respectively, and shipping from E to F, G, and H costs $10, $9, and $8, respectively. Suppliers A, B, and C can provide 200, 300 and 500 units respectively and plants F, G, and H need 350, 450, and 200 units respectively. Crossdock facilities D and E can handle 600 and 700 units, respectively. Logistics Manager, Aretha Franklin, had previously used "Chain of Fools" as her supply chain consulting company, but now turns to you for some solid advice. Set up the solution in Excel and solve with Solver. What are total costs?
Set up the solution in Excel and solve with Solver. What are total
costs?
O $8,800
O $10,300
$9,300
O $9,800
Transcribed Image Text:Set up the solution in Excel and solve with Solver. What are total costs? O $8,800 O $10,300 $9,300 O $9,800
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 5 images

Blurred answer
Knowledge Booster
Optimization models
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,