Before answering the following questions, you must draw the arrow diagram, rectangles, network calculations, and the project diagram, the details of which are shown in the table below. Time (week) Activity Dependency Resource b a A 1.5 2.5 B 2 2.5 А, В B 2.5 1 D 1.5 2 0.5 1.5 2 F 1 3 G D, E C, F, G C, G 3 3.5 3 H 4 2 1.5 2.5 2 10- The largest and least valuable of the resources needed by the project are: 7,5 O 9, 2 8, 2 O All options are incorrect 6, 3 O 6, 2 O mm222 33 63
Q: The following table provides the information necessary to construct a project network diagram and…
A: Project crashing is a process which reduces the total duration using additional costs. Here, we can…
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: The new director of special events at a large university has decided to completely revamp graduation…
A: Given data is
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Expected Time= a+4m+b6 Where a= Optimistic time b= Pessimistic time m = Most…
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: league baseball team. Draw a project network given the information in the table that follows.…
A: Find the answers below: Given Details: Given details: ID Description Predecessor Time…
Q: 1- The network below represents a project being analyzed by Critical Path Methods. Activity…
A: Since you have submitted questions with multiple subparts, as per guidelines we have answered the…
Q: 3.1 Draw an Activity-On-Arrow (AOA) network diagram representing the project. Put the node numbers…
A: Critical path examination is an undertaking arranging technique that spotlights on recognizing…
Q: Determine the critical path after you have found ES, EF, LS, LF and slack. State the path and time…
A: The answer is as below:
Q: Norton Industries is installing a new computer system. The activities, the activity times, and the…
A: Crashing an activity is basically adding more assets toward an activity so it tends to be finished…
Q: (a) What is the critical path? (b) How long will it take to complete this project? (c) Can…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The following activities are part of a project to be scheduled using CPM: АсTIVITY IMMEDIATE…
A: This question is related to the topic - Project Management and this topic fall under the operations…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Given data is
Q: Schedules and activities of some projects are shown below Draw the network diagram Activity…
A: I will be drawing the network diagrams for the 2 projects. Please post it again for other projects'…
Q: A project has been defined to contain the following list of activities, along with their required…
A: The a, b and c part answers are shown in the diagram below-
Q: The first question: The part of a construction project whose activities are shown in Table No. 1…
A:
Q: The information in the table below is available for a large fund-raising project. Activity…
A: 1. During forward pass in case of more than two preceding activities the early start will be…
Q: A project manager has compiled a list of major activities that will be required to install a…
A: The Time estimate can be calculated using formula = (Optimistic+4*Most Likely+Pessimistic)/6 Std Dev…
Q: A project has the following activities, with specified precedents and expected durations (in days).…
A: The AON diagram with the given table:
Q: Given the activities whose sequence is described by thefol lowing table, draw the appropriate…
A: Critical path refers to the stage sequences, that require maximum time for the project completion.
Q: В- using the table below, Activity Predecessor Duration A A A D E 1 В E,C F D,B 1- How many paths…
A: The project network diagram is the visual representation of project tasks and their duration to…
Q: HW 5: By using Microsoft Excel construct the Gantt chart for the project with the activities…
A: Given data:
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: A project has the following activities, with specified precedents and expected durations (in hours).…
A: A network diagram is a diagram that shows the visual form of the project activities and their…
Q: a. Draw a CPM network for the project. b. Provide an overview for the project by computing the…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: The Scott Corey accounting firm is installing a new computer system. Several things must be done to…
A: The method of analyzing the set of activities related to the project of the company is known as the…
Q: Kelle Carpet and Trim installs carpet in commercial offices. Peter Kelle has been very concerned…
A: Given Information:
Q: 1. A new application development project at NeuProd, Inc. consists of the following activities:…
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: Activity Predecessor Time(weeks) A 8 B A 6 4 D E A 11 F B 3 D, E, F 1 Using Table A, what is the…
A: Network Diagram,
Q: a Draw the Network diagram on your own paper. b. How many paths are there in the network? c. What is…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: Table 7.4 Activity Predecessor Time(weeks) 8. B 6. 4. D A 11 B 3 G D, E, F 1 1) Using Table 7.4,…
A: 1) The earliest time for completion for this project is 20 weeks so the answer is C)20 weeks
Q: 2. A network consists of the activities in the following list. Times are given in days. Activity…
A: Given data is
Q: A project consists of five activities listed below. The project network is shown for the activities.…
A: Formulae used: Expected time of an activity= ( O + 4.M + P )6 Where, O=OptimisticM= Most…
Q: A. (5 points) Draw AON diagram of the project, including activity durations. B. (4 points) Based on…
A:
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Find the given details below: Activity Dependency Optimistic Time(To) a(Weeks) Pessimistic…
Q: a. Draw a precedence diagram using AOA , AON and Gantt chart. b. Find the critical path using CPM.…
A: Below is the solution:-
Q: (i) Construct a network diagram showing the various logical activity relationships from this…
A: A project schedule network diagram shows the sequential and analytical relationship between tasks in…
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A В 7 C 4…
A: Given Information:
Q: Please help me answer parts 3. and 4. of this question if not all of them. Thank you
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: 11-23 Tom Schriber, the director of personnel of Manage- ment Resources, Inc., is in the process of…
A: In a network diagram, the activities with no predecessor activities are initial activities. When an…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Find the Given details: Activity Dependency Optimistic Time(To) a(Days) Pessimistic Time(Tp)…
Q: The following CPM/PERT network represents a small project with 4 activities labelled A through D.…
A: Given data is
Q: The fo llowing is a table of activities associated with a project at Rafay lshfaq's software firm in…
A: Note: As per the Bartleby guidelines only the first three parts have been answered. AOA ( Arrow to…
Q: Given the activities whose sequence is describedby the following table, draw the appropriate…
A: Draw the path
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: 3. Activities of a project are summarized in the following table. Activity Immediate Duration…
A: a) The network diagram is as follows: The critical path is: B-F-H The project completion time is 24…
Q: a) Draw the network diagram for this project b) Calculate for the slack time c) Find the critical…
A: Find the Given details below: Activity Normal Time(days) Crash Time(days) Immediate…
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: A senior MIS design class project team has developed the following schedule of activities for their…
A: The project network diagram helps in finding the duration of the project. It can also help in…
Step by step
Solved in 2 steps with 3 images
- An enterprise resource planning (ERP) system is best described as: Answers A E A An information system designed to allocate resources, such as staff and rooms, to an organisation's current projects B The software and hardware required to allow functional area information systems to exchange information C An information system that enables an organisation to plan the resources required for upcoming projects DA method to enable legacy departmental information systems to interoperate with newer systems. EA suite of integrated software modules for managing information about business activities.1.You’re managing a project to install 400 windows in a new skyscraper and need to figure outyour budget. Each week of the project costs the same: your team members are paid a total of $4,000every week, and you need $2,000 worth of parts each week to do the work. If the project isscheduled to last 16 weeks, calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project? 2.You’re managing a highway construction project. Your total budget is $650,000, and there isa total of 7,500 hours of work scheduled on the project. You check with your accountingdepartment, and they tell you that you’ve spent a total of $400,000. According to the schedule,your crew should have worked 4,500 hours, but your foreman says that the crew was allowed towork some overtime, and they’ve put in 5,100 hours of work. Calculate theBAC, PV, EV, AC, SPI, SV, CPI, SPI, CV for the project?Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity D. Activity B is connected to activity E. Activity C is connected to activity F. Activity D is…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a). Develop a project network. (b) Develop an activity schedule. Activity EarliestStart LatestStart EarliestFinish LatestFinish Slack A B C D E F (c) What are the critical activities? (Enter your answers as…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop a project network. A project network with 8 activities and 8 directed arcs is shown. Activity Start is connected to activity A. Activity A is connected to activity B and to activity C. Activity B is connected to activity E. Activity C is connected to activity D. Activity D is…Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (d) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes cost? (A, B, C, D, E) = (e) Develop an activity schedule for the crashed project. Activity EarliestStart LatestStart…
- Office Automation Inc., developed a proposal for implementing a software system that will standardize the accounts payable function by automatically issuing an electronic payment upon receipt of the vendor invoice. Contained in the proposal is a list of activities that must be accomplished to complete the project. The following table contains relevant information about the activities. Time (weeks) Cost ($1,000s) Activity Description ImmediatePredecessor Normal Crash Normal Crash A Plan needs 10 8 30 70 B Order equipment A 8 6 120 150 C Install equipment B 10 7 100 160 D Set up training lab A 7 6 40 50 E Conduct training course D 10 8 50 75 F Test system C, E 3 3 60 (a) Develop an activity schedule. What are the critical activities? (Enter your answers as a comma-separated list.) Assume that the company wants to complete the project in six months or 26 weeks. What is the amount of crash time (in weeks) for each activity that minimizes…1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift. Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately? NUYLOTNQhObm1bEVKUTO90 a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry. O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this. CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby. 40 Cara's gift is very thoughtful and will help to build a relationship with her clients. NUTYks10TNRUQ2h0bmkbEVKUTO90Chuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of work
- You are working in the planning team of a food factory in Malaysia, producing Lipton. Tomorrow is the deadline for shipping deliveries to Giant supermarkets ready for a new Lipton promotion. The promotion has featured an extensive social media campaign to drive sales. You have just been informed that the delivery of raw materials has broken down. There is a risk that the tight manufacturing schedule will not be feasible in the time remaining. So in this case, 1-Who dod you need to keep informed? 2. What method of communication would you choose for each?Image of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.Dave is the project manager for a construction project that is building agazebo. When the project first started, he met with the stakeholders to definethe scope. The sponsors mentioned that the gazebo is a really important partof their daughter’s wedding ceremony that was planned for 7 months fromthen. In fact, they said that if the gazebo couldn’t be completed in 7 months, itwouldn’t be worth it for them to even start the project. Dave wrote down the7-month deadline to put in his Project Scope Statement. In which section ofthe document did the deadline appear?”A. Project ConstraintsB. Project DeliverablesC. Project ObjectivesD. Project Assumptions Which of the following is a “hygiene factor” under Herzberg’s Motivation-Hygiene Theory?A. Recognition for excellent workB. Self-actualizationC. Clean clothingD. Good relations with coworkers and managers