If a project with conventional cash flows has an IRR equal to the required return, then: O The profitability index is one. O The IRR must be zero. The project should be accepted, as the NPV is greater than zero. O The payback period is less than the maximum acceptable period. The NPV is negative.
Q: Breakeven cash inflow refers to ________. the minimum level of cash inflow necessary for a…
A: Net present value is one of the discounted techniques of capital budgeting which is used to measure…
Q: :If the annual worth value of an alternative is equals to a positive value, we consider this project…
A: MARR is Minimum acceptable rate of return
Q: company is considering a project that has the following cash flow data. What is the project's IRR?…
A: IRR is the rate at which NPV of investment is zero. It is the rate of return the firm will get if…
Q: Assume a project has normal cash flows. All else equal, which of the following statements is…
A: The correct answer is option (e). The weighted average cost of capital includes the cost of…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: WACC is the required rate of return, where as IRR is the actual rate of return of the project. NPV…
Q: ve determined the profitability of a planned project by finding the present value of all the cash…
A: Present value of cash flow is related to the discount rate and the period of cash flow of the…
Q: f a project's cash flows are discounted at the internal rate of return, the NPV will always be…
A: Internal rate of return is the rate at which present value of cash inflows is equal to present value…
Q: A company is considering a project that has the following cash flow data. What is the project's IRR?…
A: IRR or internal rate of return is the rate at which present value of cash inflows is equal to…
Q: What do you know about the mathematical value of the internal rate of return of a project under each…
A: Internal rate of return(IRR) is rate at which net present value(NPV) of project is equal to zero or…
Q: Assume a project has normal cash flows (i.e. the initial cash flow is negative and all other cash…
A: Option B) - All else equal, a project's N.P.V increases as the cost of capital declines.
Q: You have determined the profitability of a planned project by finding the present value of all the…
A: We determine the profitability of project by discounting the future cash flows with appropriate…
Q: True or False A project will have multiple internal rates of return if its future net cash flows…
A: Internal rate of return (IRR) is the annual rate of return which is anticipated from the cash flows.…
Q: Datta Computer Systems is considering a project that has the following cash flow data. What is the…
A: Internal rate of return(IRR) of the project is calculated in excel below
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Statement A: FALSE Because project NPV is found by discounting the cash inflows at a discount rate…
Q: Question 1 Which one of the following statements is NOT correct? Group of answer choices If…
A: Capital budgeting is a technique to estimate the profitability of the projects. There are various…
Q: Suppose your firm is considering investing in a project with the cash flows shown below, that the…
A: Required Return = 7% Year Cash Flow 0 -5300 1 1300 2 2500 3 1700 4 1700 5 1500 6…
Q: Which of the following statements is CORRECT? O Projects with "normal" cash flows can have two or…
A:
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Since the higher the rate would be lower would be the present value factor..... which means the…
Q: The Everett Co. is looking a project with an outlay of $810 which will have a positive cash flow at…
A: IRR is the rate at which NPV is zero
Q: Yonan Inc. is considering Projects S and L, whose cash flows are shown below. These projects are…
A: Net present value is the difference between the present value of cash inflows and present value of…
Q: tively rapidly will be more sensitive to changes in the discount rate than the NPV of a project…
A: Net present value is the difference between the present value of cash flow and initial investment.
Q: The decision rule for net present value is to: Select one: O a. accept all projects with positive…
A: Net Present Value ("NPV") is a capital budgeting method under which, present value of future…
Q: Consider a project with the following cash-flows: ime Cash-flow t=1 t=2 t=3 3 t=0 -10 2 What is the…
A: “Hey, since there are multiple questions posted, we will answer first question. If you want any…
Q: Which of the following statements is incorrect regarding project appraisal techniques? At IRR, the…
A: Net Present Value ("NPV"), Internal Rate of Return ("IRR") and Profitability Index ("PI") are all…
Q: calculates that a project with conventional cash flows and a required return of 14% has a negative…
A: Internal rate of return when net present value is zero that means present value of cash flow is…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: It refers to the rate of return that is computed by the company to make a decision of selection of a…
Q: The AW of a project can be estimated by reducing all cash flows including the capital investment,…
A: Annual worth is the equivalent annual value for the cash flows for the given investment project.
Q: Projects A and B have approximately the same NPV. Their initial outlays are similar in size. Project…
A: The question is based on the concept of capital budgeting approaches for selection of project in…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Internal Rate-of-Return is discount rate that makes NPV(Net Present Value) zero for an investment…
Q: A project is economically feasible if: O a. ts future worth is less than zero O b. its annual worth…
A: Future worth is the sum of future value of cash flows. Annual worth is the equivalent annual cash…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: We will solve this problem by eliminating each option. 1) option a: A project’s NPV is generally…
Q: If the profitability index of a normal investment project is 0.5 and the initial investment required…
A: A Profitability index is a useful tool that is used by the management in order to the ranking of the…
Q: 3. Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Financial Management: Financial management comprises of two words i.e. Finance and management.…
Q: Net Present Value Suppose a project has conventional cash flows and a positive NPV. What do you know…
A: Capital budgeting techniques are the methodologies adopted by the management of the company with the…
Q: Sexton Inc. is considering Projects S and L, whose cash flows are shown below. These projects are…
A: NPV It is the best alternative method used as an indicator of the dynamic calculations of an…
Q: For the given cash flows, suppose the firm uses the NPV decision rule. Year Cash Flow 0 –$ 148,000 1…
A: NPV = sum of all PVs (present value) PV in a year = cash flow in the year * PVIF PVIF = 1/(1+r)^n…
Q: You are considering an investment into a new market and have two mutually exclusive and normal cash…
A: IRR is the rate of return when NPV is zero. The criteria to select a project is that the Net present…
Q: ssume a project has normal cash flows. All else equal, whic llowing statements is correct? A…
A: The pay back period is the amount of time required to recover the initial amount of investment and…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Point 1 is not correct as IRR is not found using this method. Cash flows cannot be compounded at…
Q: Which TWO of the following statements are correct for a potential project with an investment…
A: Capital Budgeting techniques are used to know the profitability of the project. The NPV and the IRR…
Q: O One can use the IRR rule for investment decision making without knowing the discount rate O The…
A: Question 2: The concerned question belongs to Time value of money where different methoda are used…
Q: WorldTrans is considering Projects S and L, whose cash flows are shown below. These projects are…
A: WACC is the rate that a company is expected to pay on an average to all its security holders to…
Trending now
This is a popular solution!
Step by step
Solved in 3 steps
- A project is economically feasible if: O a Its future worth is less than zero O b. Its annual worth is greater than 0 O .ts internal rate of return is equal to its external rate of return O d. Its external rate of return is less than the minimum attractive rate of return O e. Its external rate of return is greater than 0When the present value of the cash inflows exceeds the initial cost of a project, then the project should be : A. rejected because NPV is negative. B. accepted because NPV is greater than 1. C. accepted because the profitability index is negative. D. rejected because the internal rate of return is negative.What do you know about the mathematical value of the internal rate of return of a project under each of the following conditions? a.The future worth of the project is equal to zero. b. The future worth of the project is less than zero.
- If a project's cash flows are discounted at the internal rate of return, the NPV will always be negative. T/FWhich of the following statements is CORRECT? a. If a project with normal cash flows has an IRR greater than the cost of capital, the project must also have a positive NPV. b. If a project with normal cash flows has an IRR less than the cost of capital, the project must have a positive NPV. c. If the NPV is negative, the IRR must also be negative. d. A project's MIRR can never exceed its IRR. e. If Project A's IRR exceeds Project B's, then A must have the higher NPV.The internal rate of return (IRR): Group of answer choices will always lead to the same decision as will NPV. is a "purer" discount rate because is excludes all external project cash flows. is the discount rate that produces NPV of zero for a series of cash flows. None of the above
- Which of the following is CORRECT? Select one: a. If the NPV of a project is negative, the IRR for the project must also be negative. b. A project's MIRR can never exceed its IRR. c. If a project with normal cash flows has an IRR less than WACC, the project must have a positive NPV. d. If Project 1's IRR exceeds Project 2's IRR, then 1 must have a higher NPV than 2. e. If a project with normal cash flows has an IRR greater than WACC, the project must have a positive NPV. You purchase a house for $250,000. After you make your down payment of $50,000, you are financing $200,000 for 30 years at an annual percentage rate of 5.4%. How much are your monthly payments? Select one: a. Less than $1,000 b. Between $1,000 and $1,050 c. Between $1,050 and $1,100 d. Between $1,100 and $1,150 e. Greater than $1,200Which of the following statements is most FALSE? A. If a project with normal cash flows has a positive NPV, it will definitely have an MIRR greater than the cost of capital. B. If a project with normal cash flows has an IRR that is greater than the cost of capital, then taking on that project would decrease the value of the firm. C. If a project has normal cash flows, then the MIRR has to be between k and IRR if the project has positive interim cash flows (cash flows between t=0 and the end of the project). D. If a project with normal cash flows does not have any interim cash flows, the project's IRR will equal the project's MIRR. E. Multiple IRRS can exist for a project if the project has nonnormal cash flows. OA OB OCUsing IRR, a project is rejected if the IRR a. is equal to the required rate of return. b. is less than the required rate of return. c. is greater than the cost of capital. d. is greater than the required rate of return. e. produces an NPV equal to zero.
- Using NPV, a project is rejected if it is a. equal to zero. b. negative. c. positive. d. equal to the required rate of return. e. greater than the cost of capital.What are the reinvestment rate assumptions for the NPV and the IRR? A.IRR: Risk Free Rate NPV: WACC B.IRR: The IRR itself NPV: WACC C.The cash flows generated by the project are not assumed to be reinvested. So they will not earn a rate of return. D.IRR: Risk free rate NPV: Risk free Rate E. IRR:WACC NPV: WACCTrue or False A project will have multiple internal rates of return if its future net cash flows alternate between negative and positive values.