(d) Suppose you want to shorten the completion time as much as possible and you have the option of shortening activities B, F, and G for one day each. Which would you shorten? Cannot reduce any activity O Activity F O Activity G O Activity B
Q: If two sequential activities A & B overlap and the successor activity can begin 5 days before the…
A: Project scheduling is an important part of project success. Proper scheduling of project activities…
Q: b) Assuming that each task is started as soon as possible, construct the corresponding resource…
A: b)
Q: A project's activities must be completed in the sequence indicated below. Activity Duration…
A: A network diagram is a visual representation of a project which helps to identify the critical path…
Q: If an activity has a total duration of 8 days and the schedule is 50% complete, how many days until…
A:
Q: . What is a schedule and why is it important in project planning? Explain your answer in detail.
A: A far-reaching process of designing a project schedule that outlines the project phases, tasks under…
Q: Duration of Dummy activity is always constant IS Select one: O True O False
A: Dummy activity does not consume time and resource. Duration of dummy activity is not always…
Q: 77 During the execution of a project, it is discovered that not all work packages included the…
A: Project Execution is the stage of the project life cycle in which the work is completed and the…
Q: You work for a company that makes cell phones and have been made project manager for the design of a…
A: Given data, MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS)…
Q: 44. What activities make up the critical path? In crashing this project, which activity is the first…
A: Project crashing is the process of reducing the activity duration using additional cost through…
Q: What is a schedule that can be changed? Because it's good to be able to get schedules back. Are…
A: A modification in a previously prepared schedule in order to get more benefits, avoid any predicted…
Q: A, B, and C, activities are the immediate predecessors for Y activity. If the earliest finish times…
A: THE ANSWER IS AS BELOW:
Q: Describe the purpose of the Work Breakdown Structure (WBS) that was utilized to complete your PMBOK…
A: The organizational breakdown structure is critical for initiating a project. This accessible…
Q: 1(A). You want to decorate your new apartment. For that you have identified six activities. You…
A: Note: - Since we can answer only up to three subparts, we will answer only the first three subparts…
Q: True/False Statements (Tick the correct option) Selection of the critical path in network…
A: BELOW IS THE SOLUTION:-
Q: 27. Consider a project with six activities: G, B, C, D, E, and F. Assume G and F can be started as…
A: The right option is the second choice. i.e., G--> B, G--> C, B --> D, C--> D,…
Q: d. How much slack is in Activity C? What does this mean? e. How much slack is in Activity E?
A: The critical task is the task that performs the operations on the critical path of the project that…
Q: A project has four activities that take 4, 3, 6, and 7 days, respectively. What is the…
A: A project consists of a group of specialized and skilled workers working together for a common…
Q: You work for a company that makes cell phones and have been made project manager for the design of a…
A: a) Activities Precedence Duration ES EF LS LF Slack P1 — 2 0 2 0 2 0 P2 P1 4 2 6 2 6 0 P3…
Q: The time by which an activity can be rescheduled without affecting the otheractivities - preceding…
A: (B) Independent float.
Q: What is the optimal plan for expediting some activities so as to minimize the total cost of…
A: Cost optimization in the time of advanced business implies that associations utilize a blend of IT…
Q: Activity Q on a project has exactly 4 successors E, F, G, and H whose late start days are 20, 12,…
A: Below is the solution:-
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: What is the critical path through the network? What is the project completion time? Suppose the…
A: A network diagram is a visual representation of a project which helps identify the activity…
Q: You work for a company that makes cell phones and have been made project manager for the design of a…
A: EST = Early start time LST = Late start time EFT = Early finish time LFT = Late finish time
Q: What are the values of the slack for activities B and F?
A:
Q: How many activities have non-zero free slack? Choose. How many activities have non-zero total slack,…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: There are various approaches to reducing the estimated duration of activities. These are: (a) Apply…
A: A project involves various factors such as financial investment, time, efforts, the risk involved,…
Q: In reference to the attached activity precedence diagram and activity times shown. (Feel free to…
A: The critical path method helps in determining the longest project completion time and the critical…
Q: The following statement about a noncritical activity is FALSE: A. Delaying it beyond its slack will…
A: Networks are considered to be a very effective way of planning the projects. The project manager has…
Q: The difference between the late and early start time for an activity is?
A: Answer given below:
Q: When crashing a project, the general guideline is to concentrate on the path with? a. The least…
A: A project crashing is the process of reducing the total duration of the project completion based on…
Q: You are in charge of a project at the local community center. The center needs to remodel one of the…
A: For the first part, let us calculate the early finish and early start time for each of the…
Q: Identify the term being described for each of the following: g. Shortening an activity by allocating…
A: The term used to determine shortening of an activity by allocating additional resources is called…
Q: Using the priority list T7, T6, T9, T5, T2, T3, T1, Tg, T4, schedule the project below with two…
A: Make a diagraph as shown below
Q: Consider the network presented in the following table. Calculate the slack for activity D. (Enter…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: A project has 92 activities, but only 13 of them are analyzed here. Activity P, 9 days, IP = not…
A: Given here: LS(K)= 118 LS(D)= 109 LS(H)= 124 LS(R)= 116
Q: What qualities does a project need to be able to use critical path scheduling?
A: Critical path scheduling is an invaluable tool that project managers have at their disposal. Without…
Q: What does it mean for a path to have three weeks of slack? Does each activity necessarily have three…
A: Slack on the project path is important to the managers. It is the amount of time when the activities…
Q: As the slack time of an activity is higher the activity is critical Select one: O True O False
A: Slack, also called float, is the amount of time a task can slip before it bumps into another task.…
Q: If the first activity in a given project is D which precedes A, B. And activity A precedes H,G. And…
A: Given data is
Q: What is the least expensive method of halting some tasks in order to keep the project's (estimated)…
A: Project crashing would be a method in which fit indices are utilized to reduce the time of a project…
Q: Slack time for each of the activities is? (Activity A-G)
A: Find the given details below: Given Details: Activity Immediate Predecessor(s) Time (days) A…
Q: The extent of time by which an activity can be delayed beyond its earliest start time without…
A: Project management refers to the application of the knowledge, tools, and techniques for achieving…
Q: Calculate the start and finish times for each activity. (Leave no cells blank - be certain to enter…
A: Below is the solution:-
Q: What happens if there are a large number of tasks with the same priority?
A: Realizing how to focus on work influences the achievement of your undertaking, the commitment of…
Q: The activities in a project whose completion times need to be shortened in order to finish the…
A: Project management is the implementation of procedures, strategies, expertise, knowledge, and…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps with 4 images
- ++ Earned value analysis is the project management tool that is used to measure project progress. You are a project manager in company XYZ that responsible to handling the packaging machine project with the total cost budgeting is RM100,000. There are including RM24,000 (Design), RM60,000 (build) and RM16,000 (install & test). The information regarding on the project progress development in weeks 8 as shown in Table 2 below: Table 2 No 1 2 3 Type Cumulative Budgeted Cost (CBC) Cumulative Actual Cost (CAC) Cumulative Earned Value (CEV) TOTAL RM 64,000 68,000 54,000 100,000 Percentage 64.0 68.0 54.0 100.0 a) With the aid of a typical S-curve diagram, draw and explain the four cost-related measures such as TBC, CBC, CAC and CEV to analyses the overall project cost performance.The expected times and variances for the activities for a project for Test Marketers, Inc. are given below. (Assume time is provided in days.) ID 12345678 Description Pilot production Select channels of distrib. Develop mktg. program Test market Patent Full production Ad promotion Release Predecessor None None None 1 1 4 3 2,5,6,7 t₂ 6 7 4 4 10 16 3 2 Varlance [(b-a)/6]² 34225221 101.You’re managing a project to install 400 windows in a new skyscraper and need to figure outyour budget. Each week of the project costs the same: your team members are paid a total of $4,000every week, and you need $2,000 worth of parts each week to do the work. If the project isscheduled to last 16 weeks, calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project? 2.You’re managing a highway construction project. Your total budget is $650,000, and there isa total of 7,500 hours of work scheduled on the project. You check with your accountingdepartment, and they tell you that you’ve spent a total of $400,000. According to the schedule,your crew should have worked 4,500 hours, but your foreman says that the crew was allowed towork some overtime, and they’ve put in 5,100 hours of work. Calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project?
- also determined that if there are no resource constraints, the project should be complete in 30 working days. Table Q6-1: Precedence Relations and Durations for a Nine Activity Project Activity Predecessor ID A B C D E F G H I DABCDEF ID Description Site clearing Removal of trees General excavation Grading general area Excavation for trenches G H I Placing formwork and reinforcement for concrete Installing sewer lines Installing other utilities Pouring concrete Required 2 2 2 2 2 2 2 2 4 0 0 None None A A B,C B,C D,E D,E F,G 4 4 12 12 21 21 24 Table Q6-2: Resources Required and Starting Times for a Nine Activity Project Activity Workers Earliest Start Time Latest Start Time 0 9 4 15 13 2222 12 25 24 Duration (days) 4 3 [Total 2000 w 8 7 9 12 2 5 6 Given that only four workers are available for the project, determine the shortest possible time in which you can undertake this project. Draw a Gantt chart to show how you have arrived at your final schedule.What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL CRASH TIME (DAYS) TIME (DAYS) NORMAL COST 8 6 6 4 ACTIVITY Design (A) Wiring (B) Chip install (C) Software (D) Testing (E) 8 5335 400 1,000 600 1,000 1,100 CRASH COST 450 1,100 700 1,300 1,625 IMMEDIATE PREDECESSOR(S) A, B C The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $900 (enter your response as a whole number).Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of work
- Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managersMailings Review View me E E • E = AaBbCcDc Aa AaBbCcDdEe AaBbCcDdEe Normal No Spacing Heading 1 Paint Window Install Sills (2) Windows (2) Remove Siding Add New Siding Paint Exterior (2) (4) (2) 1 Install Interior (2) Remove Floor (1) 4 Install New Floor (4) Instructions: The network diagram above (activity on arrow) shows the activities needed to complete a project to remodel a storage shed. The activities are listed as well as the time (in days) it will take to complete them. Use this information to find the following values for each of these activities: early start time, early finish time, late start time, late finish time (Probably best to do in an Excel file). Based on this, find the slack time for each activity and identify the critical path. 2.B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4
- Map s ipral model on any simple projectAn R&D project in a company is working on a project to make a sample product to be displayed at an international fair in Las Vegas held in 18 months. With additional equipments, the company can make sure they make the sample in 18 months. Develop an optimal crashing time-cost solution to help the company in this project to be ready on time for the fair. C, 4 B, 3 А,5 H,7 D, 3 F, 9 G, 2 Cost per month Activity Normal Time to crash 9,000 4,000 6,000 4,000 2,000 5,000 2,000 9,000 A В C 4 E F 9. G 2 H 7 Duration Path Activity to crash (months) АВСН ADEH FGHM Inbox (102) - kellyca6@miamioh. X M Inbox (14) - christopher 10kelly@x ✰ miamioh.instructure.com/courses/190424/assignments/2380311 Proj 1 - Prj Mgt-1.docx 5 B Assignments Project #1 Project #1 Activity A B с D E F G H I J K L M N O P Q R X A group of developers is building a new shopping center. A consultant for the developers has developed the following table of activities, durations and predecessors. Determine the earliest start times and finish times, latest start and finish times, activity slack, critical path and duration for the project. There is a Bonus for finishing the project at 90% of the projected date. The bonus for early completion is $50,000. Which activities should be crashed, if the cost for 1 week reduction, for any activity, is $3500 per week, and what is the total cost of crashing? And, Net Bonus, if any. Description Award Kick-off Contract for Crew/Mach Purchase Material Excavation Build Foundation Electrical - Outside Paving Lighting - Exterior Electrical -…