Ql: For the project listed below, find the following items: 1- Total project finishing time. 2- Critical path 3- Free float for each task. • JE A otiuitu P
Q: A jewelry shop procures a ring at $20 each and sells it at $80 each. Weekly demands for the ring…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Project X has the data points below. The schedule performance index (SPI) for task P is .. Task BCWS…
A: Here, we first understand the values given for each task BCWS = Budgeted Cost of work scheduled -…
Q: Below are the production demands for the first four months of the year. What is the 4 month moving…
A: Forecasting is the process of estimating future demand based on previous or historic data and…
Q: Discuss the traditional, Western management approach to quality as compared to the quality…
A: Quality Management Philosophy: Traditional Western Quality Management Approach: The product must…
Q: Talk about the three things that need to be addressed in the section on work that has to be done in…
A: Project management is the set plan that is in the form of a document. It defines all about the…
Q: Questions What do you work on Challenges you faced and how did you overcome them (both in…
A: Project management is the process of managing and guiding a team who is working on a project to…
Q: A luxury hotel has been receiving a lot of complaints from guests recently. The manager worries that…
A: 1. Check sheet
Q: (e) With a 10-minute cycle time and six workstations, what is the efficiency? () What is the total…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: The "Merchant Model" and How It Operates
A: Merchant Model The merchant model is a business concept in which items or services are sold through…
Q: At noon time, customers arrive at Metrobank counter managed by a single cashier with mean arrival…
A:
Q: The Oldham-hackman model of job characteristics is based on what?
A: A job is characterised by a condition that if a job is capable to satisfy ita employee than the…
Q: Why is there a need for management to review regularly the Risk Assessment?
A: Risk assesment is a process of identifying the potential risks in the organisation and understanding…
Q: Eye4Customer is a 3-year-old call centre. It has launched Performance Appraisal system recently.…
A: SMART performance goals are specific in nature, measurable in terms of quality, achievable, relevant…
Q: The term "interruptions" has a variety of meanings. Describe the kind of interruptions you're…
A: Interruptions can be described as disturbance or distraction a worker faces in between a work.…
Q: Define and briefly discuss the concept of labour relations. In 10 bullet points
A: Labor relations refers to the process through which employers and employees, management, and unions…
Q: When it comes to Performance Testing, how fast can you go?
A: Performance testing refers to the evaluation of the performance of a system to find out…
Q: Why is it more difficult to implement an agile development approach in a company that has a…
A: Under Traditional Project Management, all tasks related to the proect are done in a defined…
Q: ) For a 95% service level, what is the ROP? The reorder point is 1645 cigars (round your response to…
A: GIVEN: Mean weekly demand, d-bar 225 Delivery lead time, LT 4 Service level 0.96 Standard…
Q: Data has been collected for a machine over a number of weeks and is contained in Table Q6 below. a)…
A:
Q: What lessons do we learn about organizational behavior from the Organisational Iceberg? Discuss the…
A: The distinctive set of ideas and values that drive what individuals do and how they do it is known…
Q: a) Draw the precedence diagram and assign tasks using five workstations. b) What is the efficiency…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: (3) What are the basic steps in risk management? Briefly describe each.
A: 3. Risk management process involves risk identification, risk analysis, risk response planning and…
Q: 20 8. в E H 11 к 6 10 16 14 7 F 10 25
A: Based on above network diagram we identified 4 paths 1) 1-2-5-8-10 2) 1-3-6-8-10 3) 1-3-6-9-10 4)…
Q: se choose the most and least effective answers Statement Most Least Give the customer an example of…
A: Selling a service to a customer is not very easy because in today's world every customer is rational…
Q: Maroons Medical Supplies, Inc. must order masks from its supplier in lots of 1 dozen boxes. Given…
A: Given, annual demand, d= 26000 dozens Ordering cost, o = P30 Holding or carrying cost, h =20% of…
Q: nal Rights and Pri
A: The Family Educational Rights and Privacy Act (FERPA)
Q: What are the issues and tasks for organizing a project?
A: Organizing a project means structuring a project. Structuring means managing, coordinating and…
Q: demonstrate the benefit of using the Work Breakdown Structure (WBS) concept?
A: A graphical, hierarchical, and deliverable representation of the breakdown of a project is called a…
Q: A firm is considering whether to purchase or lease land-moving equipment. The data associated with…
A: Equivalent annual cost (EAC) of owning the asset is to be calculated first Present value of annuity…
Q: In Value Engineering we cannot reduce the quality of the item which will reduce the cost: A) True B)…
A: Value engineering is an approach to provide the necessary functions in a project at the lowest cost…
Q: T-Shirts Unlimited is a retailer that sells every kind of T-shirt imaginable. The different types of…
A:
Q: Data management may be broken down into two categories: transactional and analytical. How do these…
A: One of the most important concepts in business intelligence and analytics is the idea of data…
Q: List and describe five (5) ways in which a project manager may seek to motivate their team.
A: Organizations are dependent on their employees. Businesses must rely on qualified project managers…
Q: Operations Management is the ability to influence a group toward the achievement of a vision or set…
A: Leadership is the ability of a leader to attract and influence a group to make them work in a…
Q: The First Amendment of the U.S. Constitution guarantees the right of _
A: ANSWER : The five freedoms it secures: speech, religion, press, assembly, and the option to petition…
Q: M3-evaluate how TPS has impacted on the success of Toyota
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Who among the following is NOT one of the individuals to manage Strategy Risk for a multinational…
A: There are three types of risks faced by an organization. 1. Preventable risk 2. Strategy risk 3.…
Q: Categories the challenges in surveying works towards to sustainable development.
A: Sustainable development means different things to different people, but at its core, it is about…
Q: Operations Management 3. What are the main components of attitudes? Does behavior always follow from…
A: Cognitive Component :The cognitive component of attitudes alludes to the beliefs, contemplations,…
Q: Describe what is meant by a learning curve. Provide a simple illustration of a 70% and an 80%…
A: Learning Curve A learning curve is a notion that physically depicts the relationship between cost…
Q: III. In a particular very small region, the consumer price index, C, depends on the current value of…
A: Given, The formula for consumer price index (C) is given as: C=100+e-EPF where, E= Gross regional…
Q: What is the process of releasing a product? Why is version control so important?
A: With the process of releasing a product, we could send this new product to the specific target…
Q: Question 1 : Identify an appropriate inventory management strategy which Nike could implement in…
A: Inventory management is the complete process of ordering, storing, using, and selling a company's…
Q: Valencia Products makes automobile radar detectors and assembles two models: LaserStop and…
A: Given data is L = number of laserstop model S = number of speedbuster model Objective function: Max…
Q: Operations Management Give examples of measuring service quality and measuring product quality? (2…
A: Quality is the ability of excellence of producing products that can be compared with other similar…
Q: As a project manager in product development, discuss TWO measures that could be adopted to establish…
A: Product development is the complete journey of the product. The journey starts from the idea of…
Q: According to the project network below which activity is a merge activity? Sube Teat 1 K L. Systems…
A: Project management is the management in which special types of skills knowledge and technology is…
Q: McDonald's is in downstream of McCain which is in the upstream of the potato farmers. Select one: O…
A: A supply chain is described as the various types of resources, people, and activities that are…
Q: What is the average inventory held at each warehouse? What is the annual inventory cost (holding +…
A: Inventory management is the process of managing the number of goods a business has in stock. The…
Q: Each Activity Should be Reduced Activity BY (weoks) week(s) B woek(s) week(s) wook(s) woek(s) What…
A: Project crashing is a process which helps to reduce the total duration using additional costs. A…
Trending now
This is a popular solution!
Step by step
Solved in 5 steps with 7 images
- blä 8 Q2/ By using PERT Method, Solve the ? following Q2/ For the project described in table below, assume that the activity durations are approximately normally distributed. Determine the probability to complete this project in (15 weeks). Activity Path m b a A (1,2) 1 2 В (2,3) 2 4 C (2,4) 1 3 D (4,5) 2 5 8 E (1,5) 2 4 F (5,6) 1 2 Note that the activity (3,4) is a dummy activity. 3. 3.By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B Bces Mailings Po V ates) EE E AL Review View Tell me $ Text Predictions: On 4 BIU 1. Evergreen Company wants to construct a new office building. The company has contracted a construction management contractor for this project. Given below are the details of a construction project. ✓ ✓ ✓ % Activity A 5 B C D ¶ E F — a) Construct the project network (AON) diagram for Evergreen Company and list all possible activity paths and their duration. b) Determine Evergreen Company's critical path(s). What is the duration of project competition? c) Determine the ES, EF, LS, LF, and floats for each activity. d) Construct a Gantt chart for Evergreen Company's project. AaBbCcDdEe Normal A STR 6 Predecessor(s) Duration (days) 1 2 A A B B, C E AaBbCcDdEe No Spacing !!! 3 2 1 1 & 7 E Do AaBbCcL AaBbCcDd AaBb AaBbCeDdE Heading 1. Heading 2 Title Subtitle * 00 8 I 9 Focus ( ) 0 Comm > St F
- Q1. Using a suitable example each, describe what the following project planning process activities involve: a. Establish project objective; b. Define scope; c. Create a Work Breakdown Structure (WBS); d. Estimate activity durations; e. Sequencing activities.Q1: Define Project Management plan with respect to the following points? · The role of the implementation agency · Beneficiary participation · Organizational structure and staffing · Financial management · Time control and remedial action · Supervision of the implementation of the project schedule · Supervision of implementation of a project managementFor the A-O-A network shown below, Duration (months) Tp Activity To Tm 2 A 3 C B 10 15 20 А C 10 12 14 G D 20 26 38 1 E 22 33 44 H B E F 15 21 33 5 G 8 10 12 F H 1.5 4 6.5 Determine the following using PERT (i) Expected project duration, variance and standard deviation for each activity (ii) Determine slack for each activity (iii) Target duration if the probability of project completion is 95% and 99% (iv) Probability of completion of project within 60 months and 54 months 4. 3.
- consider the network described in the table below. Time in weeks. Activity Immediate Predecessor(s) Pessimistic Probable Optimistic J -- 15 10 8 K -- 9 8 6 L J 10 6 5 M J 3 3 4 N K,M 9 5 2 O K,M 12 7 5 P L,N 10 8 3 (a) Calculate the expected duration of each activity. (b) Calculate the expected duration and variance of the critical path. (c) Calculate the probability that the project will be completed in more than 26 weeks time? How about 30 weeks?5] 51 Ex-2/ Find the project's total duration and date of completion (assume the project start date is 1/12/2014). Use the following details to draw the A-O-A Network and build its Table: Activity BC E H. R. Duration 4 3 4. 5 6. (days) Following B,D,E C,FGF,G Activity H,I RQ3) A small project consisting of eight activities has the following characteristics: Time-Estimates (in weeks) Afest apostle dime (2) Activity ABCDEFGH (a) Draw the network for the project. (b) Determine the critical path. (c) Calculate the variance of the project. -Preceding ectivity None None A A A B.C D EFO N22rann 10 10 7 3 Most likely dime (m) 4 12 9 15 75 9 3.5 5 Most Pesshmestle alme (D) AR2R=an 12 26 10 11
- N5 Explain some of the basic principles of cost management, such as profits, life cycle costs, tangible and intangible costs and benefits, direct and indirect costs, and reserves. Why is defining activities a process of project time management instead of project scope management?The activities necessary for the completion of this project are listed in the following table: Normal Crash Time Time Normal Crash Immediate Predecessor(S) Activity (Weeks) (Weeks) Cost Cost 6 3 $2,100 $2,700 -- 1 1,900 2,400 -- 3 400 800 6 1,950 2,500 с 3 1,100 1,200 A, B 1 3,100 4,000 D, E a. What is the project completion date? [Select] weeks b. What is the total cost required for completing this project on normal time? [Select] c. If you wish to reduce the time required to complete this project by 2 weeks, which activity(s) should be crashed? [Select] V and how much will this increase the total cost by? $ [Select] d. If you required an additional week reduction, what activity would you crash? [Select] and how much is the total 3 week cost of " crashing? $ [Select] ABCDEF 2003 12 4 8 4(c) Illustrate with suitable examples, the COCOMO I and II model of project management.