Marvel Parts, Incorporated, manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company uses a standard cost system for all of its products. According to the standards that have been set for the seat covers, the factory should work 980 hours each month to produce 1,960 sets of covers. The standard costs associated with this level of production are: Direct materials Direct labor Variable manufacturing overhead (based on direct labor-hours) Total $ 32,340 $ 6,860 $ 1,960 Direct materials (6,000 yards) Direct labor Variable manufacturing overhead Per Set of Covers $16.50 3.50 During August, the factory worked only 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were recorded during the month: Total $ 34,020 $ 7,770 $ 3,990 1.00 $ 21.00 Per Set of Covers $16.20 3.70 1.90 $ 21.80 At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in production. Required: 1. Compute the materials price and quantity variances for August. 2. Compute the labor rate and efficiency variances for August. 3. Compute the variable overhead rate and efficiency variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)

Principles of Accounting Volume 2
19th Edition
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax
Chapter6: Activity-based, Variable, And Absorption Costing
Section: Chapter Questions
Problem 13EA: Tri-bikes manufactures two different levels of bicycles: the Standard and the Extreme. The total...
icon
Related questions
icon
Concept explainers
Topic Video
Question
Marvel Parts, Incorporated, manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted
to fit nearly any small car. The company uses a standard cost system for all of its products. According to the standards that have been
set for the seat covers, the factory should work 980 hours each month to produce 1,960 sets of covers. The standard costs associated
with this level of production are:
Direct materials
Direct labor
Variable manufacturing overhead (based
on direct labor-hours)
Total
$ 32,340
$ 6,860
$ 1,960
Direct materials (6,000 yards)
Direct labor
Variable manufacturing overhead
Per Set of
Covers
$16.50
3.50
During August, the factory worked only 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were
recorded during the month:
Total
$ 34,020
$ 7,770
$ 3,990
1.00
$ 21.00
Per Set of
Covers
$16.20
3.70
1.90
$ 21.80
At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in
production.
Required:
1. Compute the materials price and quantity variances for August.
2. Compute the labor rate and efficiency vařiances for August.
3. Compute the variable overhead rate and efficiency variances for August.
(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero
variance). Input all amounts as positive values.)
Transcribed Image Text:Marvel Parts, Incorporated, manufactures auto accessories. One of the company's products is a set of seat covers that can be adjusted to fit nearly any small car. The company uses a standard cost system for all of its products. According to the standards that have been set for the seat covers, the factory should work 980 hours each month to produce 1,960 sets of covers. The standard costs associated with this level of production are: Direct materials Direct labor Variable manufacturing overhead (based on direct labor-hours) Total $ 32,340 $ 6,860 $ 1,960 Direct materials (6,000 yards) Direct labor Variable manufacturing overhead Per Set of Covers $16.50 3.50 During August, the factory worked only 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were recorded during the month: Total $ 34,020 $ 7,770 $ 3,990 1.00 $ 21.00 Per Set of Covers $16.20 3.70 1.90 $ 21.80 At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in production. Required: 1. Compute the materials price and quantity variances for August. 2. Compute the labor rate and efficiency vařiances for August. 3. Compute the variable overhead rate and efficiency variances for August. (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
es
vaLiaoke maturny uVELIiedu (uaaரப்
on direct labor-hours)
Direct materials (6,000 yards)
Direct labor
Variable manufacturing overhead
$ 1,960
During August, the factory worked only 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were
recorded during the month:
Total
$ 34,020
$ 7,770
$ 3,990
1.00
$ 21.00
1. Materials price variance
1. Materials quantity variance
2. Labor rate variance
2. Labor efficiency variance
3. Variable overhead rate variance
3. Variable overhead efficiency variance
Per Set of
Covers
At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in
production.
$ 16.20
3.70
1.90
$ 21.80
Required:
1. Compute the materials price and quantity variances for August.
2. Compute the labor rate and efficiency variances for August.
3. Compute the variable overhead rate and efficiency variances for August.
U
U
F
U
(Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero
variance). Input all amounts as positive values.)
Transcribed Image Text:es vaLiaoke maturny uVELIiedu (uaaரப் on direct labor-hours) Direct materials (6,000 yards) Direct labor Variable manufacturing overhead $ 1,960 During August, the factory worked only 1,000 direct labor-hours and produced 2,100 sets of covers. The following actual costs were recorded during the month: Total $ 34,020 $ 7,770 $ 3,990 1.00 $ 21.00 1. Materials price variance 1. Materials quantity variance 2. Labor rate variance 2. Labor efficiency variance 3. Variable overhead rate variance 3. Variable overhead efficiency variance Per Set of Covers At standard, each set of covers should require 2.5 yards of material. All of the materials purchased during the month were used in production. $ 16.20 3.70 1.90 $ 21.80 Required: 1. Compute the materials price and quantity variances for August. 2. Compute the labor rate and efficiency variances for August. 3. Compute the variable overhead rate and efficiency variances for August. U U F U (Indicate the effect of each variance by selecting "F" for favorable, "U" for unfavorable, and "None" for no effect (i.e., zero variance). Input all amounts as positive values.)
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Costing Systems
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Accounting Volume 2
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning