6.5 Complete the earthwork calculation sheet here and plot the resulting mass diagram. Divide ccy by 0.9 to convert to bcy (column 10). Calculate th average haul (trapezoidal formula) for the balances on this project. Is this a waste or borrow project? Alge- braic Strip- ping fill Strip- ping cut Vol. of End- Vol. of End- Total fill Adj. fill Total Mass ordi- area area cut sum fill fill cut cut (ccy) (bcy) (ccy) (8) (bcy) (10) (bcy) (11) (bcy) (ссу) (Ьсy) (5) nate (sf) (2) (sf) (3) Station (9) (7) (12) (6) (4) (1) 0.90 10 + 00 80 580 11 + 00 90 2100 0. 12 + 00 100 13 + 00 4650 100 6000 14 + 00 60 80 560 3250 15 + 00 80 1620 16 + 00 1300 85 80 2450 700 17 + 00 100 7800 18 + 00 90 3620 1980 19 + 00 80 20 + 00 80 1310 21 + 00 10 80 860 580 22 + 00 100 10 23 + 00 1620 250 100 3850 24 + 00 100 25 + 00 2600

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
100%
6.5 Complete the earthwork calculation sheet here and plot the resulting mass
diagram. Divide ccy by 0.9 to convert to bcy (column 10). Calculate th
average haul (trapezoidal formula) for the balances on this project. Is this a
waste or borrow project?
Alge-
braic
Strip-
ping
fill
Strip-
ping
cut
Vol.
of
End-
Vol.
of
End-
Total
fill
Adj.
fill
Total
Mass
ordi-
area
area
cut
sum
fill
fill
cut
cut
(ccy) (bcy) (ccy)
(8)
(bcy)
(10)
(bcy)
(11)
(bcy) (ссу) (Ьсy)
(5)
nate
(sf)
(2)
(sf)
(3)
Station
(9)
(7)
(12)
(6)
(4)
(1)
0.90
10 + 00
80
580
11 + 00
90
2100
0.
12 + 00
100
13 + 00
4650
100
6000
14 + 00
60
80
560
3250
15 + 00
80
1620
16 + 00
1300
85
80
2450
700
17 + 00
100
7800
18 + 00
90
3620
1980
19 + 00
80
20 + 00
80
1310
21 + 00
10
80
860
580
22 + 00
100
10
23 + 00
1620
250
100
3850
24 + 00
100
25 + 00
2600
Transcribed Image Text:6.5 Complete the earthwork calculation sheet here and plot the resulting mass diagram. Divide ccy by 0.9 to convert to bcy (column 10). Calculate th average haul (trapezoidal formula) for the balances on this project. Is this a waste or borrow project? Alge- braic Strip- ping fill Strip- ping cut Vol. of End- Vol. of End- Total fill Adj. fill Total Mass ordi- area area cut sum fill fill cut cut (ccy) (bcy) (ccy) (8) (bcy) (10) (bcy) (11) (bcy) (ссу) (Ьсy) (5) nate (sf) (2) (sf) (3) Station (9) (7) (12) (6) (4) (1) 0.90 10 + 00 80 580 11 + 00 90 2100 0. 12 + 00 100 13 + 00 4650 100 6000 14 + 00 60 80 560 3250 15 + 00 80 1620 16 + 00 1300 85 80 2450 700 17 + 00 100 7800 18 + 00 90 3620 1980 19 + 00 80 20 + 00 80 1310 21 + 00 10 80 860 580 22 + 00 100 10 23 + 00 1620 250 100 3850 24 + 00 100 25 + 00 2600
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 10 steps with 12 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning