In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with respective processing times of 4 min, 4 min, 36 min and 12 min. a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.) b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time? stations. (Enter your response rounded up to the next whole number.) c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line? response rounded to two decimal places.) %. (Enter your

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter12: Queueing Models
Section12.5: Analytic Steady-state Queueing Models
Problem 27P
icon
Related questions
Question
In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies
per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with
respective processing times of 4 min, 4 min, 36 min and 12 min.
a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.)
b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time?
stations. (Enter your response rounded up to the next whole number.)
c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line?
response rounded to two decimal places.)
%. (Enter your
Transcribed Image Text:In order to meet holiday demand, Penny's Pie Shop requires a production line that is capable of producing 60 pecan pies per week, while operating only 40 hours per week. There are only 4 steps required to produce a single pecan pie with respective processing times of 4 min, 4 min, 36 min and 12 min. a. What should be the line's cycle time? minutes per pie. (Enter your response as an integer.) b. What is the smallest number of workstations Penny could hope for in designing the line considering this cycle time? stations. (Enter your response rounded up to the next whole number.) c. Suppose that Penny finds a solution that requires 3 stations. What would be the efficiency of this line? response rounded to two decimal places.) %. (Enter your
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps with 3 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,