d and supply function for a bridge are the following where C is cost in cents and V is volume in veh / h . Demand V = 1500 - 10C Supply or cost function: C = 120 + 0.5V (a) What is the equilibrium volume of traffic and the associated cost? (b) 20 cents of toll is added to the cost function, what will be the new cost function and the equilibrium volume?
Q: A toll bridge carries 10,000 veh/day. The current toll is $3.00/vehicle. Studies have shown that for…
A: Determine additional revenue with new toll (in $/day)
Q: Given the data below: Daily Traffic Count Axle Load (Kips) 1000 (single axle cars) 300 (single axle…
A: The ESAL is given by: Where, Assuming Seasonal correction factor Scf = 1 N = Number of axle FE =…
Q: It costs P500, 000 at the end of each year to maintain a section of Kennon Road. If money is worth…
A:
Q: An equipment costing P250,000 has an estima life of 15 years with a book value of P30,00 at book…
A:
Q: During morning peak hour, the passenger demand is 600. Assume that passenger demand is evenly…
A: Passenger demand = 600 hr-1 Average load/ occupancy = 50 passenger/bus. Passenger demand per minute…
Q: After 10 years, the public transportation remain unimproved. The modal split will also remain…
A: Dear student, Please find the answer in the below attachments Thank you
Q: A new route for 19000 trips will be open. Using the data below, what is the most likely mode of…
A: Given, A new route for 19000 trips v tij w tij t tij Fij ϕj Coefficient (a) 0.007 0.002…
Q: Three routes connect an origin and destination with performance function t; = a¡ + bjxj/c¡ (with t's…
A: travel time in minutes is given as ti=ai+bixiciwhere ti= is in minutes and x=vehicles in…
Q: 8.4 Consider a Poisson regression model for the number of social/recreational trips generated during…
A: Given Data: The total number of members in the household = 5 The number of members in the household…
Q: Suppose that the projected road vehicle traffic flow in a corridor is 5000 vehicle-trips per hour in…
A: According to given data Traffic flow in a corridor is 5000 vehicle trips per hour in one…
Q: Q3) A manufacturing plant is to be constructed A manufacturing plant is to be constructed in the…
A:
Q: The performance function for a highway connecting a suburb with the business district can be…
A:
Q: The performance function for a highway connecting a suburb with the business district can be…
A:
Q: A large residential area has 1500 households with an average household income of $15,000, an average…
A:
Q: A suspension bridge was constructed for P 24M, after which it will have a major repair of P 5M every…
A:
Q: Buses are to be charted for an excursion. The bus company charges $20.00 per ticket if not more than…
A: it is a basic maxima and minima question
Q: A household has 17 members and an annual income of P20,000. They currently live in a neighborhood…
A: Vehicle - based Shopping trips = 0.12 + 0.09 HS + 0.011 AHI - 0.15 EH Now substitute the values to…
Q: The performance function for a highway connecting a suburb with the business district can be…
A:
Q: A state highway department is planning the all road. It estimates that the construction cost (t = 0)…
A: Construction cost = $200,000,000PV of maintenance cost =10000000.007=$14285714 for perpetuity PV of…
Q: 7. A toll bridge from Manila to Lapu-Lapu City carries 4000 vehicles per day. The present toll fee…
A: Tmax = P 3.35
Q: An existing toll road has an average traffic volume around 6,000 vehicles per day. A project is…
A: According to given Data existing toll road has an average traffic volume around 6,000 vehicles per…
Q: 5-Vehicles start arriving for a booth in a parking lot to receive free brochures at 8:45 A.M at a…
A: With the help of data above, the following graph is obtained:
Q: Suppose that the projected road vehicle traffic flow in a corridor is 5000 vehicle-trips per hour in…
A: Given traffic volume is 5000 vehicles/hour So we have to calculate cost of routes according to the…
Q: The total cost when the demand that is maximized profit is $1800, fixed cost (CF) = $5500, Cv =…
A: Given data: Maximized profit (P) = 1800$ Fixed Cost (CF) = 5500$ CV = 15.5$
Q: Compute for the Total Remaining Traffic * A.15,858 vehicles B.15,743 vehicles C.15,862 vehicles…
A: According to the data the remaining traffic is calculated.
Q: Route 1 travel time is calculated as 10 minutes + 1 minute per 100 vehicles on it. Route 2 travel…
A:
Q: toll/veh would be T = 135 + x. In order to maximize revenues, what would the new toll charge be per…
A: given- traffic volume equation for a bridge required-to find maximum revenues from the new toll…
Q: A toll bridge carries 10,000 veh/day. The current toll is $3.00/vehicle. Studies have shown that for…
A:
Q: The Department of Traffic is considering three improvement plans for a heavily traveled intersection…
A: given that, Alternative Construction cost Annual saving cost in Accidents Annual time travel…
Q: A toll bridge carries 7,000 veh/day. The current toll is $4/vehicle. Studies have shown that for…
A: let V be travel demandV=7000-500×x50since the original toll was 400 cents per vehicles the new toll…
Q: Grab taxis arrive at the Manila International Airport , according to a Poisson process, at the rate…
A:
Q: Question:- Traffic counts in the year 2000 at a counting point on a national highway gave ADT as…
A: Objective: Design of Flexible pavement as per Indian Road Congress 37. Given: The traffic counts for…
Q: An individual is planning to take an 800-mile trip between two large cities. Three possibilities…
A:
Q: A large residential area has 1500 households with an average household income of $15,000, an average…
A: From the Given Dataneed to find change in %
Q: venue will be maximized. a. Write the expression for travel demand on the bridge related to toll…
A:
Q: Tourists arrive at the Manila Zoo at a rate of 250 vehicles per hour. But before entering the zoo,…
A:
Q: There are five alternatives for improvement of a road. Determine which alternative should be chosen…
A: The following table shows the Benefit / Cost ratio for the alternatives. Alternatives Annual…
Q: The daily counts of the current traffic volume for a rural highway for one week of May 2000 are as…
A: Given:- The traffic is composed of 70% passenger car, 20% bus, 10% truck The percent of future…
Q: A toll bridge carries 5000 veh/day. the current tol is 50 cents. When the toll is increased by P0.…
A: Given:- The total capacity of the bridge = 5000 veh/day The current tole = 50 cents The increase in…
Q: Determine the share (proportion) of person-trips by each of two modes (private auto and mass…
A:
Q: [T] The following table provides hypothetical data regarding the level of service for a certain…
A: 1st point : (600, 60) , 2nd point (1000, 57) , 3rd point (1500, 54 ) , 4th point (1900,…
Q: (show your formula) Given the figure above, compute for the Annual Average Daily Traffic of the…
A: The annual average daily traffic, abbreviated AADT, is a metric used in transportation planning,…
Q: 2) Transport focus is with .............. Select one: a. none of them b. location and transport…
A: 2) Introduction : Transport Focus is a non-profit organisation that serves as a watchdog for people…
Q: The Department of Traffic is considering three improvement plans for a heavily traveled road within…
A: Using the Net present worth - i = 4% and n = 53year PA,i,n = 1+in-1i1+in⇒PA,i,n =…
Q: Consideration is being given to increasing the toll on a bridge now carrying 4500 veh/day. The…
A:
Q: After 10 years, the public transportation remain unimproved. The modal split will also remain…
A: Given data, Modal split ratio = 70% for trips from public transport Person-trip demand after 10…
Q: 1. A toll bridge carties 10,000 veh/day. The current toll is P150/vehicle. Studies shown that for…
A:
Q: Situation 03: The number of crashes for a commuter airline with service between two cities located…
A: given- distance between cities d=200 milesnumber of crashes C=3time T=5 yearsNumber of flights per…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
- A toll bridge carries 10,000 veh/day. The current toll is ₱150/vehicle. Studies shown that for eachincrease in toll of ₱25, the traffic volume will decrease by 1000 veh/day. It is desired to increasethe toll to a point where revenue will be maximized.a. Write the expression for travel demand on the bridge related to toll increase and currentvolume. b. Determine the toll charge to maximize revenues. c. Determine traffic in veh/day after toll increase. d. Determine the total revenue increase with new toll.A toll bridge carries 6000 vch/day The current toll is $3.50/vehicle. Studies have shown hat for each increase in toll of 50 cents, the traffic volume will decrease by 500 veh/day. Jus desired to increase the toll to a point where revenue will be maximized. (a) Write the expression for travel demand on the bridge, related to toll increase and current volume. (b) Determine the toll charge to maximize revenbes. (o Determine traffic in vel/day after the loll increase, (d) Determine the total revente increase with the new tol.A bridge has been constructed between the mainland and an island. The total cost (excluding tolls) to travel across the bridge is expressed as C- 50 + 0.5V, where V is the number of veh/hr and Cis the cost/vehicle in cents. The demand for travel across the bridge is V- 2500 - 10C. (a) Determine the volume of traffic across the bridge. (b) If a toll of 25 cents is added, what is the volume across the bridge? What volume would be expected with a 50 cent increase? 155 (c) A tollbooth is to be added, thus reducing the travel time to cross the bridge. The new cost function is C- 50 + 0.2V. Determine the volume of traffic that would cross the bridge. (d) Determine the toll to yield the highest revenue for demand and supply function in part (a), and the associated demand and revenue
- A toll bridge carries 5000 veh/day. the current tol is 50 cents. When the toll is increased by P0. 25. Traffic volume decreases by 5000 veh/day. Det. the additional amount of toll that should be charged such that the revenue is maximized.A city engineer has estimated the annual toll revenues from a proposed highway construction project over 20 years as follows: An = ($2,000,000)(n)(l.06)n-1 n = 1.2 .... ,20.To determine the amount of debt financing through bonds, the engineer was asked to present the estimated total present value of toll revenue at an interest rate of 6%. Assuming annual compounding, find the present value of the estimated toll revenue.Consideration is being given to increasing the toll on a bridge now carrying 4500 veh/day. The current toll is $1.35/veh. It has been found from past experience that the daily traffic volume will decrease by 400 veh/day for each 25¢ increase in toll. Therefore, if x iš the increase in toll in cents/veh, the volume equation for veh/day is V= 4500 - 400 (x/25), and the new toll/veh would be T = 135 + x. In order to maximize revenues, what would the new toll charge be per vehicle, and what would the traffic in veh/day be after the toll increase?
- 1A toll bridge carries 10.000 veh/day. The current toll is PI50/vehicle. Stodies shown that for each ancrease in toot25, the traffic volume will decrease by 1000 veh daycedesired to ncrease the toll to a pocnt where revenue will be maximized. Write the expression for travel demand on the bridge related to toll increase and current yolume, Determame the toll chargc to maximıze revenues. Determine tmic in veh day after toll increase. Duermincshelutal revenue increase with new tall7. A toll bridge from Manila to Lapu-Lapu City carries 4000 vehicles per day. The present toll fee is P2.30. When the toll fee is increased by PO.20, traffic volume will decrease by 400 vehicles per day. It is desired to increase the toll fee to a point where revenue will be maximized. Determine the toll change to maximize revenue.Average demand on a rural roadway ranges from zero to 600 veh/day when the cost per trip goes from $1.75 to zero. (a) Calculate the net user benefits per year (in dollars) if the cost decreases from $1.50 to $0.75/trip (assume a linear demand function). $ 29 x Your response is within 10% of the correct value. This may be due to roundoff error, or you could have a mistake in your calculation. Carry out all intermediate results roundoff error. (b) Compare the value calculated in (a) with the benefits as calculated in typical highway studies. (Enter the benefits in dollars as calculated in typical highway studies.) $ 88000 x Your response is within 10% of the correct value. This may be due to roundoff error, or you could have a mistake in your calculation. Carry out all intermediate results E roundoff error.
- An existing toll road has an average traffic volume around 6,000 vehicles per day. A project is proposed to widen the toll road to increase the road capacity. It is projected that the traffic volume would increase to 10,000 vehicles if the toll rate is reduced from $5 to $4 per vehicle. Assume that the toll rate is the only factor affecting the traffic volume on the toll road. a) Determine the impact of the toll change on consumer surplus. b) Calculate the point elasticity of demand for the toll road. c) Calculate the arc elasticity of demand for the toll road.A toll bridge carries 10,000 veh/day. The current toll is $3.00/vehicle. Studies have shown that for each increase in toll of 50 cents, the traffic volume will decrease by 1000 veh/day. It is desired to increase the toll to a point where revenue will be maximized. Let V be the Volume X be the increase in toll charge (a) Write the expression for travel demand on the bridge related to toll increase and current volume. (b) Determine the increase in toll charge (c) Determine the new toll charge to maximize revenues. (d) Determine traffic in veh/day after toll increase. (e) Determine total revenue increase with new toll.A bridge has been constructed between the mainland and an island. The total cost (excludingtolls) to travel across the bridge is expressed as C = 50 + 0.5V, where V is the number ofveh/hr and C is the cost/veh in pesos. The demand for travel across the bridge is V = 2500 −10C.a. Determine the volume of traffic across the bridge.b. If a toll of 25 pesos is added, what is the volume across the bridge?c. A tollbooth is to be added, thus reducing the travel time to cross the bridge. The new costfunction is C = 50 + 0.2V. Determine the volume of traffic that would cross the bridge.