Exercise 7-13 (Algo) Computing ABC Product Costs [LO7-3, LO Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit 0.90 0.50 Annual Production 24,000 units 49,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $28 in direct materials per unit, and Sprockets require $16. b. The direct labor wage rate is $13 per hour. c. Hubs require special equipment and are more complex to manufacture than Sprockets. d. The ABC system has the following activity cost pools: Activity Cost Pool (Activity Measure) Machine setups (number of setups) Special processing (machine-hours) General factory (organization-sustaining) Estimated Overhead Cost $ 17,280 $ 164,500 $ 266,600 Hubs 80 4,700 ΝΑ Activity Sprockets 64 0 ΝΑ Total 144 4,700 ΝΑ

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter5: Process Costing
Section: Chapter Questions
Problem 2PB: The following product costs are available for Kellee Company on the production of eyeglass frames:...
icon
Related questions
Question

Please do not give solution in image format thanku 

Exercise 7-13 (Algo) Computing ABC Product Costs [LO7-3, LO7-4]
Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow:
Direct Labor-Hours
per Unit
0.90
0.50
Annual Production
24,000 units
49,000 units
Hubs
Sprockets
Additional information about the company follows:
a. Hubs require $28 in direct materials per unit, and Sprockets require $16.
b. The direct labor wage rate is $13 per hour.
c. Hubs require special equipment and are more complex to manufacture than Sprockets.
d. The ABC system has the following activity cost pools:
Activity Cost Pool (Activity Measure)
Machine setups (number of setups)
Special processing (machine-hours)
General factory (organization-sustaining)
Estimated Overhead
Cost
$ 17,280
$164,500
$ 266,600
Hubs
80
4,700
ΝΑ
Activity
Sprockets
64
0
ΝΑ
Total
144
4,700
ΝΑ
Transcribed Image Text:Exercise 7-13 (Algo) Computing ABC Product Costs [LO7-3, LO7-4] Fogerty Company makes two products-titanium Hubs and Sprockets. Data regarding the two products follow: Direct Labor-Hours per Unit 0.90 0.50 Annual Production 24,000 units 49,000 units Hubs Sprockets Additional information about the company follows: a. Hubs require $28 in direct materials per unit, and Sprockets require $16. b. The direct labor wage rate is $13 per hour. c. Hubs require special equipment and are more complex to manufacture than Sprockets. d. The ABC system has the following activity cost pools: Activity Cost Pool (Activity Measure) Machine setups (number of setups) Special processing (machine-hours) General factory (organization-sustaining) Estimated Overhead Cost $ 17,280 $164,500 $ 266,600 Hubs 80 4,700 ΝΑ Activity Sprockets 64 0 ΝΑ Total 144 4,700 ΝΑ
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Complete this question by entering your answers in the tabs below.
Required 1 Required 2
Compute the activity rate for each activity cost pool.
Activity Cost Pool
Activity Rate
per setup
Machine setups
Special processing
per MH
Required:
1. Compute the activity rate for each activity cost pool.
2. Determine the unit product cost of each product according to the ABC system.
Required 1 Required 2
Complete this question by entering your answers in the tabs below.
< Required 1
Direct materials
Direct labor
Overhead
Unit cost
Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculations. Round.
your answers to 2 decimal places.)
Hubs
Required 2 >
Sprockets
< Required 1
Required 2
Transcribed Image Text:Required: 1. Compute the activity rate for each activity cost pool. 2. Determine the unit product cost of each product according to the ABC system. Complete this question by entering your answers in the tabs below. Required 1 Required 2 Compute the activity rate for each activity cost pool. Activity Cost Pool Activity Rate per setup Machine setups Special processing per MH Required: 1. Compute the activity rate for each activity cost pool. 2. Determine the unit product cost of each product according to the ABC system. Required 1 Required 2 Complete this question by entering your answers in the tabs below. < Required 1 Direct materials Direct labor Overhead Unit cost Determine the unit product cost of each product according to the ABC system. (Do not round intermediate calculations. Round. your answers to 2 decimal places.) Hubs Required 2 > Sprockets < Required 1 Required 2
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting: The Cornerstone of Busines…
Managerial Accounting: The Cornerstone of Busines…
Accounting
ISBN:
9781337115773
Author:
Maryanne M. Mowen, Don R. Hansen, Dan L. Heitger
Publisher:
Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning