Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000’s) TBC 1 2 3 4 5 Task 1 40 10 15 10 5 Task 2 23 6 10 5 2 Task 3 15 9 4 2 Task 4 6 3 3 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000’s) 1 2 3 4 Task 1 15 21 12 6 Task 2 2 5 6 3 Task 3 1 5 5 Task 4 2 What is the CAC at the end of week 4? Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40% 62% 85% 100% Task 2 15% 25% 75% 90% Task 3 2% 7% 45% Task 4 10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows: Budgeted Per Week (in 000’s) TBC 1 2 3 4 5 Task 1 40 10 15 10 5 Task 2 23 6 10 5 2 Task 3 15 9 4 2 Task 4 6 3 3 What is the total cumulative TBC? What is TBC at the end of week 4? Assume 4 weeks have passed and these are the actual costs per week: Actual Costs Per Week (in 000’s) 1 2 3 4 Task 1 15 21 12 6 Task 2 2 5 6 3 Task 3 1 5 5 Task 4 2 What is the CAC at the end of week 4? Below is the cumulative percentage of work complete per task per week: Cumulative Percentage Complete 1 2 3 4 Task 1 40% 62% 85% 100% Task 2 15% 25% 75% 90% Task 3 2% 7% 45% Task 4 10% What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Chapter1: Taking Risks And Making Profits Within The Dynamic Business Environment
Section: Chapter Questions
Problem 1CE
Related questions
Question
- Assume you are the project manager and based on your customer’s requirements you have determined there are four main tasks in a Dream Backyard project. Each phase has been assigned a TBC. Specifically, the customer wants a pool and spa built (Task 1 - $40,000); all plumbing, electrical, and mechanical installed (Task 2 - $23,000); a pool deck with planters and a raised fire pit (Task 3 - $15,000); and landscaping and clean up (Task 4 - $6,000). You estimate this will take 5 weeks to complete. The costs are budgeted as follows:
|
|
Budgeted Per Week (in 000’s)
|
||||
|
TBC |
1 |
2 |
3 |
4 |
5 |
Task 1 |
40 |
10 |
15 |
10 |
5 |
|
Task 2 |
23 |
6 |
10 |
5 |
2 |
|
Task 3 |
15 |
|
|
9 |
4 |
2 |
Task 4 |
6 |
|
|
|
3 |
3 |
What is the total cumulative TBC? What is TBC at the end of week 4?
- Assume 4 weeks have passed and these are the actual costs per week:
|
Actual Costs Per Week (in 000’s) |
|||
|
1 |
2 |
3 |
4 |
Task 1 |
15 |
21 |
12 |
6 |
Task 2 |
2 |
5 |
6 |
3 |
Task 3 |
|
1 |
5 |
5 |
Task 4 |
|
|
|
2 |
What is the CAC at the end of week 4?
- Below is the cumulative percentage of work complete per task per week:
|
Cumulative Percentage Complete |
|||
|
1 |
2 |
3 |
4 |
Task 1 |
40% |
62% |
85% |
100% |
Task 2 |
15% |
25% |
75% |
90% |
Task 3 |
|
2% |
7% |
45% |
Task 4 |
|
|
|
10% |
What are the CEV, CPI, and CV at the end or week 4? What is the SPI?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Understanding Business
Management
ISBN:
9781259929434
Author:
William Nickels
Publisher:
McGraw-Hill Education
Management (14th Edition)
Management
ISBN:
9780134527604
Author:
Stephen P. Robbins, Mary A. Coulter
Publisher:
PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract…
Management
ISBN:
9781305947412
Author:
Cliff Ragsdale
Publisher:
Cengage Learning
Management Information Systems: Managing The Digi…
Management
ISBN:
9780135191798
Author:
Kenneth C. Laudon, Jane P. Laudon
Publisher:
PEARSON
Business Essentials (12th Edition) (What's New in…
Management
ISBN:
9780134728391
Author:
Ronald J. Ebert, Ricky W. Griffin
Publisher:
PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:
9780134237473
Author:
Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:
PEARSON