Indiana Co. began a construction project in 2018 with a contract price of $162 million to be received when the project is completed in 2020. During 2018, Indiana incurred $33 million of costs and estimates an additional $85 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenu over time according to the percentage of the project that has been completed. Suppose that, in 2019, Indiana incurred additional costs of $64 million and estimated an additional $51 million in costs to complete the project. Indiana (Do not round you percentage calculated): Multiple Choice Recognized $3.00 million loss on the project in 2019. Recognized $6.13 million gross profit on the project in 2019. Recognized $3.13 million loss on the project in 2019. Recognized $3.13 million gross profit on the project in 2019.
Q: On June 15, 2021, Sanderson Construction entered into a long-term construction contract to build a…
A: Under construction costing the revenue can be recognized either on the percentage of completion…
Q: On July 1, 2020, Oriole Construction Company Inc. contracted to build an office building for Gumbel…
A:
Q: During 2021, Cord Builders, Inc. work on a P9,000,000 fixed-price construction contract that was…
A: Completed contract method:- In this method of revenue recognition, revenue and cost does not get…
Q: In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a…
A: A company has to recognize revenue and expenses in the year they are earned and incurred,…
Q: Indiana Co. began a construction project in 2021 with a contract price of $160 million to be…
A: Calculate the gross profit recognized in 2021. Working note: Calculate the percentage of…
Q: Sage Hill Inc. began work on a $10,700,000 non-cancellable contract in 2020 to construct an office…
A: Journal entry: It is prepared to record the financial and non financial transaction of the business…
Q: Pharoah Construction entered into a contract to construct a bridge for a contract price of $2.95…
A: Compute revenue recognized for each year using percentage of completion method as shown below:
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Requirement 4 : 2018 2019 2020 Revenue $ 2,800,000 $ 3,692,964 $…
Q: On July 1, 2020, Torvill Construction Company Inc. contracted to build an office building for Gumbel…
A: Percentage of completion method This method is a concept as part of revenue recognition under which…
Q: In February 2020, Cullumber Construction signed a contract and commenced construction on a parking…
A: Construction Contracts : In this type of questions revenue will be recorded on the basis of % of…
Q: In 2021, Cupid Construction Co. (CCC) began work on a two-year fixed price contract project. CCC…
A: The cash that remains to be collected is calculated by deducting the cash received from the contract…
Q: In 2020, Blue Construction Corp. began construction work under a 3-year contract. The contract price…
A: Construction Contract: The term "construction contract" refers to agreements to do architectural,…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Solution 1: Amount of revenue and gross profit (loss) to be organized in each of three years using…
Q: Suneilert Construction Company had a contract starting April 2021, to construct a P15,000,000…
A: As per the percentage completion method, the revenue and cost of construction contact are recognized…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: 2018 2019 2020 Revenue 3000000 3500000 35000000 Gross profit (loss) 360000 1200000 574000
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Year Actual cost incurred (A) Total cost incurred till date (B) Total estimated Cost ( C ) % of…
Q: Jhun Co. recognizes construction revenues and expenses using the percentage of completion method.…
A: A method under which each and every contract is considered as a cost unit and profit and loss for…
Q: In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a…
A: The percentage of completion method of accounting necessitates time frame reporting of revenues and…
Q: n 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Revenue(each year)=Cost incurred/(total expected cost)*Total expected revenue-Revenue earlier…
Q: Headland Construction Company began work on a $417,500 construction contract in 2020. During 2020,…
A: Under construction process, the revenue or loss can be calculated on the basis of percentage of work…
Q: Diamond Construction which has a calendar year end, has entered into a non-cancellable fixed priced…
A: Calculation for percentage of completion 2019 2020 2021 Cost incurred upto date (A) 1,850,000…
Q: Indiana Co. began a construction project in 2021 with a contract price of $162 million to be…
A: In case of percentage of completion method, revenue is recognized over duration of contract based on…
Q: percentage of completion method
A: Gross income for the year = Contract price * Cost incurred during the year/Expected total cost
Q: In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000.…
A:
Q: In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a…
A: A company has to recognize revenue and expenses in the year they are earned and incurred,…
Q: In 2020, Steinrotter Construction Corp. began construction work under a 3-year contract. The…
A:
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: Percentage completion method: The percentage of completion method is one of method used in…
Q: In February 2020, Sandhill Construction signed a contract and commenced construction on a parking…
A: 30-09-2020 30-09-2021 Cost Incurred till date 20,750,000 40,200,000 Billings in Progress…
Q: In 2018, SM Residences entered into a 3-year agreement in to construct a condominium project for a…
A: Percentage of completion of project is the ratio between the amount of construction completed and…
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: NOTE : As per BARTLEBY guidelines, when multiple sub parts of the question are given, then first…
Q: At the beginning of 2021, the Harding Construction Company received a contract to build an office…
A: Long period contract costing deals with the accounting treatment of income and expenses of a…
Q: Cullumber Construction Company had a contract starting April 2021, to construct a $43000000 building…
A: % completed = Cost incurred / Estimated cost % completed = $18124000 / $39400000 % completed = 46%
Q: How much is the Gross Profit/Loss Realized in 2018? Celestial Holdings Co. began constructing a…
A: There are 2 methods of accounting for long-term contracts:- Completed contract method Percentage of…
Q: During 2019, Gulf Co. started a construction project with a total contract price of $3,500,000.…
A: Expected Revenue from Construction Contract 3,500,000 Less: Actual Cost Incurred…
Q: [The following information applies to the questions displayed below.] In 2021, the Westgate…
A:
Q: Grouper, Inc. began work on a $6,491,000 contract in 2020 to construct an office building. During…
A: Calculate gross profit: Particulars Amount Cost incurred during the year (1) $1,941,020 Cost…
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: Journal Entry: Journal entry has two effects for every transaction. The journal entry is passed by…
Q: REQUIRED: a) Using percentage-of-completion method, prepare schedules to compute the profit and…
A: The amount earned from the business operation is known as operating income, but when the expenses to…
Q: On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to…
A: "Since you have posted a question with multiple sub parts, we will solve first three sub parts for…
Q: Kingbird Construction Company began work on a $418,500 construction contract in 2020. During 2020,…
A: Cost till date (a) $ 2,85,500 Further expense (b) $ 1,55,765 Total expense ( a+ b ) $…
Q: Franklin Construction entered into a fixed-price contract to build a freeway-connecting ramp for $30…
A: Following are the calculation of gross profit or loss recognized in 1st year if recognize revenue…
Q: MacDonalds Construction Co. was a low bidder on a construction project to build a dam for…
A: Under contract costing, the percentage of completion method revenues and expenses are recognized on…
Q: [The following information applies to the questions displayed below.] In 2021, the Westgate…
A: Step 2 in solution
Q: In 2019, Tarlo Company agrees to construct a highway for Brice County over a 3-year period (2019…
A:
Q: In 2018, the Laguna Inc entered into a contract to construct a road for 5th Avenue for $14,000,000.…
A: The percentage of completion method is a revenue recognition accounting concept that evaluates how…
Q: In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: Journal entries refers to the systematic documentation of the financial transactions of a company in…
Q: In 2018, the Westgate Construction Company entered into a contract to construct a road for Santa…
A: A balance sheet is a financial statement that presents a company's assets, liabilities and…
Q: Cullumber, Inc. began work on a $7,164,000 contract in 2020 to construct an office building. During…
A: Percentage-of-completion method indicates a method of reporting revenue for the year which is…
Q: In February 2020, Sheridan Construction signed a contract and commenced construction on a parking…
A: A journal entry is a practice of recording or maintaining track of some financial or non-financial…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?Indiana Co. began a construction project in 2021 with a contract price of $150 million to be received when the project is completed in 2023. During 2021, Indiana incurred $36 million of costs and estimates an additional $84 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed.Indiana Co. began a construction project in 2018 with a contract price of $160 million to be received when the project is completed in 2020. During 2018, Indiana incurred $36 million of costs and estimates an additional $82 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2019, Indiana incurred additional costs of $66 million and estimated an additional $54 million in costs to complete the project. Indiana (Do not round your percentage calculated): Multiple Choice Recognized $13.2 million gross profit on the project in 2019. Recognized $10.2 million loss on the project in 2019. Recognized $3.00 million loss on the project in 2019. Recognized $10.2 million gross profit on the project in 2019.
- Indiana Company began a construction project in 2024 with a contract price of $165 million to be received when the project is completed in 2026. During 2024, Indiana incurred $37 million of costs and estimates an additional 87 million of costs to complete the project Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed In 2025Indiana incurred additional costs of $57 million and estimated an additional $39 million in costs to complete the projectIndianaIn 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Costs incurred during the year Estimated costs to complete as of year-end Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2022 2021 $2,184,000 $3,510,000 5,616,000 2,106,000 2021 2,120,000 1,860,000 2022 . Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years assuming the following costs curred and costs to complete information. (Do not round intermediate calculations and round your final answers to the nearest hole dollar amount. Loss amounts should be indicated with a minus sign.) 2021 $2,184,000 5,616,000 2023 2023 $2,316,600 3,574,000 4,306,000…In 2024, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2026. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. Note: Do not round intermediate calculations. Loss amounts should be indicated with a minus sign. Answer is complete and correct. 2024 $ 2,400,000 5,600,000 2,000,000 1,800,000 2024 $ 3,000,000 $ $ 600,000 $ 2025 2026 4,500,000 $ 2,500,000 900,000 $ 300,000 2025 $ 3,600,000 2,000,000 4,000,000 3,600,000 2026 $ 2,200,000 0 4,000,000 4,600,000
- In 2024, KP Building Incorporated began work on a four-year construction project (called Cincy One). The contract price is $460 million. KP recognizes revenue on this contract over time according to percentage of completion. At the end of 2024, the following financial statement information indicates the results to date for Cincy One: INCOME STATEMENT: Gross profit (before-taxes) recognized in 2024 $ 43 million BALANCE SHEET: Accounts receivable from construction billings $ 30 million Construction in progress $ 86 million Less: Billings on construction $ (96 million) Net billings in excess of construction in progress $ 10 million Required: Compute the following, placing your answer in the spaces provided and showing supporting computations below. Note: Round your percentage answer to the nearest whole number. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).Indiana Company began a construction project in 2024 with a contract price of $162 million to be received when the project is completed in 2026 During 2024 Indiana incurred $35 million of costs and estimates an additional $15 million of costs to complete the project Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed in 2025, Indiana incurred additional costs of $59 milion and estimated an additional $38 million in costs to complete the project indiana Note: Do not round intermediate calculations. Multiple Choice recognized $911 milion gross profe on the project in 2025 recognized $9.00 million gross prefit on the project in 2025 ced $3000 mon gress profe on the project in 2025In 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2024 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2024 $ 135 Cash collected on project during 2024 $ 105 Construction in progress, 12/31/2024 $ 207 Estimated percentage of completion during 2024 60% What were the construction billings by CCC during 2024?
- In 2024, Cupid Construction Company (CCC) began work on a two-year fixed price contract project. CCC recognizes revenue over time according to percentage of completion for this contract, and provides the following information (dollars in millions): Accounts receivable, 12/31/2024 (from construction progress billings) $ 37.5 Actual construction costs incurred in 2024 $ 135 Cash collected on project during 2024 $ 105 Construction in progress, 12/31/2024 $ 207 Estimated percentage of completion during 2024 60% What are CCC's estimated remaining construction costs on the project at the end of 2024?Bartov Corporation agreed to build a warehouse for $2,500,000. Expected (and actual) costs for the warehouse follow : 2019, $400,000; 2020, $1,000,000; and 2021, $500,000. The company completed the warehouse in 2021. Compare revenues, expenses, and income for each year 2019 through 2021 assuming that Bartov’s performance obligation for the warehouse is fulfilled over time and that the costs incurred provide a close approximation of the value conveyed to the customer.Khodra Construction had a contract starting April 2021, to construct a $9,000,000 highway that is expected to be completed in September 2023, at an estimated cost of $8,250,000. At the end of 2021, the costs to date were $3,795,000 and the estimated total costs to complete had not changed. The progress billings during 2021 were $1,800,000 and the cash collected during 2021 was 1,200,000. What amount of Construction in Process should Khodra Construction have reported at December 31, 2021? $