Explain which method for determining activity time estimate, deterministic are they perceive to be preferable?
Q: Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2…
A:
Q: Q3. Construct network and do the numbering according to Fulkerson's rule for the following: Activity…
A: Each node is addressed by a circle and numbered by utilizing Fulkerson's Rule. Following advances…
Q: What is an Aggregate Project plan?
A: Operations management is the management of business practices within an organization in order to…
Q: Define each of these terms, and indicate how each is determined.a. Expected activity time
A: Expected Activity time is calculated for anticipating the approximate time in which any activity…
Q: H.W For the following activities, draw the network diagram and by using forward and backward pass,…
A: Given data is
Q: Optical Disk Preinstallation Project 18. The optical disk project team has started gathering the…
A: Given data, Activity Description Duration Predecessor 1 Define Scope 6 None 2 Define…
Q: Draw the network and identify the critical path. Also calculate the earliest-latest starting and…
A: The method used for scheduling a set of activities that form part of a project, is called critical…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A:
Q: Fill the table below using the Activity-on-Arrow (A-o-A) network given and answer the questions.…
A:
Q: Determine the expected activity completion times, te
A: Formula:
Q: Activity Preceding activity Optimistic Most Pessimistic Likely A 3 8 A 1 3 C A 11 D 4 3 4 В, С В, D…
A: A - 3 6 8 B A 1 3 5 C A 2 2 11 D C 4 3 4 E B, C 3 5 4 F B, D 5 2 2 G E, F 3 6 12…
Q: estimate the work unit price and the work price.
A: From the given points in the question, the following conclusions can be drawn: 1- The number of days…
Q: The manager of the Oak Hills Svimming Club is planning the club's swimming team program. The first…
A: The activity schedule is as calculated below: Forward Pass:Early Start (ES) = Maximum (or Highest)…
Q: For a particular project, consider following list of Activities, their duration in Days and their…
A: Given data is,
Q: 3.22 Four Squares Productions, a firm hired to coordinate the release of the movie Pirates of the…
A: Given data is
Q: Problem #2-Freeze Inc. is planning the implementation of a new sales offices in the Tampa - FL area…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: Give data of a project. Project manager checks the project at the end of week 10th Manpowers/ weeks…
A: Cost Variance (CV = EV - AC) Cost Performance Index (CPI = EV/AC) Schedule Variance (SV = EV -…
Q: What is an activity slope and what does it indicate?
A: Project management contains leading and controlling the project activities to achieve the project…
Q: An activity on a PERT network has these time estimates: optimistic = 2, most likely = 3, and…
A: We have, Optimistic, To = 2 Most likely, Tm = 3 Pessimistic, Tp = 6
Q: using the PERT formula calculate the time value for each activity and construct the network diagram
A: A PERT diagram is a project management took which enables to understand the relationship between…
Q: Develop an activity schedule for this project using early and late start and finish times, compute…
A: A forward and backward passing network diagram including 5 different time dimension for a project…
Q: 16. To complete the wing assembly for an experimental aircraft, Rhea V. has laid out the major steps…
A: Activity Optimistic time Most Likely time Pessimistic time Predecessor A 1 2 3 B 2 3 4 C…
Q: Q1,Draw the network. Q2,what is the critical path Q3,how many weeks will it take to complete the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Activity Precedence Activity Times (in week) A A 8 C В D A E C,D F E 8 E 7 H E F,G,H 4 4
A: A Gantt chart, generally employed in project management, is one of the most familiar and helpful…
Q: 3. Information relating to"RUHUNA X" project is given below. Estimated cost per Activity predecessor…
A: Activity Predecessors Duration A - 2 B A 10 C A 4 D A 5 E…
Q: Preceding Activity Duration Activity (weeks) C, D 3 2 F What is the project's critical path? B -D-G…
A: Activity Immediate Predecessors Duration A - 5 B - 4 C A 2 D B 1 E B 5 F B 5 G C,D 4…
Q: Given the following AON network and activity time estimates, determine the expected project…
A: Determine the expected time and variance for every activity as follows - Time (t)=a+4m+b6 Variance…
Q: Project planners sought judgment of various knowledgeable engineers, vendors and foremen and have…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: Draw a project network for this problem. Fill in all the blanks in the following table.…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Q3: Draw the network diagram and determine the critical path for the following project: Activity…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Analyze projects using network-planning models?
A: A network planning model helps in establishing a sequence of activities in a project. These models…
Q: Task time estimates for a production line setup project at XYZ Company are as follows; Activity Time…
A: We are authorized to answer three subparts at a time since you have not mentioned which part you are…
Q: A. Draw a project network for this problem. B. Fill in all the blanks in the following table.…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: t a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing…
A: Since you have posted a question with multiple sub-parts, we will solve the first three sub-parts…
Q: Define each of these terms, and indicate how each is determined.a. Expected activity time.
A: For calculating the expected activity time, the parameters required are the following: Optimistic…
Q: Schedules and activities of some projects are shown below Draw the network diagram Activity…
A: Note: - Since we can answer only up to 3 sub-parts we will answer questions 1, 2, and 3 from the…
Q: Define each of these terms, and indicate how each is determined.b. Variance of an activity time.
A: For calculating the variance, the parameters required are the following: Optimistic time: This is…
Q: Activity b Immediate a m Predecessor (days) A 3 5 B 0.5 1 1.5 A C D 4 A 5 7 9 B E 1 2 3 F 6. 9 12 D…
A: Given data is
Q: At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing…
A: The critical path is A-C-E-G Duration 32
Q: . Draw a project network for this problem. b. Fill in all the blanks in the following table. c.…
A: Below is the solution:-
Q: Paul Silver, owner of Sculptures International, just initiateda new art project. The following data…
A: Given data is
Q: (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth…
A: Note: As per the Bartleby guidelines only three parts have been answered:
Q: A student club plans on holding a campus-wide event at the end of the semester. The activities that…
A: Given that: Duration Immediate Activity (weeks) Predecessor A 2 -- B 3 A C 1 A D 3…
Q: Find the activity duration (t), latest start (LS) and latest finish (LF) times for activity A.
A: Given: Early start (ES) = 5 Early finish (EF) = 16
Q: On June 12, 2013, the Delta Corporation was awarded a $160,000 contract for testing a product. The…
A: The three imperatives project chiefs work inside are budget, scope, and schedule. Schedule (or time)…
Explain which method for determining activity time estimate, deterministic are they perceive to be preferable?
Step by step
Solved in 2 steps
- Explain the term Variability in Activity Times?At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 10 11 12 selected musicians B: Reserve site - 8 10 12 C: Manage travel logistics A 2 7 9 for music group D: Screen & hire B 4 5 6 security personnel E: Arrange advertising C 7 7 7 & ticketing F: Hire parking staff A, D 8 9 16 G: Arrange concession sales E 6 7 11At a local university, the Student Commission on Programming and Entertainment (SCOPE) is preparing to host its first rock concert of the school year. To successfully produce this rock concert, SCOPE has listed the requisite activities and related information in the following table (duration estimates measured in days). Immediate Most Activity Predecessor(s) Optimistic Probable Pessimistic A: Negotiate contract with - 10 11 12 selected musicians B: Reserve site - 8 10 12 C: Manage travel logistics A 2 7 9 for music group D: Screen & hire B 4 5 6 security personnel E: Arrange advertising C 7 7 7 & ticketing F: Hire parking staff A, D 8 9 16 G: Arrange concession sales E 6 7 11 Which project network is correct? IMG is attached Compute the expected duration and variance of each activity. If required, round your answer to two decimals. If your answer is zero, enter “0”.…
- 2. The following table lists the activities of a network along with their time estimates: Activity Predecessor Duration (Days) Optimistic (a) Most Likely (m) Pessimistic (b) A None 2 5 8 B None 4 7 16 C A 3 6 9 D A 2 5 8 E C 5 8 11 F D 3 6 15 G B 2 5 14 H E, F 2 5 8 I G 6 9 12 J H, I 0 0 0 (a) Draw the project network. Use activity on node (A-O-N) method. (b) Identify the Critical Path. Calculate the length and variance of the Critical Path. (c) Identify the non-critical activities. Work out the Total Slack (TS) and Free Slack (FS) for all the non-critical activities. (d) State whether the network is sensitive or insensitive! (e) What is the approximate probability that jobs on the critical path will be completed by the due date of (i)24 days, (ii) 29 days?The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 a) What is the critical path? b) What is the project expected time? c) What is the probability of completing in 13…Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity A B C D E F G H 1 J K L ES ID EF ¤¯¯ SL SL LS Time LF Predecessor A, B C E F E D D, G, I 1 Duration in Weeks 5 3 8 3 4 10 8 18 20 7 5 10 6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation
- The manager of the Oak Hills Swimming Club is planning the club’s swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows: Time (in weeks) Activity Description Immediate Predecessor Optimistic Most Probable Pessimistic A Meet with board ------ 1 1 2 B Hire coaches A 4 6 8 C Reserve pool A 2 4 6 D Announce Program B, C 1 2 3 E Meet with Coaches B 2 3 4 F Order Team Suits A 1 2 3 G Register Swimmers D 1 2 3 H Collect Fees G 1 2 3 I Plan first practice E, H, F 1 1 1 b) What is the project expected time? c) What is the probability of completing in 13 weeks? d) What is the…What is an activity slope and what does it indicate?SAQ 3: For the present, construct the appropriate network diagram representing this data. Include "Start" and "End" activities as appropriate. Activity Duration Preceding Activity Start A 5 4 C 6 A E 5 B F 6. С, D End Е, F 2.
- Define Matrix Project?The manager of the Oak Hills Swimming Club is planning the club's swimming team program. The first team practice is scheduled for May 1. The activities, their immediate predecessors, and the activity time estimates (in weeks) are as follows. Time (Weeks) Immediate Predecessor Activity Description Optimistic Most Probable Pessimistic A Meet with board 1 1 2 B Hire coaches A 4 8 Reserve pool A 4. 6 D Announce program В, с 3 E Meet with coaches B 4 F Order team suits A 1 2 3 G Register swimmers D 2 3 H Collect fees G 1 I Plan first practice Е, Н, F 1 1 1 (a) Draw a project network. (Submit a file with a maximum size of 1 MB.) Browse. No file selected. (b) Develop an activity schedule. (Round your answers to two decimal places.) Earliest Start Earliest Finish Latest Latest Activity Slack Start Finish A B D E F G H I (c) What are the critical activities? (Enter your answers as a comma-separated list.) What is the expected project completion time (in weeks)? (Round your answer to two decimal…Please answer for activity’s A-K .