what would happen to the completion time.
Q: example of cost control for project
A: Cost Control A tool which is used by the organization’s management in controlling and regulating the…
Q: B. What is the expected project completion time? 7 weeks 8 weeks 9 weeks 6 weeks C. Which are the…
A: In this question, I would construct the Gantt chart based on the given Activity ID, Activity…
Q: 13.39 Activity A is worth $500, is complete, and actually cost $500. Activity B is worth $1.000, is…
A: Earned Value (EV) is the sum of percentage completed multiplied by the task budget. The calculation…
Q: What is a due date?
A: In general, the due date is like if purchased certain material for production purpose on credit…
Q: Discussion on reasons of lowering productivity Conclusion In PROJECT MANAGEMENT
A: Productivity is defined as the ratio between the output volume and the volume of inputs. It measures…
Q: What is a work breakdown structure, and how does one create one? What are the tools and inputs…
A: In this question. Would define the WBS or Work breakdown structure, Next, I would write the steps to…
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: Ssus and the management at yankee ltd. Want an expected time and variance for pest control activity…
A: Given: Optimistic time (a) = 2 weeks Pessimistic time (b) = 8 weeks Most likely Time (m) = 4 weeks…
Q: Question 37 How much slack is there in task A? Your Answer: Your Answer Question 38 If the crash…
A: Slack is the available time in a activity for delaying the project without affecting the total…
Q: james is replacing the window of a commercial passenger aircraft, but realises that he doesn’t quite…
A: Ethics is described as a discipline that deals with what is bad and what is good and also highlights…
Q: The FWO has just made the winning bid of 54 million Rs. to construct a new Building. Company has…
A: Master Working Sheet as mentioned-
Q: What is the completion time ?
A: Completion time is the time when the project completes all the activities involved and accomplish…
Q: An activity originally estimated to cost $100,000 and require 30 weeks to complete. Now the activity…
A: Earned value is the measurement of completed work from the total plan of the project.
Q: From a project resource management context, discuss the significance of a Work Breakdown Structure…
A: A work breakdown structure is a project management approach for completing a difficult, multi-step…
Q: project. She analyzes the tasks involved in making the app and produces the PERT chart umbers…
A: This various paths are the possible ways of making the health app for the company who wants to enter…
Q: Q1:- The timetable for one of the projects was as in Table No. (1), answer the following: 1- Draw…
A: Below is the solution:-
Q: What is the role of capacity in the management of projects?
A: It is a system of allocating resources to achieve maximum productivity. It also helps us determine…
Q: d. Determine the probability that the team and the contractor will be in place and the project…
A: Based on the 3-time estimates given, we find the Expected duration and Variance for each activity as…
Q: What is meant by the need to make trade-offs between cost, performance, and schedule? Give examples.
A: To be recognised as a success, programmes must reach budget, timeline, protection, and efficiency…
Q: How does the Work Breakdown Structure differ from the project network?
A: Work Breakdown structure is the clear breakdown of the entire working processes of the project into…
Q: completion time is 31 weeks. What is the be nuch will it cost? Show your work. Activity Expected…
A: Given: Each company takes 1 week to complete the project. Cost per activity to crash is $200…
Q: (f) What is the largest number of weeks allotted to finish the electrical wirings without delaying…
A: Below is the solution:-
Q: Task Name Normal time Normal Crash time Crash cost (slope) Predecessor cost 4. 85 3. 10 5. 100 4. 30…
A: We are using Forward pass method to solve below problem. Forward pass is a strategy to push ahead…
Q: Sushant and his team of frenco Ltd. Want to ascertain the expected time and variance for an Activity…
A: Given : Optimistic Time (a) - 2 weeks Pessimistic time (b) - 8 weeks Most likely time (m) - 3 weeks…
Q: a) Briefly describe what is meant by the term 'Work Breakdown Structure' (WBS), when applied to…
A: CPM stands for Critical Path Method, which was invented by DuPont and first used in the chemical…
Q: days. Carl's team should be able to complete the project in
A: A network diagram is the graphical representation of project activities and shows their duration of…
Q: 11- What is the time to complete the project that achieves the probability of its magnitude? 16.5
A: z-score is calculated as the difference between the expected duration of the project and the actual…
Q: A renovation of the gift shop at Orlando Amway Center has six activities (in hours). For the…
A: Given data is
Q: Define Time–Cost Models and Project Crashing?
A: Project crashing Project crushing refers to the process of reducing the project duration by…
Q: what is the difference between work package and wbs?
A: Introduction of work package A work package is a group of related tasks within a project. Because…
Q: 3- The value of the variance of the critical path in the project is
A: Variance = square of sum standard deviations of critical activities Standard deviation = (b-a)/6
Q: What constitutes the terms “completion” or “level of effort”?
A: The term 'level of effort' is related to project management. It is a support-type project that does…
Q: 2. Tom Schriber, a director of personnel of Management Resources, Inc., is in the process of…
A: A Project Evaluation and Review Technique (PERT) is a device that projects the board uses to deal…
Q: 5. H,GF 21 Find total duration to finish the project And find critical oath By AoA method 3:33 PM
A: Activity Immediate Predecessors Duration A - 5 B - 12 C A 7 D C…
Q: How do we estimate the likelihood of a project being finished by a certain date? In this…
A: Project Evaluation and Review Technique (PERT) is a technique for evaluating and reviewing projects.…
Q: snip
A: If the early start time of a task is 4 days and its early finish time is 6 days, then the task is 2…
Q: Explain what exactly is a work breakdown structure and how do they produce one ?
A: Project management is a subset of management that entails applying specialized knowledge to provide…
Q: What are Project Scheduling Models, and how are they defined?
A: Scheduling is the process of arranging the production activities in order so that the complete…
Q: What is the expected completion time? What is the critical path? What is the latest that Jersey…
A: A network diagram is visual diagram of activity relationship in a project which helps to identify…
Q: 1. What is the expected (estimated) time for each activity? 2. Based on the calculation of estimated…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Master schedule has the following time fences, in the correct order, Select one: a. Slushy, Frozen &…
A: It is characterized as the time spans arrangement which indicate the kinds of changes all together…
Q: Which of the following activities is NOT considered a project? A. Developing a new software program…
A: Note: Since you have posted multiple independent questions in the same request, we will solve the…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: What is the earliest completion time of the project? days
A: A project network diagram is the process of a project shown visually. It is a diagram that has boxes…
Q: What would a project manager have to do to crash an activity?
A: Project crashing is the point at which you abbreviate the term of a venture by diminishing the hour…
Step by step
Solved in 3 steps with 1 images
- Using PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A В 3 -- C A 7 А, В 3 E 4 F D a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. Early Finish Early Start Task Late Late Slack Start Finish A B C D E F c. What is project completion time?Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4D E F G H Activity A B 100 Predecessor ABB А Crashing - Example Crash Duration 6 A C.E C.D.E.F 2 4 6 5 5 16 Normal Duration 7 3 5 4 1 2 5 4 2 4 a) Use the heuristic procedure to determine the crash schedule. 150 100 Normal Cost 100 100 25 50 b) Given that the indirect project cost is 20TL per day, obtain the cost vs. duration curve. 100 50 Crash Cost 170 150 50 75 180 200 136 200Activity A B CEDFGHJLNMI OKSQ Duration 2 4 3 2 758 31 47 3 11 8 2 4 3 Weeks Followed EFGH DDF By Q J N Q: For the activities shown in the table above, find the time duration of the project and the critical path. Arrange the information E.S, E.F, L.S, L.F, and T.F in a table.
- Consider the following: Activity A < ש ס ח ד B C Normal time 4 W N Crash time Normal cost Crash cost Predecesso 3 1 3 4 3 2 2 2200 2400 500 2200 600 3600 1000 3 8 6 F 3 G 4 What is the cost for crashing the project by 5 days? 2600 2800 500 2600 1200 4200 2000 AB с D.EActivity Predecessor Optimistic Most Likely Pessimistic 14 4 14 B. C A 6. 13 14 D A,B 4 8. 12 10 12 F C,E 5. 11 8 Find the mean and standard deviation of each task in this project then find the following: d) T probability to finish the project in more than 31 weeks. The m- The probability to finish the project in less than 31 or more than 35. g) In how many weeks can we complete the project with 90% probability?Time Immediate Time Activity (weeks) Predecessor(s) Activity (weeks) 5 6 9 7 ABCD 5622 A A Dave's earliest start (ES) and earliest finish (EF) are: Activity A B ооши G H Dave's latest start (LS) and latest finish (LF) are: Activity H ES 0 0 5 5 6 6 11 12 LS 13 EFGH EF 5 6 7 7 11 12 20 19 LF Immediate Predecessor(s) B B C, E D, F
- A project consists of five activities as shown in the following table. Activity Floor sanding Floor buffing Paint mixing Wall painting Ceiling painting Optimistic Time (hr) Most Probable Time (hr) 4 4 0.5 2 3 5 5 Сл 1 3 7.5 Pessimistic Time (hr) 6 6 1.5 10 9 Naturally, the paint mixing precedes the painting activities. Also, both ceiling painting and floor sanding must be done prior to floor buffing. (a) Construct the PERT/CPM network for this problem.Activity A B CDEFG 3. You have been appointed as the project leader of a project to be undertaken by your company. You have identified the following tasks and made the time estimates for each task as listed in the table below: с Preceding "from" activity A A A B,C C,D,E F Succeeding "to" activity B,C,D E E F F G Estimated duration work days) 3 5 3 10 8 14 7 a) Use the above table to construct a project network diagram. b) Determine the critical path for the project and its duration.11. Using PERT, Adam Munson was able to determine that the expected project completion time for the construction of a pleasure yacht is 24 months, and the project variance is 4. Part 2 a) The probability that the project will be completed in 20 months = ______ (round your response to four decimal places)