Given the following activity network: Ki A1 Activity A1 takes 5 weeks, A2 takes 8 weeks, and A3 takes 2 weeks. What is the earliest start time of A3? A) 10 weeks B) 15 weeks C) 7 weeks D) 13 weeks
Q: PROBLEM 5 Brenda Mage, an undergraduate accountancy major at Ateneo de Zamboanga University, is…
A:
Q: The word "right" form the procurement point of view within the supply chain is 1) Planning &…
A: Procurement: Procurement process contains the series of actions to collect the goods…
Q: Ah Heng is in egg business. He has three poultry farms, A, B and C. The eggs are sent to three…
A: The question is related to Transportation Problem. The basis rule of transportation problem is…
Q: What are control charts? What are the various types? What are the critical features?
A: In the context of statistics, different types of charts and graphs have been used. These charts and…
Q: A new airline has decided to join the market. It is considering offering flights out of Cagayan, and…
A: C = Charges per ticket for the round trip to Cebu P = Charges per ticket for the round trip to…
Q: Which of the following elements of the balanced scorecard shows the expected cause-and-effect…
A: A cause-and-effect relationship is generally can be observed where the following conditions are…
Q: discuss the importance of work measurement.
A: Introduction Work Measurement in Operation Management can be define as the technique which performs…
Q: Describe the inventory that one would expect at IKEA.
A: IKEA is the world’s biggest home furnishing retailer, providing approximately 9,500 items &…
Q: Calculate the annual economic order quantity from the information provided below.
A: EOQ stands for economic order quantity. It is a company's optimal order quantity that undervalues…
Q: 1) Find the time to complete this project assuming the given duration of each task is constant.…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: ng and supplying perspective and with a simple diagram describe how goods move from the supplier of…
A: Supply Chain management: Supply chain management is the enhancement of an item's creation and stream…
Q: The management of CDC Construction Pioneers have decided to build 900 new apartments in the Kasoa…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: the benefits of EA and ERP
A: Enterprise architecture can be broadly defined as a process of planning, implementing as well as…
Q: List three advantages of project management and explain each
A: Project management generally helps the groups or the teams to arrange, track, implement or execute…
Q: The product vision or features are unclear. Product owners are permitted to change requirements and…
A: Project methodology- Different projects come with different requirements to achieve their particular…
Q: Draw up a plan for a preliminary assessment of waste minimization opportunities in a small…
A: Waste minimization is indeed a method of waste management that aims to lessen the quantity as well…
Q: lue chain of Apple is presented in the following figure. Which activity adds the ast value?
A: Ans) Given graph is between value added and production process
Q: All of these are goals that the company has identified, with NO priorities. a) Formulate this given…
A:
Q: What are the benefits of automation and how will the communication signalling technology increase…
A: Operation manager is an individual who is responsible for managing an organization's operations.…
Q: inute to check a pati A doctor spends 10 r
A: Given: Receptionist takes 1min nurse takes 2mins Doctor spends 10mins staff member takes 3mins
Q: The management of CDC Construction Pioneers have decided to build 900 new apartments in the Kasoa…
A: Objective Functions and Constraints: Based on the given details, the objective…
Q: Why is operations management is an important activity to a project? Who is suited to become…
A: Operations management is quite a significant activity for a project. It is an activity that helps in…
Q: A small bank has $1,000,000 in new funds that must be allocated to various loan types, including…
A: Given data is Rate of return by home loans = 7% = 0.7 Rate of return by personal loans = 12% = 0.12…
Q: A local factory assembling calculators produces 400 units per month and sells them for P1,842 each.…
A: Production = 400 units per month Selling price (P) = P1842 per unit Fixed cost (F) = P50825 Variable…
Q: Problem 1: Auto Mart is a mythical seller of a variety of automobile parts and accessories. Auto…
A: Given data is Annual demand(D) = 16000 Holding cost = $2.50 Order cost(S) = $50
Q: b) Ghana Post has established various truck and air routes around the country over which it ships…
A: Network of routes and the flow capacities (in tons of packages per day) are shown as follows:…
Q: Dave Escalona, a DLSL Computer Engineering graduate, is considering the possibility of opening a…
A: Decision making is a process of selecting the best alternatives from all possible decisions based on…
Q: PROBLEM 2 Professor Weejohs teaches two sections of business analytics, which combined will result…
A: Time taken (in minutes) Time available (in hrs.) AJ 7.2 12 Romel 12 10 Exams to…
Q: PROBLEM 7 Eyewitness News is shown on channel 5 Monday through Friday evenings from 5:00 P.M. to…
A:
Q: What are the net requirements for N?
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: machines (A, B, and C) in the same order. The processing times are listed below. Use Johnson's Rule…
A: Sequencing is an appropriate order of plan as per which the process of operations works. It defines…
Q: START 1 A 1 H H H H B 1 с N 2 N N END N 3 + 3 D W H T 5 5 @ w RE 00 UI U 3 3 C 3 1 F 1 3 S 3 6 5 130…
A: Find the Given details below: Activity ImmediatePredecessors Duration A - 1 B A 1 C A 1 D…
Q: Period 1 2 3 4 5 6 1. Compute the four period moving average forecast for period 6 and 7. Assume the…
A:
Q: Suppose that a firm begins at time t=0 with a capital stock of K(0) = 500,000 pesos and, in addition…
A:
Q: 1. PREDECESSOR DIAGRAM (AON) 2. FILL UP (ES.EF.LS.LF.S) CHART 3. GANTT CHART
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: A particular branch of ABC Co. is experiencing some inventory control problems. The manager…
A: If we like to employ proper management, here, we will order the EOQ quantity, first, I will…
Q: in relation to project management Part 2: Identify at least three project ideas related to any of…
A: The market for project the board ability is hot laborers with project the executives experience and…
Q: Use Johnson's rule to determine the optimal processing sequence for the jobs listed in the following…
A: Given data is
Q: GM Electronics expects to sell 800 alarm systems each month of 2022 at R4 000 each. The cost price…
A: Annual Demand, d =800 ×12 =9600 alarm systems Unit cost, u =R 2000 Holding cost, h =0.01×2000 = R 20…
Q: Am I on the right track to do this question correctly? If not please show me where I went wrong and…
A: Below is the replica of the sheet provided in the question. Formulas:
Q: Difference between purchasing and procurement
A: Purchasing and procurement are the two distinct activites that are carried out at the time of…
Q: Opportunity costs are relevant to which of the following decisions? Whether to accept a special…
A: Opportunity cost is related to the economic benefit that is foregone by selecting an alternative.…
Q: what are some traits of a facility manager that indicate project management and an operational…
A: Facility Manager:- According to the International Organization for Standardization, facility…
Q: GOT7 Soda Pop, Inc., has a new fruits drink. The production planner has assembled the following cost…
A: Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: lves conforming to proj
A: You can't stress enough how vitally important quality is to successful project management. With…
Q: Which of the following is a disadvantage of partnership? Question 5 options: Unlimited…
A: A partnership can be stated as the formal organization by two or more two parties to handle or…
Q: Consider the following network for conducting a two-week (10 working days) computer training class:…
A: A network diagram is a visual representation of a project which helps to identify the activity…
Q: Given the following highway rerouting project, refer to the two pics please :)) (a) Draw the…
A: Note: - Since the answers for subparts a, b, and c are given in the question we will answer subpart…
Q: Demand beyond planning horizon can be managed by keeping a safety stock. GIVE ME ME MOER DETALIS…
A: Given, Service level, α =95% , Lead time, L =4 weeks =1 month
Q: Cubway, the sandwich shop, is run by Jim, Tim and Kim. When a customer arrives, Jim spends 5 minutes…
A: Here, First, I would draw the flow chart for this application case or situation, the flow chart is…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- Here is a CPM network with activity times in weeks: (A(7)) (B(5)) E(4)) (G(3) (C(6)) (F(8)) (D(6))1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift. Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately? NUYLOTNQhObm1bEVKUTO90 a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry. O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this. CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby. 40 Cara's gift is very thoughtful and will help to build a relationship with her clients. NUTYks10TNRUQ2h0bmkbEVKUTO90Which of the following are contractual terms (Select all that apply) NDA MOU LOI MAO CCB Communication can include which of the following Kick-off meetings Listening Outward E-mail All of the above Risk activities should be assigned To a team After a trigger occurs Without being added to the Risk Register To a single person In priority order What does CV stand for and what does it mean? (Select all that apply) Cost Variance, calculated EV – AC Continuous variability, measure of process Cost Variance, <1 is over budget Cost Variance, >1 is over budget Cost Variance, calculated AC – EV
- Lights Incorporated calculates cost for an equivalent unit of production using the weighted-average method. Data for July: Work-in-process inventory, July 1 (35,000 units): Direct materials (97% completed) Conversion (46% completed) Balance in work in process inventory, July 1 Units started during July Units completed and transferred Work-in-process inventory, July 31: Direct materials (97% completed) Conversion (46% completed) Cost incurred during July: Direct materials Conversion costs $ 122,950 77,400 $ 200,350 86,000 95,900 25,100 $ 185,500 266,000 The cost of goods completed and transferred out under the weighted-average method is calculated to be: (Round your Intermediate calculations to 2 decimal places and final answer to the nearest whole dollar amount.) Multiple Choice $627,740. $553,343. $578,840. $102,946. $569,680.Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 6 C − 1 D B 10 E A, D 3 F C 6 G E, F 8 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are ▼ C - F - G A - E - G B - D - E - G . c) The project length for the leadership training program development project = enter your response here days. d) Slack time for each of the activities is: Activity Slack Time A enter your response here B enter your response…Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 4 B − 6 C − 1 D B 10 E A, D 5 F C 5 G E, F 8 This exercise contains only parts b, c, and d. Part 2 b) The critical activities for the leadership training program development project are ▼ B - D - E - G C - F - G A - E - G . Part 3 c) The project length for the leadership training program development project = enter your response here days. Part 4 d) Slack time for each of the activities is: Part 5 Part 6 Part 7…
- Explain when you think a baseline should be updated and why.Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a number of activities that must be completed before a training program of this nature could be conducted. The activities, immediate predecessors, and times appear in the accompanying table: Activity Immediate Predecessor(s) Time (days) A − 2 B − 5 C − 3 D B 10 E A, D 4 F C 5 G E, F 12 This exercise contains only parts b, c, and d. b) The critical activities for the leadership training program development project are B - D - E - G . c) The project length for the leadership training program development project = 31 days. d) Slack time for each of the activities is: Activity Slack Time A 00 B nothing C nothing D nothing E nothing F…Simplifying the ABC System: DBC Electan Company produces two types of printers. The company uses ABC, and all activity drivers are duration drivers. Electan Company is considering using DBC and has gathered the following data to help with its decision. A. Activities with duration drivers: Activities Products Changeover Assembly Testing Rework Total Hours Printer A 1,000 12,000 8,000 8,000 25,000 Printer B 4,000 8,000 12,000 12,000 25,000 Total hours 5,000 20,000 20,000 20,000 50,000 B. Activities with consumption ratios and costs: Activities Products Changeover Assembly Testing Rework CostAssignment Printer A 0.20 0.60 0.40 0.80 $155,000 Printer B 0.80 0.40 0.60 0.20 $155,000 Activity costs $75,000 $120,000 $60,000 $55,000 $310,000 C. Products with cycle time and practical capacity: Products Cycle Time PracticalCapacity…
- Three point estimates and bottom up estimating are used in developing: (select one correct answer) Schedules Risks Cost estimates ScopeExercise 1 Your Customers Are Using My Parking Lot! You own a hardware store that is located in a strip mall. Three months ago an Italian restaurant opened next door. Parking is limited and each respective business in the strip mall has a designated number of parking spaces in front. This is generally not a problem because your store has more customers during the day, while the restaurant is busier at night. The problem is on Friday and Saturday nights when your store is open later and the restaurant is busier. You are concerned because business at the restaurant has been increasing as the restaurant becomes more well known. Instructions: Implications of NegotiationTh3 task is pr0vided in th3 pictur3. (creat3 a DATA FLOW DIAGRAM for the Creat3 a DATA FLOW DIAGRAM for the CASH RECEIPTS SYSTEM that is pr0vided in the pictur3 I WILL RAT3 TH3 TUT0R H3LPFUL IF ANSW3RED ASAP