of F. E is an immediate predecessor of F. The activity durations are D=4, E=3, F=9. A. the critical path is D-E-F, duration 13 B. the critical path is D-F, duration 16 C. slack at D is 3 units D. slack at E is 3 units E. none of the above Which of the following is the best example of competing on low-cost leadership? A. A firm offers more reliable products than its competitors. B. A firm's products are introduced into the market faster than its competitors. C.A firm's research and development department generates many ideas for new products. D. A firm produces its product with less raw material waste than its competitors. E. A firm advertises more than its competitors. Which of the following services is least likely to be unique, i.e., customized to a particular individual's needs? A. elementary education B. computer consulting C. legal services D. hairdressing E. dental care
Critical Path Method
The critical path is the longest succession of tasks that has to be successfully completed to conclude a project entirely. The tasks involved in the sequence are called critical activities, as any task getting delayed will result in the whole project getting delayed. To determine the time duration of a project, the critical path has to be identified. The critical path method or CPM is used by project managers to evaluate the least amount of time required to finish each task with the least amount of delay.
Cost Analysis
The entire idea of cost of production or definition of production cost is applied corresponding or we can say that it is related to investment or money cost. Money cost or investment refers to any money expenditure which the firm or supplier or producer undertakes in purchasing or hiring factor of production or factor services.
Inventory Management
Inventory management is the process or system of handling all the goods that an organization owns. In simpler terms, inventory management deals with how a company orders, stores, and uses its goods.
Project Management
Project Management is all about management and optimum utilization of the resources in the best possible manner to develop the software as per the requirement of the client. Here the Project refers to the development of software to meet the end objective of the client by providing the required product or service within a specified Period of time and ensuring high quality. This can be done by managing all the available resources. In short, it can be defined as an application of knowledge, skills, tools, and techniques to meet the objective of the Project. It is the duty of a Project Manager to achieve the objective of the Project as per the specifications given by the client.
Step by step
Solved in 2 steps