which of the following do you need to know to calculate the IRR of a project?. 1. project's estimated cash flows 2. project's level of risk 3. project's required rate of return 4. project's NPV a. 1 and 2 b. 4 only c. 1,2 and 3 d. 1 only e. 2 only
Q: nternal rate of return For the project shown in the following table, calculate the internal rate…
A: IRR is rate at which net present value of the cash flows will be equal to 0 it is calculated using…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: WACC is the required rate of return, where as IRR is the actual rate of return of the project. NPV…
Q: How many of the following investment criteria always use all of a project's cash flows in their…
A: Capital budgeting techniques are used to determine whether the projects undertaken are profitable to…
Q: c) Project E, Project F and Project G are independent projects with conventional cash flows. The…
A: Capital budgeting is a financial process of evaluating investments in capital projects in terms of…
Q: dependent capital investment project requires an initial cash outflow at time 0, followed by cash…
A: NPV is net present value that is difference between present value of cash flow and initial cash flow…
Q: What do you know about the mathematical value of the internal rate of return of a project under each…
A: Internal rate of return(IRR) is rate at which net present value(NPV) of project is equal to zero or…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Statement A: FALSE Because project NPV is found by discounting the cash inflows at a discount rate…
Q: Which of the following should you focus when assessing the NPV of a project for a MNC? I.…
A: Net Present Value (NPV) is the technique of capital budgeting which defines the profitability of the…
Q: Which of the following projects have conventional cash-flow streams? Select all that are…
A: Solution:- Conventional cash flow stream is that cash flow stream in which the sign of cash flows…
Q: fe of the project. Which one of the following statements is correct with respect to this…
A: NPV Method assumes that all the cash flows are reinvested at the company's Cost of Capital. IRR…
Q: Which of the statements below is TRUE regarding capital budgeting? O A. Capital budgeting deals with…
A:
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Since the higher the rate would be lower would be the present value factor..... which means the…
Q: Consider the following two sets of project cash flows: Project Year 0 Year 1 Year 2 Year 3 Year 4…
A: a) It is assumed that both the project is mutually exclusive. The correct investment decision and…
Q: 1) In IRR method the cash flows from a project are reinvested at the cost of capital. II) IRR is the…
A: Answer is A. III and I Explanation- I) In IRR method the cash flows from a project are reinvested…
Q: What is the net present value of a project with the following cash flows and a required return of…
A: NPV is the sum of present value of future cashflows PV = cashflow/(1+rate)^year
Q: Consider a project with the following cash-flows: ime Cash-flow t=1 t=2 t=3 3 t=0 -10 2 What is the…
A: “Hey, since there are multiple questions posted, we will answer first question. If you want any…
Q: onsider the following two mutually exclusive projects: When (at what levels of the cost of capital)…
A: Calculating IRR and cross over rate IRR is the rate at which NPV is zero
Q: Consider a project with the following cash-flows: Time Cash-flow t=0 t=1 t=2 t=D3 -10 2 What is the…
A: “Hey, since there are multiple questions posted, we will answer first question. If you want any…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: It refers to the rate of return that is computed by the company to make a decision of selection of a…
Q: mpute the NPV for Project X and accept or reject the project with the cash flows shown below if the…
A: Net present value or NPV is excess of present value of cash inflows over present value of cash…
Q: Which of the following is/are true for the average accounting return method of project analysis? I.…
A: Average Accounting Rate of return is used for capital budgeting decision for a project. The Average…
Q: Define “the stand-alone principle” applying in evaluating projects and discuss the types of…
A: Company's management discretion is to set the company's capital structure that is applicable at the…
Q: Net present value (NPV) is one method that can be used evaluate the financial viability of potential…
A: Data given:: Initial investment = $ 190,000 Annual cash flow = $ 58,000 n…
Q: Consider the following two sets of project cash flows: Project Year 0 Year 1 Year 2 Year 3 Year…
A: Here, Project Year 0 Year 1 Year 2 Year 3 Year 4 Year 5 Year 6 Discount rate X -830 145 158 193…
Q: Projects A and B have approximately the same NPV. Their initial outlays are similar in size. Project…
A: The question is based on the concept of capital budgeting approaches for selection of project in…
Q: Mathematically, we can determine the rate of return for a given project’s cash flow series by…
A: When Cash Flows are discounted by using Internal Rate of Return for a period of cash flows held.…
Q: Define capital expenditures and provide examples of capital expenditures. 2. Cash flows for a…
A: As you have asked multiple questions, we will solve the first question as per policy of Bartleby.…
Q: What is the estimated rate of return for n this project
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: Define each of the following terms:b. Incremental cash flow; sunk cost; opportunity cost;…
A: Introduction: This question is related to the concepts of corporate finance. Corporate money…
Q: ic net present value model of capital budgeting deal with the problem of project risk? What…
A: Introduction : In simple words, net present value refers to the amount that is calculated by…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: We will solve this problem by eliminating each option. 1) option a: A project’s NPV is generally…
Q: Consider the following two mutually exclusive projects: When (at what levels of the cost of…
A: We need to calculate IRR and incremental IRR using excel. IRR is rate at which NPV is zero whereas…
Q: How can we develop the cash flow series over the project life based on the assumption of most likely…
A: Below is the cash flow developed on the base of assumption:
Q: Calculating the payback period for a capital project requires knowing which of the following? a.…
A: Payback period = Initial investment/Annual cash inflows
Q: In considering the payback period, ____. a. it considers the time value of money in determining…
A: The term payback period refers to the amount of time required by a project to recover its initial…
Q: a. What is the typical discount rate used with the Net Present Value (NPV) when project risk is the…
A: a) The rate of return the stockholders anticipate to get, or the rate at which the firm borrows,…
Q: a. If your decision rule is to accept the project with the greater IRR, which project should you…
A: Net present value is the difference between the present value of cash inflows and the present value…
Q: Which of the following statements is CORRECT? Assume that the project being considered has normal…
A: Point 1 is not correct as IRR is not found using this method. Cash flows cannot be compounded at…
which of the following do you need to know to calculate the IRR of a project?.
1. project's estimated cash flows
2. project's level of risk
3. project's required
4. project's NPV
a. 1 and 2
b. 4 only
c. 1,2 and 3
d. 1 only
e. 2 only
Companies use capital budgeting techniques to evaluate the projects. IRR is internal rate of return. It is one of capital budgeting techniques.
Step by step
Solved in 3 steps
- 5. IRR (S5.3) Write down the equation defining a project's internal rate of return (IRR). In practice, how is IRR calculated?Dwight Donovan, the president of Campbell Enterprises, is considering two investment opportunities. Because of limited resources, he will be able to invest in only one of them. Project A is to purchase a machine that will enable factory automation; the machine is expected to have a useful life of four years and no salvage value. Project B supports a training program that will improve the skills of employees operating the current equipment. Initial cash expenditures for Project A are $102,000 and for Project B are $47,000. The annual expected cash inflows are $32,178 for Project A and $15,474 for Project B. Both investments are expected to provide cash flow benefits for the next four years. Campbell Enterprises' desired rate of return is 6 percent. (PV of $1 and PVA of $1) (Use appropriate factor(s) from the tables provided.) Required a. Compute the net present value of each project. Which project should be adopted based on the net present value approach? b. Compute the approximate…which of the following could potentially impact the NPV of a project? 1. initial investment amount 2. book value of the initial investment at the end of the project 3. opportunity costs 4. sunk costs a. 1 and 3 b. 1,2,3 and 4 c. 1,2 and 3 d. 1,2 and 4 e. 1 and 2
- Mf4. 1. Calculate the Payback period 2. Calculate the Net Present Value (NPV) of both projects 3. Calculate the Internal Rate of Return (IRR) of both projects 4. Critically discuss the merits of each investment appraisal method, then discuss the result of the evaluations you have made of the two projects and advise the company which project should be undertakenWhich of the following should you focus when assessing the NPV of a project for a MNC? I. variability of the project's cash flow. II. correlation of the project's cash flow relative to the prevailing cash flows of the MNC. III. interest rate IV. capital structure A. II, III B. I, III C. III, IV D. I, IIOne must know the discount rate of an investment project to compute its: a. NPV and PI. b. NPV and IRR. c. PI NPV IRR and Payback Period. 4. Payback period and IRR.
- Which of the following is/are true for the average accounting return method of project analysis? I. does not need a cutoff rate II. ignores time value of money II. is based on project's cash flows IV. easily obtainable information for computation Multiple Choice I only I, II, II, and IVPls refer to the attached image. pls show formula and solution in manual calculation. 1. NPV of Project Z? 2. Payback period of Project X? 3. Payback period of Project Y? 4. Payback period of project Z? 5. Based on the calculated NPV and payback period, which project would you recommend and why? Include the implications of projects' NPVs and payback period in your explanation.QUESTION 1 The accounts manager of VM Gym & Sports has been asked to evaluate a potential capital investment of a set of rowing machines. The following data is available for cach project: Machine 1 Machine 2 RM RM Cost (immediate outlay) 500,000 245,000 Expected annual profits (losses) Year 1 I. 80,000 84,000 Year 2 90,000 136,000 Year 3 116,000 126,000 Year 4 146,000 150,000 Annual running costs 30,000 24,000 Annual service costs 36,000 20,000 Estimated residual value equipment 40,000 30,000 *The total annial running and service costs for Machine 2 in the first year is RM 36,000 The committee has estimated a cost of capital of 30% and employs the straight-line method of depreciation for all fixed assets when calculating net profit. The following discount factors are given: Year Cost of capital 10% 50% 0.909 0.667 2. 0.826 0.444 3. 0.751 0.296 4. 0.683 0.198
- Compute the Profitability Index (PI) for each project? Project A Project B Profitability Index (PI) 5- In light of your answers above, suppose that these two projects might be mutually exclusive or independent. According to these two assumptions, fill in the blanks in the table below with the suitable answer: Points Investment Criteria If A and B are mutually exclusive, then I would select If A and B are independent, then I would select PBP NPV IRR PIb) Using data provided below, compute appropriate values and fill the table below to help identify the least risky and most risky project among alternatives A, B and C using appropriate criteria. Project EV D D2 Var St. dev Coef.0f Var TT 12 0.2 A 18 0.7 28 0.1 10 0.3 В 22 0.6 32 0.1 11 0.1 C 21 0.8 31 0.1 Where n denotes the profit, P is the probability, EV stand for Expected value, D is the Deviation, D$ denote the deviation square, St. dev is the standard deviation and finally Coef.of Var is the coefficient of variation.Question 5: Find the net present value, interpret whether the NPV suggests you should accept or reject the project, find the payback period, find the discounted payback period, find the profitability index, interpret whether the profitability index suggests you should accept or reject the project, find the internal rate of return, explain whether the internal rate of return can repay the cost of borrowing money to conduct the project, find the modified internal rate of return, and explain with the modified internal rate of return can repay the cost of borrowing money to conduct the project. All for the following situation: The initial capital outlay is $175,000, the first-year annual operating cash flow is projected to be 20,000 but should grow by 5% per year during each of the project's 30 years, the after-tax-salvage cash flow is guessed to be $500,000, the required rate of return on this project is 15.50% and the company weighted average cost of capital is 12.50%.