1- Construct the project network 2- Find the expected duration and variance for each activity 3- Find the critical path and expected project completion time
Q: a. The minimum project duration b. The amount of slack for each activity c. The total cost for…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Determine the critical path and project completion time.
A: A PERT diagram indicating the activity duration in three dimensional process which helps to…
Q: Identify the critical path in the project. b. Determine the length of the project. Using the data,…
A: The critical path method is a process that helps to identify tasks that are essential for project…
Q: From the above table, determine the critical path? and what is the total project completion time…
A: In this question, I have to prepare the network diagram, based on this network diagram, we could get…
Q: Given the following network, with activity times in months, determine the earliest and latest…
A: Formula:
Q: a. Construct the network diagram for this project. b. Determine the earliest and latest start times…
A: Below is the solution:-
Q: Describe the need of expert project management for complicated projects and why it is necessary.
A: This question is related to the topic -Project Management and this topic fall under the operations…
Q: Draw the project network. Find the critical path and total project duration. Find the Earliest Start…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO FIRST THREE PARTS OF THE QUESTION. FOR REST…
Q: Set up a table and calculate Early Event Times (TE), Late Event Times (TL), Activity Free Slack…
A: THE ANSWER IS AS BELOW:
Q: Calculate the ES, EF, LS, and LF times and the slack for each activity in the figure below and…
A: The ES, LS, EF and LF are as as follows.
Q: Duration Durations Figure 3. Project Schedule Network (Duration in Days) Q10-11-12 Consider the…
A:
Q: Draw a project network. B. What are the critical activities and what is the expected project…
A: ANSWER : A)
Q: A. Draw a project network. B. What are the critical activities? C. Will the project be completed…
A:
Q: The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty…
A: A project network diagram is a graphic depiction of a project's process. A network diagram is a…
Q: Construct a Gantt chart for the following set of activities, and indicate the project completion…
A: Gantt chart is a type of bar chart, which is used for scheduling business activities. It shows the…
Q: Activities of a project is given below: Activity b Immediate Predecessor A 3 B 1 4 7 3 6. B 2 8. В…
A: f) deadline of project = 19.28 days
Q: Direction: Analyze and solve the following problem completely. 1. Construct the project network…
A: PERT project management CPM are two well-known administrative procedures. PERT is a truncation of…
Q: Given the following project: Activity Predecessor Normal Time (day) Normal Cost ($) Crash…
A: Note: - Since the exact question to be answered is not specified, we will answer the first question…
Q: 1. Draw the network diagram for the project below. 2. What is the critical path and completion…
A:
Q: Two international banks are integrating two financial processing software systems as a result of…
A: Activity Immediate Predecessors Activity Time A - 3 B A 1 C A 2 D…
Q: (a) Draw a project network. (b) Determine the expected time and variance for each activity. (c)…
A:
Q: a. Draw a project network diagram then show the calculation for Early Start (ES), Early Finish (EF),…
A: Here, in the table data, we have a column for activity, dependency and duration, based on the table…
Q: Draw a Network Calculate Earliest Start Time, Earliest Finish Time, Latest Start Time and Latest…
A: Find the Given details below: Description of Activity Activity Duration (Days) 1-2 A 8 1-3 B…
Q: Find What is the best way to draw a project network?
A: A project network is a graphical depiction very similar to a flow chart that shows the sequence in…
Q: Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Component of the project activities described in the following table, the critical path of the…
A:
Q: Given the following network, with activity times in months, determine the earliest and latest activ…
A: A network diagram is a visual representation of a project which helps to identify critical paths and…
Q: Activity Predecessor Duration in Weeks А A 3 C A 2 D В 3 E 4 F D G B 1 H D 3 I C
A: Hi, we are supposed to answer three sub parts at a time. Since you have not mentioned which subpart…
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: 1. Determine the critical path for the project network in the following Figure:
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: Activity Predecessor Duration A. 5 A 12 20 15 B 15 F D, E 10 G F 18 F 12 G,H 8. A,
A: A network diagram visually presents the activities, along with their order and duration, that must…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: The following table contains information related to the car problems of 2 SUV being maintained in…
A: Given data is
Q: 2. | Jean Walker is making plans for spring break at the beaches in Florida. In applying techniques…
A: Given data is
Q: Activity Preceding activity Activity duration A - 6 B - 3 C - 1 D A, B 2 E A, C 5…
A: Given data is
Q: a. Determine the expected project completion time and the variance. b. What is the project's…
A: The critical path is a method to find the shortest duration by which a project can be completed with…
Q: Given the following network, with activity times in weeks, determine the earliest and latest…
A: Solution Activity Duration Earliest Start Time Earliest Finish Time Latest Start Time Latest…
Q: Find the project's total duration and described the completion of the project activities after the…
A: ANSWER IS AS FOLLOWS:
Q: Draw up a table including activity, expected time and variance and then construct the project…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: Analyze the following project information and apply Critical Path Method to calculate slack time for…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: Find the project details in the below table, draw the network activity diagram and identify the…
A: Critical path can be defined as the path which is having the longest duration.
Q: The table below shows a small project of 9 activities with the following time estimates: Most…
A: Given Information:
Q: For the project data in Table below, answer the following questions: a) Draw an AOA network of the…
A: ANSWER IS AS BELOW:
Q: 1). Based on the below table: (a) Construct a network for this problem. (b) Determine the expected…
A: Since you have submitted multiple questions with multiple subparts, as per guidelines we have…
Q: The table below shows the activities in a project and their pessimistic, most likely and optimistic…
A: Find the X and Y value: So the X and Y values are 3 and 12 respectively/
Step by step
Solved in 2 steps with 3 images
- Kimpel Products makes pizza ovens for com-mercial use. James Kimpel, CEO, is contemplating produc-ing smaller ovens for use in high school and college kitchens.The activities necessary to build an experimental model andrelated data are given in the following table: a) What is the project completion date?b) Crash this project to 10 weeks at the least cost.c) Crash this project to 7 weeks (which is the maximum it canbe crashed) at the least cost.The following precedence diagram reflects three time estimates for each activity. Determine: Use Table B1 and Table B2. 9-10-12 3 8 5-7-10 8-10-14 11-12-13 6 11 14-18-26 10.5-13-15.5 10 8-8-8 1 5-6-7 2 4 13-13-13 7 7-10-12 a. The expected completion time for each path and its variance. (Round intermediate calculations to 4 decimal places and final answers to 2 decimal places.) Path Mean Var. Std. Dev. 1-2-3-8-11 37.33 1-2-4-6-11 43.00 5.11 1-2-4-7-11 0.81 1-2-5-9-10-11 46.83 1.25 9-9-9 10-11-12 10-12-14Using PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,c. What is the expected project completion time? (Do not round intermediate calculations. Round your answer to 2 decimal places.) Project completion time d. What is the probability of completing this project within 16 days? (Use Excel's NORMSDIST() function to find the correct probability for your computed Z-value. Do not round intermediate calculations. Round "2" value to 2 decimal places and final answer to 4 decimal places.) Probability 10 00 days 09994Create a risk matrix for this project:Event Cost ($000) ProbabilityEquipment breakdown 40 .20Vendor is late with key segment 200 .60Subcontractor has labor issues 140 .30Weather problems 15 UnknownFunding delays 50 .40 to .60Testing delays 20 .40Explain your reasoning for your placement of the events Weather problems and Funding delays.
- 7. Contract requirements state that a project must be completed within 180 working days, or it will incur penalties for late completion. Analysis of the activity network reveals an expected project completion time of 145 working days with a project variance of 400. What is the probability that the project will be completed before the late-payment deadline? (select the closest answer) Select one: a. about 4% b. over 99% c. about 80% d. about 46% e. about 96%quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?Using your results from Problem 6,(a) Calculate the probability that the project will be completedin 38 weeks.(b) Calculate the probability that the project will be completedin 42 weeks
- A company is willing to develop their rocket before the end of current financial year which is now 28 weeks away. The chief engineer of the company has decided to use PERT technique in order to plan, schedule and control program of development for the data given in table below. What is the probability that the program will be completed by the end of the current financial year? (all durations are in weeks). (i) G) Optimum Duration Most likely duration Pesimistic duration 1 2 3 8 13 3 2 8 4 3 8 10 4 7 10 3 6. 3 8 4 9 10 4 8. 4 9. 5 7 9. 12 6. 5 11 7 9. 14 8 4. 00 2.Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing smaller ovens for use in high school and college kitchens. The activities necessary to build an experimental model and related data are listed in the following table Total Cost with Crashing Immediate Predecessor(s) $2,050 $2,800 a) Based on the given information regarding the activities for the project, the project completion date = b) To reduce the duration of the project to 10 weeks at the least cost, the following is the order of what needs to be followed while crashing the activities: The first activity to crash is by 2 weeks at a per week crashing cost of Ned, one should crash activity dollars. Total cost of crashing the project to 7 weeks = and activity E by 1 week at a total per week crashing cost of dollars. dollars. weeks. dollars. dollars. Normal Activity Time (weeks) A TERSE Doo LU LỞ MATMARIATION percen 32 TON * Next one should crash activity D and activity by 2 weeks for an…The following information relates to a project (task times are in weeks). Use the information to solve for the critical path and then to determine the probability that the project could be completed within 36 weeks. Task A B C D E F Preceding Tasks to 4 4 2 None A B D, E tm 6 7 7 8 13 9 8 0 W CON 6 tp 8 10 12 18 15 10 Click the icon to view the table of standard normal probabilities. The probability that the project is completed within 36 weeks is. (Enter your response rounded to four decimal places.)