The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $200 per day penalty for each day the project lasts beyond day 16. Crash Cost (5) 1.000 2.200 1.500 1,500 1,500 1,400 1,000 500 a. What is the projects duration if only normal times are used? The project duration is 22 day(s). (Enter your response as an integer) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day(s). (Enter your response as an integer) Activity B C D E F G H Normal Time (days) 4 5 5 3 4 2 3 5 Normal Cost (5) 800 1,000 500 1,200 1,500 1,300 900 300 Crash Time (days) 3 3 3 2 4 1 1 3 Immediate Predecessor(s) AB 8 C.D. E E G

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 21P
icon
Related questions
Question
The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $200 per day penalty for each day the project lasts beyond day 16.
Normal Time
(days)
4
Crash Time
(days)
3
3
Crash Cost
($)
1,000
2,200
1,500
5
5
3
3
2
1,500
4
4
1,500
2
1
1,400
1
1,000
3
500
a. What is the project's duration if only normal times are used?
The project duration is 22 day(s). (Enter your response as an integer.)
b. What is the minimum-cost schedule?
With the minimum-cost schedule, the project duration is day(s). (Enter your response as an integer)
Activity
A
8
C
D
E
F
G
H
3
5
Normal Cost ($)
800
1,000
500
1,200
1.500
1,300
900
300
Immediate
Predecessor(s)
-
AB
B
C. D
E
E
G
Transcribed Image Text:The Advanced Tech Company has a project to design an integrated information data base for a major bank. Data for the project are given in the following table. Indirect project costs amount to $250 per day. The company will incur a $200 per day penalty for each day the project lasts beyond day 16. Normal Time (days) 4 Crash Time (days) 3 3 Crash Cost ($) 1,000 2,200 1,500 5 5 3 3 2 1,500 4 4 1,500 2 1 1,400 1 1,000 3 500 a. What is the project's duration if only normal times are used? The project duration is 22 day(s). (Enter your response as an integer.) b. What is the minimum-cost schedule? With the minimum-cost schedule, the project duration is day(s). (Enter your response as an integer) Activity A 8 C D E F G H 3 5 Normal Cost ($) 800 1,000 500 1,200 1.500 1,300 900 300 Immediate Predecessor(s) - AB B C. D E E G
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 6 steps with 1 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,