Critical Path Scheduling Construct a Pert diagram for each of the two problems below (see scheduling practice problems in the ch 5 module or practice) Include Early Finish, Late Finish, Slack times and identify the critical path (both in the table and on the Pert chart). Please construct the Pert/Network diagram by hand. You can then submit a scanned copy of your filled in charts and pert diagrams. Please submit as one file via dropbox. 1. Activity Expected Time A 3 B 4 с 4 D 5 E 2 3 2 1 6 3 5 2 Activity A B с D E F G H I J G H I J K L ExpectedTime 4 6 2 4 3 4 2 3 1.5 3 Immediate Predecessors A A A с B, E C,D,E G,H A A B B B, C D, E F H G, I I K Immediate Early Predecessors Finish Early Late Finish Finish Late Finish Slack Slack Critical Path? Critical Path?

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
Critical Path Scheduling
Construct a Pert diagram for each of the two problems below (see scheduling practice problems in the ch 5 module
for practice)
- Include Early Finish, Late Finish, Slack times and identify the critical path (both in the table and on the Pert
chart). Please construct the Pert/Network diagram by hand. You can then submit a scanned copy of your filled in
charts and pert diagrams. Please submit as one file via dropbox.
1.
N
Activity
A
B
с
D
E
F
Activity Expected Time
A
B
с
D
G
H
I
J
E
F
G
H
I
J
K
L
3
4
2
3
3
4
4
5
2
3
ExpectedTime
4
6
2
1.5
3
2
1
6
3
5
2
Immediate Predecessors
--
A
A
A
A
B
B
B, C
D, E
F
H
G, I
с
Immediate
Early
Predecessors Finish
B, E
C,D,E
G₂H
I
K
Early Late
Finish Finish
Late
Finish
Slack
Slack
Critical
Path?
Critical
Path?
Transcribed Image Text:Critical Path Scheduling Construct a Pert diagram for each of the two problems below (see scheduling practice problems in the ch 5 module for practice) - Include Early Finish, Late Finish, Slack times and identify the critical path (both in the table and on the Pert chart). Please construct the Pert/Network diagram by hand. You can then submit a scanned copy of your filled in charts and pert diagrams. Please submit as one file via dropbox. 1. N Activity A B с D E F Activity Expected Time A B с D G H I J E F G H I J K L 3 4 2 3 3 4 4 5 2 3 ExpectedTime 4 6 2 1.5 3 2 1 6 3 5 2 Immediate Predecessors -- A A A A B B B, C D, E F H G, I с Immediate Early Predecessors Finish B, E C,D,E G₂H I K Early Late Finish Finish Late Finish Slack Slack Critical Path? Critical Path?
Expert Solution
steps

Step by step

Solved in 3 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.