3. Draw a project network from the following information. What activity(s) is a burst activity? What activity(s) is a merge activity?
Q: The project schedule has the following characteristics:(i) Construct the network. (ii) Compute E and…
A: The given problem is Activity Duration 1-2 4 1-3 2 2-4 2 3-4 7 3-5 5 4-6 5 5-6 6…
Q: 2) Draw the network corresponding to the following information. Also, complete the table, identify…
A: Critical Path : B----D----G----H Critical Path Duration : 30
Q: a. Draw a project network. b. What is the critical path? c. What is the normal project cost? d.…
A: Find the Slope calculations below:
Q: Picture attached below
A: ACTIVITY DURATION ES EF LS LF SLACK CRITICAL A 3 0 3 0 3 3 - 3 = 0…
Q: 1- Construct the project network 2- Find the expected duration and variance for each activity 3-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: 1. Draw the network diagram for the above project. 2. What is the critical path? 3. What is the…
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: Which process involves measuring against the project schedule baseline by looking to see what things…
A: Project schedule A project schedule can be explained as a plan for completing a project…
Q: 1. Organize the information above in an activity precedence table showing the activity, precedent…
A: Project network is the graphical representation of project activities and their duration to complete…
Q: A local grocery store plans on holding a big sales event at the end of season. The activities that…
A: Given - Activity Duration (Weeks) Immediate Predecessor A 3 - B 1 A C 4 A D 2 B E 3 D,…
Q: a) Draw an ACON diagram of the project, including activity durations. b) Define the critical path,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: a) Draw the network diagram. What is the project completion time? What is the critical path? b)…
A: The network diagram is a graphical representation of the project and is made up of a series of…
Q: Solve the following project by hand and submit your notes: Activity Normal Time (weeks) Crash…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO THREE SUB-PARTS AT A TIME. PLEASE POST THE REST…
Q: Þroject, Activity, Predecessor, Duration Below is a project listed in a table with: • activity, •…
A: Given- Activity Predecessor Duration (Weeks) A None 3 B A 7 C A 5 D B 12 E B 8 F C 5…
Q: Direction: Analyze and solve the following problem completely. 1. Construct the project network…
A: PERT project management CPM are two well-known administrative procedures. PERT is a truncation of…
Q: Two international banks are integrating two financial processing software systems as a result of…
A: Activity Immediate Predecessors Activity Time A - 3 B A 1 C A 2 D…
Q: (a) Construct an AOA network representation for the project. (b) Construct an AON network…
A: The activity on arrow diagram is as follows:
Q: a. Develop a project network. b. Develop an activity schedule. C. What are the critical activities,…
A: A project schedule network diagram shows the sequence of the task that is performed to complete a…
Q: Example 4: The details of the project network are given in table below, if indirect cost (overhead)…
A: critical path: A-B-E
Q: Using the following information, create a project network diagram. Calculate, ES, EF, LS and LF for…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: Draw the network diagram of the following activities. Activity Dependencies Duration A 2 В 2 4. D 8…
A: a. The minimum time required to complete the project is known as the project duration and that can…
Q: Consider the below project information for questions 1-4. Activity Immediate Duration (days)…
A: Answer: A project consists of different activities. The project mentioned in the question is having…
Q: ) Construct an AON diagram using the above the Project Management table. ) What is the Critical Path…
A: The answer is as below:
Q: Activity Predecessor Duration in Weeks А A 3 C A 2 D В 3 E 4 F D G B 1 H D 3 I C
A: Hi, we are supposed to answer three sub parts at a time. Since you have not mentioned which subpart…
Q: 2.2.1 Draw the project network diagram. 2.2.2 Identify the project critical path. 2.2.3 What is the…
A: Find the Given details below: Activity Predecessors Duration(Days) A None 8 B None 4 C A 5…
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: Enrichment Exercise 7.2 Promoter of championship boxing match must perform the task shown in the…
A: An approach is a better way of looking at teaching and learning concepts. An approach gives rise to…
Q: snip
A: Answer: Please note- Since we only answer up to first 3 sub-parts, we will answer the first 3.…
Q: Consider the following project.…
A: The critical path method (CPM), otherwise called critical path examination (CPA), is a booking…
Q: 1. Construct the PERT network for this project 2. Compute for the Earliest Start Time and Latest…
A: Note: - Since we can answer only up to three subparts we will answer the first three subparts(1, 2,…
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: 2. A network consists of the activities in the following list. Times are given in days. Activity…
A: Given data is
Q: Three recent college graduates have formed a partnership and have opened an advertising firm. Their…
A: Expected time Te=Optimistic Time +4×Most Likely Time +Pessimistic Time6 Variance σ2=Pessimistic Time…
Q: 1. Determine and provide the following information for Activity 1: Latest Finish Duration …
A: Latest finish: -5 Duration: 3 Latest start: -8 Start date: 0
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A В 7 C 4…
A: Given Information:
Q: 4. How long can activity C be delayed without delaying the whole project?
A: Since you have asked multiple questions, we will solve the first question for you. If you want any…
Q: A public accounting firm requires the following activities a.…
A: ES- Early Start: Earliest time an activity can start. LS- Late Start: The latest time an activity…
Q: Project ALPHA has 6 activities from A to Fas follows: Activity Duration Preceded By B A D Legend:…
A: Given data is
Q: Immediate Estimated Activity Predecessors Duration A t+5 months В t+1 month C В t+2 months A, C t+4…
A: The critical path method (CPM), or critical path analysis (CPA), is a calculation for planning a…
Q: Ql: For activities shown in table below, find the new time of pro project manager decided to update…
A: Given that: Activities A-J What to do: First: Find the Critical path of the activities. Second:…
Q: 2) Following is a table listing the project activities, sequencing requirements and other relevant…
A: Given that: Activity Regular Time Crash Time Regular Cost Crash Cost A 6 2 $2,000 $3,800…
Q: For each of the following network diagrams, determine both the critical path and the expected…
A: Since we only answer up to 3 sub-parts, we'll answer the first 3. Please resubmit the question and…
Q: Using the information in Table-1, assuming that the project team will work a standard working week…
A: Given data is Working days = 5
Q: Activity Immediate Predecessor(s) Estimated Activity Duration (in days) NONE 2 B A 4 A B 5 E C,D 8.…
A: The network diagram based on the given information is as follows:
Q: a. Determine the expected activity completion times b. Identify the critical path. c. If activity…
A: Given data is
Q: The Virginia Department of Transportation is undertaking aconstruction project to widen a large…
A: For each activity, calculate the expected time μ=(a + 4m + b)/6 For each activity, Variance…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 1 images
- Explain the factors that hinder the success of 5S 1.)Project sponsor is not decision maker 2.) Organizational policies 3.) Lack of experiencce in undertaking cross-functional activities 4.) Lack of top management support 5.) Implementation carried out through orders from the top 6.) Implementation done by task forces 7.) 5S treated as a project 8. )Emphasis on immediate resultsRESEARCH TOPICS1. The difference between project feasibility and project appraisal and their significance toproject sustainability2. The interplay between the project components (Cost, time, scope and quality) and thesignificance to project performance and sustainability3. Report writing process and utility of project report to project managementCan you help me with these two discussions and how much. I added the four causes to discussion 1Discussion 1Choose any four âcausesâ of change within a project in table 9.1 in the text. Provide a project example and scenario, and describe the impact of each change. Was there a level of change control in the project examples that tracked ownership, documentation and approval of these changes?-Poor Communication-Difficulty Scoping-Poor Planning-Unforeseen ProblemsDiscussion 2The identification of all changes to a project is only the first step for ensuring a control system is in place. Describe the detailed steps you would implement for your project to ensure an entire change control process is in place. Consider the following topics in your answer: documentation, analysis, approval and implementation. Why is the baseline configuration important to this topic?
- (a) What questions would you ask of the competencies of the Project Manager?Knowledge, performance and interpersonal skills. (b) Distinguish between management and interpersonal skills of Project Manager. Management- planning, coordination, meeting management. Interpersonalskills- influence, negotiation, leadership. (c) What questions will you ask if you are assigned to manage your project cost?Market prices, spreadsheet of all vendors,Project Cost. 1. Discuss project cost relative to project planning. 2. In which phase is the cost completed in the project life cycle? 3. Explain the Determine Budget process.23 The Identify Stakeholders process has four inputs Three of them are project charter, enterprise environmental factors and organizational process assets. What is the fourth one? A Procurement documents B Stakeholder register C. Stakeholder engagement matrix D Stakeholder management plan 24 The Project Managers have maximum authority in which type of organization? A Weak Matrix B Strong Matrix C Functional D Balanced Matrix 25 Accepted deliverables are an input to the Close Project or Phase process These deliverables would have been accepted through which of the following processes? A. Validate Scope B Control Quality C. Control Scope D. Perform Quality Assurance 26. Which process group corresponds to the "do" part of the plan-do-check-act cycle? A Closing B. Monitoring and Controlling C. Planning D. Executing 27. To control the schedule, a project manager is re-analyzing the project to predict project duration. This is done by analyzing the sequence of activities with the least…
- . Q3: Answer A or B A\ Answer the following 1- A represents Hierarchical Breakdown of a Project in to element. 2- Resources are different than Expenses 3- A hierarchical structure that identifies the company-wide projects and enables organizing and management of those projects by means or subdivision or level is: 4- How many types of reports we have in Primavera 5- The finish of the successor activity depends on the finish of the predecessor activity is referred as B\ Correct the answer 1- Ponds is the base currency by default in Primavera 2- WBS is a Set of codes to organize the project in the EPS in groups according to specific categories 3- Activity tab used to apply constraints, select an activity and select the 4- The E.P.S usually reflects the management structure of your Organization 5-A resource is the project personal job titles or skills, such as mechanical engineer, inspector or CarpenterAABCDE Activity J К Predecessor None PZABUD FGHL-KL EOFICI LA C H с H J.I,K Draft PDS Identify team Kickoff team meeting Source previous rocket Identify & order missing or new materials/parts Assembly Simulation Alpha Test Beta Test Training of key people Buy food to bring Launch DITONT Duration (wks) 1 1 0 2 4 8722860 1. Show the Critical Path. Give reasons for your answer. 2. If you needed to shorten the duration of the project, which activity or activities would you shorten and why?How does 'Evaluating the project team, project team members, and the project manager.' help in closing a project
- a. Develop a network for this projectManaging risk in project is the responsibilities of all stakeholders. Althoughthe potential risk cannot be eliminated, however, the potential risks to happen can be minimized and reduced. In organization, risks can come from all aspects such as business, technical, market, program, or other types of risks. 1. Describe TWO types of analysis processes conducted in performing risk analysis and management.2. List and discuss any THREE types of risk components that can be used to classify the severity level of risk categories. 3. Evaluate how organizations identify, manage, and minimize risks by adopting the use of risk register table?Prepare an Executive Summary of the AMAZON GO and product you want to use for your final projectPrepare an Executive Summary of the AMAZON GO and product you want to use for your final project. Use the attached rubric and include:a brief description of the company and the product, using a or the company’s mission, vision, etc. to explain why you think this product will be successful;a detailed description of the ;and a rough list of potential media choices to reach your target market.For questions check the rubric. My company is Answer Preview for Prepare an Executive Summary of the AMAZON GO and product you want to use for your final projectAPA330 Words Added to cart