Start 5- E 4: By using PERT draw the network diagram and determine Te, S, V, C. P for the following Assume D= 45weeks. Activities path 1-2 1-3 2-4 3-4 End A B C D To Tm Tp 12 18 12 16 3 6 4 8 8 12 12

Operations Research : Applications and Algorithms
4th Edition
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Wayne L. Winston
Chapter9: Integer Programming
Section9.6: Solving Combinatorial Optimization Problems By The Branch-and-bound Method
Problem 3P
icon
Related questions
Question
Q3: For the following network diagram find critical path and critical time
2
2
Start
3
24: By using PERT draw the network diagram and determine Te, S,V, C. P for the following
Assume D= 45weeks.
Activities path To
1-2
3
1-3
6
2-4
4
3-4
8
End
A
B
C
D
Tm Tp
6
12
12
18
8
12
12
16
Transcribed Image Text:Q3: For the following network diagram find critical path and critical time 2 2 Start 3 24: By using PERT draw the network diagram and determine Te, S,V, C. P for the following Assume D= 45weeks. Activities path To 1-2 3 1-3 6 2-4 4 3-4 8 End A B C D Tm Tp 6 12 12 18 8 12 12 16
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Properties of Different Architectures
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Operations Research : Applications and Algorithms
Operations Research : Applications and Algorithms
Computer Science
ISBN:
9780534380588
Author:
Wayne L. Winston
Publisher:
Brooks Cole