Parcial 3 4 25 points Skipped eBook Required information Save & Exit Submit [The following information applies to the questions displayed below] Lauder Company manufactures and distributes various fixtures used primarily in new building construction. At the company's Bayside plant, Lauder produces two models of one widely used fixture designated by model names LC-20 and LC-50. Currently, the Bayside plant uses direct labor-hours to allocate manufacturing overhead costs to products. The vice president-manufacturing (VP-M) at Lauder has recently been considering updates to the company's costing systems as a way to ensure that managers had the best information available for decision making. However, rather than update throughout the entire firm, the VP-M and CFO agreed to test an ABC system. Because of its size and focus, the Bayside plant was selected for the experiment. An ABC study team, consisting of both plant and corporate employees was formed to propose an ABC system and compare the product costs with those reported by the current system. Based on the experiment, the executives at Lauder will decide whether to roll out the new cost system to the entire company. The study team identified four cost pools into which the manufacturing overhead costs could be grouped. There was a great deal of discussion about both the pools and the cost drivers. The final system selected consisted of the following pools and drivers. The costs were based on the forecasts for the coming year. Activity Drivers Machine-hours Cost Fools Costs Material inspection $ 475,200 Direct material cost References Assembly 2,652,000 Equipment setup 948.000 Packaging and shipping Production runs 584,999 Units shipped Data for production of the two products at the Bayside plant for the coming year of operations follows: Total direct material costs Total direct labor costs Total machine-hours Total number of production runs Number of units produced and shipped Products LC-20 $640,000 $504,000 LC-50 $216,000 110,550 10 288,000 $252,000 55.200 72.000 All direct labor at the Bayside plant is paid $35 per hour. The study team decides to look more closely at the assembly activity and determines that it can be broken down into two activities: production and engineering. Production covers the costs of ongoing manufacturing while engineering includes those activities dealing with design changes, equipment calibration, and so on. The costs attributed to production are $1,989,000, and the costs attributed to engineering are $663,000. After discussion with plant engineers, the team decides that although machine-hours are an appropriate cost driver for production, the best cost driver for engineering is setups because most of the work arises from changes in the way the product is run Required: a-1. Compute the totals of the cost driver rates shown below. a-2. What unit product costs will be reported for the two products if the revised ABC system is used? Complete this question by entering your answers in the tabs below. Req A1 Reg A2 Compute the totals of the cost driver rates shown below. Note: Round "Packaging and shipping" answer to 2 decimal places. Material inspection Production Engineering Equipment setup Packaging and shipping % of material dollars per hour per setup Mc Graw < Prev or 4 田 Next >

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter4: Activity-based Costing
Section: Chapter Questions
Problem 36P: Reducir, Inc., produces two different types of hydraulic cylinders. Reducir produces a major...
Question
None
Parcial 3
4
25
points
Skipped
eBook
Required information
Save & Exit
Submit
[The following information applies to the questions displayed below]
Lauder Company manufactures and distributes various fixtures used primarily in new building construction. At the
company's Bayside plant, Lauder produces two models of one widely used fixture designated by model names LC-20 and
LC-50. Currently, the Bayside plant uses direct labor-hours to allocate manufacturing overhead costs to products.
The vice president-manufacturing (VP-M) at Lauder has recently been considering updates to the company's costing
systems as a way to ensure that managers had the best information available for decision making. However, rather than
update throughout the entire firm, the VP-M and CFO agreed to test an ABC system. Because of its size and focus, the
Bayside plant was selected for the experiment. An ABC study team, consisting of both plant and corporate employees was
formed to propose an ABC system and compare the product costs with those reported by the current system. Based on
the experiment, the executives at Lauder will decide whether to roll out the new cost system to the entire company.
The study team identified four cost pools into which the manufacturing overhead costs could be grouped. There was a
great deal of discussion about both the pools and the cost drivers. The final system selected consisted of the following
pools and drivers. The costs were based on the forecasts for the coming year.
Activity Drivers
Machine-hours
Cost Fools
Costs
Material inspection
$ 475,200
Direct material cost
References
Assembly
2,652,000
Equipment setup
948.000
Packaging and shipping
Production runs
584,999 Units shipped
Data for production of the two products at the Bayside plant for the coming year of operations follows:
Total direct material costs
Total direct labor costs
Total machine-hours
Total number of production runs
Number of units produced and shipped
Products
LC-20
$640,000
$504,000
LC-50
$216,000
110,550
10
288,000
$252,000
55.200
72.000
All direct labor at the Bayside plant is paid $35 per hour.
The study team decides to look more closely at the assembly activity and determines that it can be broken down into two activities:
production and engineering. Production covers the costs of ongoing manufacturing while engineering includes those activities dealing
with design changes, equipment calibration, and so on.
The costs attributed to production are $1,989,000, and the costs attributed to engineering are $663,000. After discussion with plant
engineers, the team decides that although machine-hours are an appropriate cost driver for production, the best cost driver for
engineering is setups because most of the work arises from changes in the way the product is run
Required:
a-1. Compute the totals of the cost driver rates shown below.
a-2. What unit product costs will be reported for the two products if the revised ABC system is used?
Complete this question by entering your answers in the tabs below.
Req A1
Reg A2
Compute the totals of the cost driver rates shown below.
Note: Round "Packaging and shipping" answer to 2 decimal places.
Material inspection
Production
Engineering
Equipment setup
Packaging and shipping
% of material dollars
per hour
per setup
<RgA1
Reg A2 >
Mc
Graw
< Prev
or 4 田
Next >
Transcribed Image Text:Parcial 3 4 25 points Skipped eBook Required information Save & Exit Submit [The following information applies to the questions displayed below] Lauder Company manufactures and distributes various fixtures used primarily in new building construction. At the company's Bayside plant, Lauder produces two models of one widely used fixture designated by model names LC-20 and LC-50. Currently, the Bayside plant uses direct labor-hours to allocate manufacturing overhead costs to products. The vice president-manufacturing (VP-M) at Lauder has recently been considering updates to the company's costing systems as a way to ensure that managers had the best information available for decision making. However, rather than update throughout the entire firm, the VP-M and CFO agreed to test an ABC system. Because of its size and focus, the Bayside plant was selected for the experiment. An ABC study team, consisting of both plant and corporate employees was formed to propose an ABC system and compare the product costs with those reported by the current system. Based on the experiment, the executives at Lauder will decide whether to roll out the new cost system to the entire company. The study team identified four cost pools into which the manufacturing overhead costs could be grouped. There was a great deal of discussion about both the pools and the cost drivers. The final system selected consisted of the following pools and drivers. The costs were based on the forecasts for the coming year. Activity Drivers Machine-hours Cost Fools Costs Material inspection $ 475,200 Direct material cost References Assembly 2,652,000 Equipment setup 948.000 Packaging and shipping Production runs 584,999 Units shipped Data for production of the two products at the Bayside plant for the coming year of operations follows: Total direct material costs Total direct labor costs Total machine-hours Total number of production runs Number of units produced and shipped Products LC-20 $640,000 $504,000 LC-50 $216,000 110,550 10 288,000 $252,000 55.200 72.000 All direct labor at the Bayside plant is paid $35 per hour. The study team decides to look more closely at the assembly activity and determines that it can be broken down into two activities: production and engineering. Production covers the costs of ongoing manufacturing while engineering includes those activities dealing with design changes, equipment calibration, and so on. The costs attributed to production are $1,989,000, and the costs attributed to engineering are $663,000. After discussion with plant engineers, the team decides that although machine-hours are an appropriate cost driver for production, the best cost driver for engineering is setups because most of the work arises from changes in the way the product is run Required: a-1. Compute the totals of the cost driver rates shown below. a-2. What unit product costs will be reported for the two products if the revised ABC system is used? Complete this question by entering your answers in the tabs below. Req A1 Reg A2 Compute the totals of the cost driver rates shown below. Note: Round "Packaging and shipping" answer to 2 decimal places. Material inspection Production Engineering Equipment setup Packaging and shipping % of material dollars per hour per setup <RgA1 Reg A2 > Mc Graw < Prev or 4 田 Next >
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub