The demand for the product is 275,000 parts per week. a) Determine the TAKT time for the process and explain briefly what this means. b) Determine the number of workers required for the process.

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question
A process is scheduled to run 24 hours every weekday across 3 shifts. Each shift gets a 20-minute break. There is also a 10-minute production meeting at the start of each shift. The total operation time for 1
part is 0.8 minute.
The demand for the product is 275,000 parts per week.
a) Determine the TAKT time for the process and explain briefly what this means.
b) Determine the number of workers required for the process.
Transcribed Image Text:A process is scheduled to run 24 hours every weekday across 3 shifts. Each shift gets a 20-minute break. There is also a 10-minute production meeting at the start of each shift. The total operation time for 1 part is 0.8 minute. The demand for the product is 275,000 parts per week. a) Determine the TAKT time for the process and explain briefly what this means. b) Determine the number of workers required for the process.
Expert Solution
steps

Step by step

Solved in 3 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,