In a job shop, effective capacity is only 79 percent of design capacity, and actual output is 53 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity? a. The Design Capacity needed to achieve the required actual job outputs =Blank 1 (round to whole number) b. The Effective Capacity needed to achieve the required actual job outputs = Blank 2 (round to whole number)
Q: An operations planner, Lovell Bradley, is developing a sales and operations plan that involves back…
A:
Q: If contracts are not well managed by the buying organisation could lead to adverse outcome. You are…
A: The objective of the question is to identify and discuss five potential negative outcomes that could…
Q: Explain the function of demand forecasting in the logistics system and supply chain of a company!…
A: Find the given details below:
Q: for this table. In other words, the table of data provided does not need a composite primary key.…
A: The objective of the question is to identify and depict the full key, partial, and transitive…
Q: Network Analysis Given this WBS, draw out a network diagram and use the two-pass and enumera methods…
A: The objective of this question is to determine the critical path for the project based on the given…
Q: R7.3. A farm sells its own produce in its large retail and wholesale outlets. It can produce…
A: Linear programming is a mathematical method used to find the best possible outcome or solution from…
Q: You have just determined the actual number of workstations that will be used on an assembly line to…
A: Total cycle time is :Actual number of workstations is :The time for the sum of all the tasks is :The…
Q: A company has three warehouses that supply four stores with a given product. Each warehouse has 30…
A: Find the given details below:Note that we could not solve the first condition through the solver…
Q: Worthington Hills grocery store has five regular checkout lines and one express line (12 items or…
A:
Q: Month Demand Forecast Error Abs Error alpha 1 20 2 18 3 21 4 25 5 24 6 27 7 22 8 30 9 23 10 20 11 29…
A: Given month and actual demand: MonthDemand (At)120218321425524627722830923102011291222
Q: Priority-Discipline Queueing Models Southeast Airlines is a small commuter airline serving primarily…
A:
Q: You are a Quality Manager for a very well-known food ingredient company that produces monosodium…
A: The process mean (μ) = 2018 g The process standard deviation (σ) = 16 gSample of bags = 8
Q: A company manufactures plastic bottles, buckets, and cups. The profit units are $10 for a plastic…
A: The Simplex Method or Simplex Algorithm is used for calculating the optimal solution to the linear…
Q: Identify how one can avoid making confirmation bias and overconfidence bias errors in the…
A: The objective of this question is to understand how to avoid two common cognitive biases -…
Q: Facility Coordinate Location (x, y) Cost of unit truck Annual Load load (ton) ABCDE 10, 80 10 452…
A: We have given: FacilityCoordinate LocationCost of unit truck loadAnnual Load…
Q: d iscuss the role of supervisors or managers in conducting traditional performance reviews.
A: Performance evaluations are essential to an employee's professional development in an organisation…
Q: Using the data in the images, compute the inventory value of each product by multiplying the…
A: IDProduct categoryProduct namePurchase costSelling priceSupplierQty. on hand1LeisureBlue…
Q: 2 to 17. Compute for the inventory-related cost if the entity purchased 500 boxes more and less than…
A: EOQ stands for economic order quantity. It is a method to measure the quantity which should be…
Q: s project. d the project duration is 30 days. (Enter your response as a whole number.) e activities…
A: The objective of the question is to understand the details of activities G, H, and I in a project…
Q: ou have just started work as the Supply Chain Manager for Skateboards company These powered skate…
A: Supply chain management is the aspect of management that deals with all the movement or flow that…
Q: Mention and explain three (3) reasons why multinational companies are growing.
A: The growth of multinational companies can be attributed to several factors. Here are three key…
Q: 4. The Spencer Optics Company produces an inexpensive line of sunglasses. The manufacturing process…
A: SOLUTIONGiven Informationlet's break down the informationBy the using these excel formulas in the…
Q: Transmissions are delivered to the fabrication line three at a time. It takes two hour for…
A: Operation management is an aspect of management that deals with the management of the production,…
Q: Please help with correct answers in details: Step by step The product development group at Landon…
A: Project Scheduling and Critical Path Analysisa) Activity Schedule and Critical Path:Here's the…
Q: One role a group member can play is evaluating by offering judgments about a topic, a(n)…
A: 1.one role a group member can play is evaluating by offering judgments about a topic,a(n)…
Q: Sales for the past five months have been 15, 18, 12, 17, 13. Use the following methods to obtain a…
A: The last-value method is one of the simplest forecasting techniques. It involves taking the sales…
Q: Please help with correct answers in details: Step by step Suppose these data show the number of…
A: Compute four-week and five-week moving averages for the time series.WeekSales (1000s of…
Q: The Bawl Corporation supplies alloy ball bearings to auto manufacturers in Detroit. Because of its…
A: For calculating the weeks of supply and inventory turns, use the following formulas:a. Weeks of…
Q: Draw the network diagram. Calculate the expected duration and variance of each activity. Calculate…
A: Project management is the branch of management that deals with organizing and overseeing the…
Q: = The table below defines the precedence relationships and element times for a new model toy. (a)…
A: Ideal cycle time = 1.1 minuteRepositioning time = 0.1 minuteUptime proportion = 1.0 minute
Q: Kimpel Products makes pizza ovens for commercial use. James Kimpel, CEO, is contemplating producing…
A: Find the given details below:
Q: ormulate an integer linear program that can be used to determine the minimum number of service…
A: A linear program model is a mathematical model with a linear objective function a set of linear…
Q: You have committed to migrating your software platform from a server based to a cloud based product…
A: Given, the total cost of the project: Project completion time: monthsAmount paid after months: The…
Q: For each of the following parts, answer the question as specifically and completely as is possible…
A: Note:Since you have posted multiple questions, we will provide the solution only to the first…
Q: Jim's Camera shop sells two high-end cameras, the Sky Eagle and Horizon. The demands and selling…
A: Therefore:Revenue function (R=226Ps−0.60Ps2+0.45PsPh+265Ph−0.64Ph2)Optimal price for Sky Eagle…
Q: Compute the reliability of the bridge system as shown in Figure 1. If the omponent reliability is R₁…
A: Reliability refers to the probability that a system, component, or process will perform its intended…
Q: What is throughput time of this process? A 12.8 min B 10.75 min C 19.00 min D 31.00 min E 22.50 min
A:
Q: An output of 720 units per shift (7.40 hours) is desired for a new processing system. The system…
A: Desired output = 720 unitsShift timing = 7.4 hrs.No. of working stations= 4Task time at each station…
Q: Please provide information in a short paragraph format for the Mt. Kumar Road project in Grenada.…
A: Project management is the branch of management that deals with organizing and overseeing the…
Q: Location Score Factor (100 points each) Weight Convenience A 0.15 80 Parking facilities 0.20 72…
A: Using the weight and location score provided in the table, we have to find out the composite score…
Q: Please help with question #2. The based country is Trinidad and the countries trading to is…
A: Mitigating Foreign Exchange Risk for a Trinidadian MNCScenario: Let's simulate a Trinidadian MNC…
Q: Activity Predecessors 1 Description Duration Start job 1 2 1 Relocate electric 6 3 1 4 3 5 4 6 4 7…
A: To calculate the Latest Finish (LF) time for each activity, we'll start by drawing the Activity on…
Q: 9. The VP of manufacturing for the N. L. Hyer Company is ready to decide on her sales and oper-…
A: Production rate, in terms of manufacturing, refers to the number of goods that can be produced…
Q: Choose a business of your own wish and draw a supply chain and list the key components. Post the…
A: Operation management is an aspect of management that deals with the management of the production,…
Q: Within an organization, democratic decision making tends to lead to Group of answer choices more…
A: The objective of the question is to understand the impact of democratic decision making within an…
Q: How to respond in 100 words? Since the early years of the first decade of the 21st century, there…
A: Whistleblowing is the act of disclosing information pertaining to unethical or illegal practices…
Q: Describe your version of a 'cut set' leading to a fall from a construction ladder.
A: The objective of this question is to describe a 'cut set' that could lead to a fall from a…
Q: Are Key Suppliers Part of the Sourcing Team Process?
A: Operation management is an aspect of management that deals with the management of the production,…
Q: What is the impact of skills on current and future workforce requirements in an organization? How…
A: Skills play a pivotal role in shaping both current and future workforce requirements within an…
Q: Consider the following linear programming model: MAX Z=MAX(4X₁ + 2X₂ +5X₂) -----> Objective function…
A: Linear programming helps us to find the optimal solution/best outcome, given the constraints.
Step by step
Solved in 3 steps with 2 images
- I submitted this question a couple days ago. However, I am still a little confused. Here was the original question: Collins Little Company has a staff of 4 employees, each working 8 hours per day at a rate of $20/hour. Their overhead expenses are $200/day. Collins processes and closes on 12 titles each day. They are considering purchasing a computerized title search system that will allow the processing of 20 titles per day. With the new system, they could cut their staff to 2 employees working the same hours at the same pay, but their overhead expenses would double to $400 per day. 1. Compute the labor productivity with the old system (in titles / hour). 2. Compute the labor productivity with the new system (in titles / hour). 3. Compute the multifactor productivity with the old system (in titles / dollar). 4. Compute the multifactor productivity with the new system (in titles / dollar). One of the answers is: Labor Productivity = 12/(4*8) Another is: Labor Productivity =…1. What is the outcome when a bottleneck resource is augmented with more capacity? 2. Which of the following statements are true? a) Installed capacity in service systems are always based on peak demand b) Service systems designed to handle average capacity will be more effective c) Improving effectiveness of a service will require greater investment of capacity d) None of the above 3. The arrival rate at the second server in a two stage serial queuing system is a. Service rate of server 1 b. Same as arrival rate at server 1 c. Minimum of service rate and arrival rate at server 1 d. Cannot be determined In a worker paced assembly line, consider a situation where the daily requirement has suddenly increased. Which of the following statements will be true? 4. In a worker paced assembly line, consider a situation where the daily requirement has suddenly increased. Which of the following statements will be true? a) The required cycle time will also increase proportionally b) The…An airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, the average number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand is expected to increase to 99 customers for this flight segment in three years, what capacity requirement should be planned? Assume that management deems that a capacity cushion of 20 percent is appropriate. The needed capacity requirement is [A] customers per day. (Enter your response rounded up to the next whole number.)
- Please do not give solution in image formate thanku Some of your constraints have slack. What does that mean? Select one: A. Slack indicates how much one additional unit of the resource is worth. B. If more of the resource were available, then profit could increase. C. There is more of the resource than is needed for the best solution. D. Slack indicates the total number of hours.Help ! Choice Bank receives credit card applications that need to be reviewed for a decision. There are two types of applications; preapproved, and non-preapproved. Preapproved applications only need a quick review and therefore take 6 minutes to process. Applications that are not preapproved need a secondary credit check and take 15 minutes to process. The bank receives 10 preapproved applications every hour and 6 applications that are not preapproved every hour. What is the utilization of the process? Group of answer choices 50 % 62.5 % 68.75 % 75 % 100 %A company producing a standard line and a deluxe line of dishwashers has the following time requirements (in minutes) in departments where either model can be processed. Standard Deluxe Stamping 3 6 Motor Installation 10 10 Wiring 10 15 The standard models contribute $20 each and the deluxe $30 each to profits. Because the company produces other items that share resources used to make the dishwashers, the stamping machine is available only 30 minutes per hour, on average. The motor installation production line has 60 minutes available each hour. There are two lines for wiring, so the time availability is 90 minutes per hour. Write the formulation for this linear program. What are the optimal daily production quantities of each product and the optimal daily profit?
- Mack’s guitar fabrication shop produces low cost, highly durable guitars for beginners. Typically, out of the 100 guitars that begin production each month, only 80 percent are considered good enough to sell. The other 20 percent are scrapped due to quality problems that are identified after they have completed the production process. Each guitar sells for $300. Because some of the production process is automated, each guitar only requires 10 labor hours. Labor is paid at $10/hour, materials cost is $40/guitar, and overhead is $2,000. a) Calculate the labor and multifactor productivities. b) After some study, the operations manager recommends 3 options to improve the company’s multifactor productivity: (1) increase the sales price by 10 percent, (2) improve quality so that only 10 percent are defective, or (3) reduce labor, material, and overhead costs by 10 percent. Which option has the greatest impact on the multifactor productivity measure?Effective capacity is:a) the capacity a firm expects to achieve, given the currentoperating constraints.b) the percentage of design capacity actually achieved.c) the percentage of capacity actually achieved.d) actual output.e) efficiency.An airline company must plan its fleet capacity and its long-term schedule of aircraft usage. For one flight segment, the average number of customers per day is 70, which represents a 65 percent utilization rate of the equipment assigned to the flight segment. If demand is expected to increase to 80 customers for this flight segment in three years, what capacity requirement should be planned? Assume that management deems that a capacity cushion of 15 percent is appropriate. The needed capacity requirement is enter your response here customers per day. (Enter your response rounded up to the next whole number.)
- Which answer is FALSE and explanation A populer fast food restaurant has one cashler who takes an average of 1.5 minutes to serve a customer.suppose demand at the restaurant is forecast to be 35 Customers per hour from 11am to 1 prn and 50 customers per hour from 6 pm to 8 pm.which of the following statements are false? (a) The flowrate of the restaurant is 35 customers per hour during the 11am to 1pm period and 40 customers per hour during the 6pm to 8pm period (b) The flowrate of the restaurant is 35 customers per hour during the 11am to 1pm period and 50 customers per hour during the 6pm to 8pm period (c) The capacity of the restaurant is 40 customers per hour during both time intervals - 11am to 1pm and 6pm to 8pm (d) the utilization of the cashier is 87.5% during the 11am to 1pm period and 100% during the 6pm to 8 pm periodA shoe manufacturer that operates 8 hours a day (no break) has developed a new sneaker per an important client's request. However, the client does not want to proceed with an order if the manufacturer cannot reach at least 88% efficiency during production. If SAM (standard allowed minute) to complete 1 pair of shoes is 30 minutes, how many pairs of shoes must each employee at the factory produce in a day to meet this client's requirements? Round your answer to the nearest whole number, but do not round until your final answer. Group of answer choices 14 pairs 16 pairs 15 pairs 12 pairsIn a job shop, effective capacity is only 88 percent of design capacity, and actual output is 69 percent of effective output. What design capacity would be needed to achieve an actual output of 11 jobs per week? What is its effective capacity?a. The Design Capacity needed to achieve the required actual job outputs =( ) (round to whole number)b. The Effective Capacity needed to achieve the required actual job outputs =( ) (round to whole number)