Identify the critical path in the project. b. Determine the length of the project. Using the data, determine the probability that the project will be completed in greater than 54 days. а. с.
Q: a small project consisting of eight activities has the following characteristics:…
A: Note: - As we can answer only up to three subparts we will answer the first three subparts of part…
Q: a. The minimum project duration b. The amount of slack for each activity c. The total cost for…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Q3: Determine the time completion of project for the activities shown below: Activity: A BCDEFGHIJ K…
A: Given Information:
Q: Q1) by using Bar chart planning technique find the following a- Total duration for the project b-…
A: The detailed solution of the given question is in Step 2.
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A:
Q: Optimistic Most Likely Pessimistic Activity Predecessor 4. 6. 14 A 4. 14 B. 6. 13 14 A,B 4. 8. 12 10…
A: Here, to find the answers to parts d(, f) and g), we will first find the expected mean duration and…
Q: a) What is the probability that the project can be completed in 25 days or fewer?
A: The expected activity time is the time taken by the particular activity to complete the project…
Q: n the objective o
A: Project Manager Duties and Responsibilities
Q: activity predecessor optimistic time(days) Most likely time(days) Pessimistic time(days) A - 4 8 24…
A: Find the Given details below: Activity Predecessors Optimistic Time(To) a(Days) Pessimistic…
Q: List the Ethical issues faced in Project Management?
A: The objective of the project accomplishes through the process includes skills, knowledge, and method…
Q: 31) Use the values in the table to calculate activity durations and variances for the project. Which…
A: Network diagram: Calculation of expected time and variance with given Optimistic, pessimistic and…
Q: Q3: Determine the time completion of project for the activities shown below: H Activity. | A В С D E…
A: We have the given Activity starting from A to P Expected duration (weeks) Preceding activities
Q: Q.3/ Consider the project given in the next table. Find the probability that the project will be…
A: The activities have three types of time estimates depicted by a,m, and b. a=optimistic time m=most…
Q: List the three types of project management office (PMO)?
A: A project management office is a department within an organization, government agency, or enterprise…
Q: Determine the critical path, and how many weeks will the project take to complete, suppose D could…
A: To find a critical path, one needs to first find all the possible paths to finish the project from…
Q: Would a project manager ever consider crashing anoncritical activity in a project network?…
A: Crashing an activity happens when a task director strips a cycle down to the briefest time and least…
Q: • Q2:Find out the completion time and the critical activities for the following project: D 20 E H 11…
A: The project network diagram is the diagram which shows the project activities and their duration to…
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: From the network diagram, The possible paths and their duration are: A-D-G-H = 3+3+1+3 = 10B-E-F =…
Q: Q3: Determine the time completion of project for the activities shown below: Activity ABCD E FGHI K…
A: given
Q: TABLE 1: Activities and duration project Duration in weeks Activity Proceeding activity Optimistic…
A:
Q: Give some examples of ethical iss-ues that may arise on projects. What can project manager do to…
A: Throughout the course of project management, numerous ethical boundaries must be crossed. The…
Q: Activities of a project is given below: Activity b Immediate Predecessor A 3 B 1 4 7 3 6. B 2 8. В…
A: f) deadline of project = 19.28 days
Q: a. Determine the project completion time if no activity is crashed. What would be the total cost of…
A: Below is the solution:-
Q: of the project, the same principles of project management (2) Whatever the apply. (a) quality (b)…
A: Project management: It is the utilization of methodologies, devices, and methods to progressively…
Q: Q2:Find out the completion time and the critical activities for the following project: D 20 B E H 11…
A: Project management is the management in which different types of skills and techniques are used to…
Q: Q1: For activitics shown in table below, find the new time of project after updating, if the project…
A:
Q: Duration Activity IPA Optimistic Realistic Pessimistic 2 8 19 12 C A 10 12 19 B 18 23 C 7 16 19 F…
A: Available Paths Are: A-B-F-End A-B-D-F-End A-B-D-G-End A-C-G-End A-C-E-End
Q: (2) In the context of project management, why is it important to manage risks?
A: Every organization faces unknown risks or harmful events that can devastate the company's finances…
Q: Q1: Determine the duration of project for the activities shown below, and find the critical path by…
A: Given data is
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: • Q1: Determine the critical path, the critical activities and the project completion time.…
A: The project network diagram is the diagram that shows the activity and the project duration to…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: Activity Preceding activity Activity duration A - 6 B - 3 C - 1 D A, B 2 E A, C 5…
A: Given data is
Q: 3- The value of the variance of the critical path in the project is
A: Variance = square of sum standard deviations of critical activities Standard deviation = (b-a)/6
Q: Activity A BEDCFGHI 5 5 2 3 3 4 5 5 6 Duration (days) Following B,D,E C,F F F,G G G H,I R R Activity…
A:
Q: a. Determine the expected project completion time and the variance. b. What is the project's…
A: The critical path is a method to find the shortest duration by which a project can be completed with…
Q: Task ID Task Predecessor Original Duration Original Cost Crashed Duration Crashed Cost 1 2…
A: Find the Given details below: Task ID Activity Predecessor Original duration (NT) (Days) Original…
Q: 2. Find the critical path. What is the earliest time that the project can be completed?
A: From the following table the critical path can be ascertained: ACTIVITY EXPECTED TIME…
Q: The project manager of Good Public Relations gathered the data shown in Table 7.15 for a new…
A: Critical path method is one of the effective project scheduling technique in which project can be…
Q: What is the project duration?
A: THE ANSWER IS AS BELOW:
Q: Gabrielle Kramer, owner of Pet Paradise, is opening a new store in Columbus, Ohio. Her major concern…
A: Project Evaluation and Review Technique (PERT) may be a technique utilized in project management…
Q: Determine: a. The critical path(s). b. The duration of the project. c. Total margin of J, D and…
A: A critical path indicating the longest duration path from a project which identified by selecting…
Q: Activity Duration (day) Predecessor (s) Act. A 2 Act. B 3 Act. C 3 А Act. D 4 В Act. E 3 C,D Act. F…
A: Find the given details below: Given Details: Activity Duration(Days) Predecessor A 2 - B 3…
Q: parameters of the ch
A: Project management An important part of managing projects is knowing how to manage them effectively.…
Q: Determine a) The slack available of every activity. b) The critical path c) The duration of the…
A: Project network is the diagram that shows the project tasks or activities and their duration to…
Q: The project shown within details what is the possibility t finish the project in 38 days? And what's…
A: Given that: Activity a m b 1 to 2 2 7 8 2 to 3 5 6 9 2 to 4 3 7 8 2 to 5 4 5 6 3 to 6…
Q: What is lag in project management?
A: Project Management - It is considered as the process which is used to manage the activities or…
Step by step
Solved in 3 steps with 4 images
- 1.The chief engineer of firm XYZ is responsible for supervising the construction work of a road. He has identified the activities and their durations for each stage of operation. Activity Duration (days) Preceding activities A 5 - B 10 - C 1 - D 8 B E 10 B F 9 B G 3 A,D H 7 A,D I 4 F J 3 F K 5 C,J L 8 H,E,I,K M 4 CJ Draw a network diagram (AOA) for this road construction project. Which are the critical activities? How long the project will take?O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,Consider the following list of activities with time (in months) Activity A B C D E F G H Immediate Predecessor ----- ----- A A,B A,B C D,F E,G Activity Optimistic Most Probable Pessimistic A 3.5 4.0 4.5 B 2.0 3.0 7.0 C 6.5 7.5 10.0 D 5.0 5.5 6.0 E 5.0 6.5 8.0 F 8.0 9.5 11 G 6.0 7.0 9.5 H 4.0 5.0 6.0 a) Identify the critical path. b) What is the expected time to complete the project? c) What is the variance of the project completion time? d) What is the probability of completing in 32 months?
- quetion 1 a)What is a burn-down chart? What purpose does it serve? b)Why should a project manager be concerned with monitoring a project’s progress? c) Describe how the SPI and CPI can be used to forecast the final cost of a project?c) A research and development department in XYZ Company is developing a new product for the company to attract more customers and hence maximize on sales. The R & D manager has revealed that the following activities will take place in the coming weeks. Activity ABCDEFGH А с Η I Immediate predecessors None A A B B с E D,F G,H Optimistic time 4 5 4 15 10 8 4 1 6 Most likely time 6 7 8 20 18 9 00 8 2 7 Pessimistic time 8 15 12 25 26 16 12 3 8 Page 1 of 5 i. Draw the network for this project. ii. Calculate the estimated time for each activity. iii. Find the Critical Path and the expected number of weeks for completion of the project.Table below gives estimates in weeks, for forned activity (Durations are PERT. using Activity Duration Preceded Resources Ryan 5 1. 15 Order review 2. Order vender parts 3. Produce standard parts 20 custom parts development Manufacture custom parts 10 4. Design 13 5 18 7. Assemble 10 5 I 1 I 1 4 Carly Ryan Lauren Connor Ryan 2,3,6 Dawn Test 2,5 been engaged to you Assuming that project detalje have indicated festurces), USE CCPM (Critical Chain Project Management) below (Aur Project: to ESTIMATE the project duration by showing Jage of your programming procesa lindicate each and and
- Please help with (b) and (c) as both answers given were incorrect! Please need correct answers. Blue Lagoon is a contractor that installs residential swimming pools, projects that consist of nine major activities. The activities, their immediate predecessors, and the activity time estimates (in days) are shown. Activity Immediate Predecessor Optimistic Most Probable Pessimistic A 3 5 6 B 2 4 6 C A, B 6 7 8 D A, B 8 10 11 E B 2 4 6 F C 1 2 3 G D 6 10 12 H D, F 7 9 11 I E, G, H 3 4 5 (a) What are the critical activities? (Enter your answers as a comma-separated list.) $$A, D, G, I (b) What is the expected time (in days) to complete the project? (Round your answer to two decimal places.) (c) Based only on the critical path, what is the estimated probability that the project can be completed in 28 or fewer days? (Round your answer to four decimal places.)A network consists of the activities in the following list. Times are given in weeks. Activity Preceding Time A В 3 -- C A 7 А, В 3 E 4 F D a. Draw the network diagram. b. Calculate the ES, EF, LS, LF, and Slack for each activity. Early Finish Early Start Task Late Late Slack Start Finish A B C D E F c. What is project completion time?3.8 Roger Ginde is developing a program in supply chain management certification for managers. Ginde has listed a num- ber of activities that must be completed before a training program of this nature could be conducted. The activities, immediate pre- decessors, and times appear in the accompanying table: a) DrawtheappropriateAONPERTdiagramforJ.C.Howard’s management team. b) Find the critical path. c) What is the project completion time? • • 3.11 The following is a table of activities associated with a project at Rafay Ishfaq’s software firm in Chicago, their dura- tions, and what activities each must precede: ACTIVITY DURATION (WEEKS) PRECEDES A (start) 1 B, C B 1 E C 4 F E 2 F F (end) 2 — ACTIVITY IMMEDIATE PREDECESSOR(S) TIME (DAYS) A — 2 B — 5 C — 1 D B…
- Given the data for a project in table Q3, using the following assumptions: 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: Date of finish BAD O GYEK 1. 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report co Table Q3 Duration (Hrs) No of Workers Budget Activity predecessor A None 48 12000 64 32000 C 16 10000 32 4. 12000 B,C 32 8000 B,C 16 6000 G B,C 16 4 10000 H. 64 16000 3. 16 4000 32 1 12000 K 32 3 16000 H. 48 1 12000 Total Budget of RM150000scenarios of a project activities (tables given below) and their required times to be completed in addition to their predecessors for developing a Website': Activity Description Duration (days) Preceding Activities A Determine user needs 8 В Review s/w and languages 4 C Purchase software 10 -- D Design format and style 10 В E Write programs 6. A F Review outcome product with user 12 C G Make revisions 4 C H Select server site 8 E I Install on server 14 D, F J Test 8. G, H, I 1. Draw the path. 2. Calculate the early finishing time (forwards calculations) 3. Highlight the total time to complete the project (days) 4. Calculate the late finishing time (backwards calculations) 5. Calculate the slack time of the non-critical path activities 6. Identify the critical path (highlight critical path activities) 7. what would happen if activity D revised to take 14 instead of 10 days?What possible project do you anticipate that we can undertake to uplift the image of the school 1. Justify objectives 2.Develop a well WBS and its deliverables for the project 3. Establish relationships between activities, show predecessor and successor of the activities. 4. Draw a network diagram and determine durations. 5. Human resource capacity,teams, roles, responsibilities, and competencies. 6. Organizational structure that will be adopted and why.