In the following table there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b) while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated. Create Gantt chart and estimate critical path Time estimates Expected time (TE) Activity Predecessor Opt. (O) Normal (M) Pess. (P) a 4 6. 4 3 5 a 5 d a 4. 10 6. e b, c 4. 7 f d 4. 8 4 8. Note: - you can neglect time estimated and calculate only Expected time - all times in davs

Elements Of Electromagnetics
7th Edition
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Sadiku, Matthew N. O.
ChapterMA: Math Assessment
Section: Chapter Questions
Problem 1.1MA
icon
Related questions
Question
100%
I need the answer quickly
In the following table there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b)
while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete).
Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time
estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated.
Create Gantt chart and estimate critical path
Time estimates
Expected time
(TE)
Activity
Predecessor
Opt. (0)
Normal (M)
Pess. (P)
a
4
6.
b
3
9.
a
4
5
7
5
d
a
4
6.
10
6.
e
b, c
4.
7
5
f
d
3
8
4.
3
8
Note:
- you can neglect time estimated and calculate only Expected time
all times in days
Transcribed Image Text:In the following table there are seven tasks, labeled a through g. Some tasks can be done concurrently (a and b) while others cannot be done until their predecessor task is complete (c and d cannot begin until a is complete). Additionally, each task has three time estimates: the optimistic time estimate (O), the most likely or normal time estimate (M), and the pessimistic time estimate (P). The expected time (TE) is estimated. Create Gantt chart and estimate critical path Time estimates Expected time (TE) Activity Predecessor Opt. (0) Normal (M) Pess. (P) a 4 6. b 3 9. a 4 5 7 5 d a 4 6. 10 6. e b, c 4. 7 5 f d 3 8 4. 3 8 Note: - you can neglect time estimated and calculate only Expected time all times in days
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Dimensional Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Elements Of Electromagnetics
Elements Of Electromagnetics
Mechanical Engineering
ISBN:
9780190698614
Author:
Sadiku, Matthew N. O.
Publisher:
Oxford University Press
Mechanics of Materials (10th Edition)
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:
9780134319650
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Thermodynamics: An Engineering Approach
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:
9781259822674
Author:
Yunus A. Cengel Dr., Michael A. Boles
Publisher:
McGraw-Hill Education
Control Systems Engineering
Control Systems Engineering
Mechanical Engineering
ISBN:
9781118170519
Author:
Norman S. Nise
Publisher:
WILEY
Mechanics of Materials (MindTap Course List)
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:
9781337093347
Author:
Barry J. Goodno, James M. Gere
Publisher:
Cengage Learning
Engineering Mechanics: Statics
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:
9781118807330
Author:
James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:
WILEY