A plant has an effective capacity of 900 units per dayand produces 800 units per day with its product mix; what is itsefficiency?
Q: A 1,500,000 SF plant employs 300 people and produces 242,000 LCD panel per month. The plant is idle,…
A: Given- No. of workers= 300Monthly production = 242,000 LCD panel per monthFixed costs = $3,000,000…
Q: A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand…
A: Production is the process of converting inputs into finished products and services for the…
Q: If a plant has an effective capacity of 6,400 and an efficiency of 88%, then its actual (planned)…
A: Given data is Effective capacity = 6400 Efficeincy = 88%=0.88
Q: A manufacturing shop is designed to operate most efi ciently at an output of 550 units per day. In…
A: An organization is a group of people who work together to achieve a specific or particular…
Q: Pipes are installed in a process with two resources. The first resource has a capacity of 0.34 pipes…
A: In order to arrive at the capacity of the pipes, first, we need to know the bottleneck. The…
Q: e) How much total idle time is present each cycle? f ) What is the efficiency of the assembly line…
A: Below is the solution
Q: A company makes two products X and Y, using a single resource pool. The resource is available for 8…
A: Availability of resources for production of X and Y = 8 hrs. (480 minutes) Unit load of X = 15…
Q: A product line manufacturing shoes has five stations in series whose individual capacities per shift…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: Explain what is the process of determining expected output in operations
A: Outputs are the results of a task especially following its execution. All submissions for projects…
Q: A company offers ID theft protection using leads obtained from client banks. Three employees work 40…
A:
Q: Mark Tuan, the Production Manager at MT Mills, can currently expect his operation to produce 1000…
A: Find the given details below: Given Details: Current Production Output 1000 Square yards/ ton…
Q: A. If three machines are assigned to an operator, what will be the cost per unit produced? B. If…
A: A) With the help of the data given the following points can be ascertained: Total time of work per…
Q: A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled…
A: Design Capacity = 800 trucks Effective Capacity = 600 trucks Actual Output = 400 trucks
Q: The bathtub theory of operations management is being promoted as the next breakthrough for global…
A: Given Information: Bathtub capacity = 40 gallons of capacity Output = 2 gallons per hour Input = 4…
Q: A manufacturing shop is designed to operate most efficiently at an output of 550 units per day In…
A: A product is a tangible substance that is offered in the market to satisfy the desire or requirement…
Q: Amy Xia’s plant was designed to produce7,000 hammers per day but is limited to making 6,000…
A: Capacity utilization is a part of plant utilization. It means how much capacity the plant is and how…
Q: A company makes two products X and Y, using a single resource pool. The resource is available for 8…
A: Production is the process in which inputs are combined to have the required output. It includes a…
Q: NorSal Trondheim operates a salmon processing facility where fish are purchased from local sources…
A: Note: - Since we answer up to 3 subparts, we will answer questions 1,2 and 3. Please resubmit the…
Q: A computer repair service has a design capacity of 80 repairs per day. Its effective capacity,…
A: Design capacity (DC) = 80 repairs per day Effective capacity (EC) = 64 repairs per day Output per…
Q: Determine the utilization and the efficiency for each of these situations: a. A loan processing…
A: Hence, the efficiency is 87.50% and the utilization is 70%.
Q: A company manufactures a product using two machine cells. Each cell has a design capacity of 250…
A:
Q: me, how does capacity analysis react?
A: There is a limit to how much can be produced in a given day in manufacturing and industrial…
Q: Determine the utilization and the efficiency for each of these situations:a. A loan processing…
A: Calculations: Formula:
Q: Collins Little Company has a staff of 4 employees, each working 8 hours per day at a rate of…
A: a) Determine the labor productivity with the old system:
Q: A process currently services an average of 41 customers per day. Observations in recent weeks show…
A: Given data: Average customers per day = 41 Current utilisation = 90% = 0.90 The management wants a…
Q: The output of a plant is 4335 pounds of ball bearings per week (five days). If each ball bearing…
A: Given data is Output = 4335 pounds Number of days = 5 Weight of ball bearing = 0.0113 gram
Q: The Banana Box plant produces 500 banana boxes in two 10-hour shifts. Due to higher demand, they…
A: The answer would be:
Q: Klassen Toy Company, Inc., assembles two parts (parts 1 and 2): Part 1 is first processed at…
A: Station A= 15min/ unit Station B= 10min/unit Station c= 20min/ unit Station D = 15 min/unit
Q: A seed company has a design capacity of 80 Metric Tonnes (MT) per day. Its effective capacity,…
A: Given Information: Design Capacity = 80 MT per day Effective Capacity = 64 MT per day Actual Output…
Q: A work center containing 7 machines with the same capacity operates 2 shifts per day 6 days per week…
A: Capacity management is the process of ensuring that a company maximises its potential operations and…
Q: 1. Determine the utilization and the efficiency for each of these situa a. A loan processing…
A: Calculations: Formula:
Q: Explain how to keep a repetitive or product-oriented facility's production flow balanced?
A: Manufacturing is a repetitious and product-oriented enterprise in which standard products are…
Q: a. How much will Tri-County need to charge its customers per MWh to break even next year? $. (En…
A: The answer is as below:
Q: Use the information below to calculate the efficiency and utilisation at a repair workshop: 2.3…
A: Given data is Design capacity = 100 vehicles/day Effective capacity = 80 vehicles/day Actual output…
Q: Under ideal conditions, a picture frame manufacturing facility can produce 480 frames per day. Under…
A: Given data Under the ideal scenario, a firm manufactures 480 frames in a day Under a normal…
Q: If a plant has an effective capacity of 6,400 and an efficiency of 88%, then its actual (planned)…
A: Effective capacity is the maximum measure of work that an association is capable of finishing in a…
Q: Uberya Towing Services repair vehicles that break down at an average 8 vehicles per day. The…
A: Given Average no. Of vehicles that breakdown on a daily basis= 8Average no. Of vehicles, a mechanic…
Q: The following diagram describes a service process where customers go through through either of two…
A: The lowest capacity is Operation 2, which is 10 per hour when compared operation 1, 2, and 3. The…
Q: What are the capacity requirements for the next four years? (Assume that there is no learning.)…
A: Plastic sprinklers:1 machineCapacity 240,0005 workersTotal available capacity = 240,000 * 1 =…
Q: A loan processing operation that processes an average of 8 loans per day. The operation ha design…
A: Efficiency is frequently calculated as a ratio of actual to anticipated production. On the other…
Q: Purple Swift manufactures birdhouses in lots of 10. Eachbirdhouse takes 45 minutes to paint. After…
A: Utilization = Average Output Rate / Maximum Capacity Utilization = [(Number of lots x Setup Time) +…
Q: A manufacturing shop is designed to operate most efficiently at an output of 550 units per day. In…
A: Capacity utilization rate is nothing but the process of calculating the percentage of the potential…
Q: A manufacturing firm maintains one product assembly line to produce signal generators. Weekly demand…
A: Given, Weekly demand = 35 units Line operates for 7 hours per day and 5 days per week. Total…
Q: A company operates 8 hours per shift, two shifts per day, five days a week with 12 hours maintenance…
A: Operating hour(h) = 8 Number of per day shift(s) = 2 Days per week (d) = 5 Maintenance hour(M) = 12…
Q: Lucy and Marry have jobs wrapping chocolate candies and placing them into boxes. Lucy, a novice…
A: This question is related to the topic-Production Management and this topic falls under the…
Q: a. An output of 930 units per shift (8.00 hours) is desired for a new processing system. The system…
A: Efficiency is the proportion between total activity time and total station time. Here, we can…
Q: What a flow line for production or service?
A: Flowline production is operated to produce high capacities of goods with high manufacturing rates…
A plant has an effective capacity of 900 units per day
and produces 800 units per day with its product mix; what is its
efficiency?
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 2 images
- A fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each, and only 400 trucks were repaired. What are the utilization and efficiency of the repair shop?3. A bread-manufacturing line typically produces 150 loaves of bread during an 8-hour shift. On average, there are 30 loaves under processing in the line at any given time. What is the value and what is the L value? What is the average time it takes to produce a loaf of bread from the raw ingredients?A. Which machine would is constraint in the plant? B. Which product mix provides highest gross profit? Product M= ______ units Product N=_______units C. What is the maximum weekly net profit this plant can earn using the product mix from Part b?
- Operations management How does the capacity analysis react when many processes are running concurrently?JB Bunt's fleet repair facility has the capacity to repair 800 trucks per month. However, due to scheduled maintenance of their equipment, management feels that they can repair no more than 600 trucks per month. Last month, two of the employees were absent several days each, and only 400 trucks were repaired. What is the utilization of the repair shop?If a plant has an effective capacity of 6,400 and an efficiency of 88%, then its actual (planned) output =_______units (enter your response as a whole number).
- A company has a factory that is designed so that it is most eficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?A company has a factory that is designed so that it is most efficient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?A company has a factory that is designed so that it is most efi cient (average unit cost is minimized) when producing 15,000 units of output each month. However, it has an absolute maximum output capability of 17,250 units per month, and can produce as little as 7,000 units per month without corporate headquarters shifting production to another plant. If the factory produces 10,925 units in October, what is the capacity utilization rate in October for this factory?
- A computer repair service has a design capacity of 80 repairs per day. Its effective capacity, however, is 64 repairs per day, and its actual output is 62 repairs per day. The manager would like to increase the number of repairs per day. Which of the following factors would you recommend that the manager investigate: quality problems, absenteeism, or scheduling and balancing? Explain your reasoning.A business company has the following capacity per month based on the following: 30 working days per month; 1 shift operation at 8 hours per shift; 30 minutes break per shift per employee ABC company produces bicycles and has the following Capacities per process. Frame Welding: 60 bikes per hour per machine Painting: 20 bikes per hour per worker Assembly: 50 bikes per hour per worker Inspection: 100 bikes per hour per worker What can be observed from the system if the demand for the month is 5,000 bikes?Term that describes when multiple (usually similar) products can be produced in a facility less expensively than a single product.