The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Following are five projects under consideration. Criteria Weight Project 1 Project 2 Project 3 Project 4 Project 5 Strong sponsor Project 1 Project 2 Project 3 Project 4 Project 5 2 2 4 6 10 8 Supports business strategy 3 3 Which project would you choose first? c 5 4 2 0 10% of sales from Urgency new products Competition 1 4 7 6 10 1 10 0 2 1 1 7 Using the scoring matrix above, what score would you give to each project? 3 2 5 1 8 5 Fill market gap 1 5 6 6 1 1

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question
If the weight for "Strong Sponsor" is changed from 2 to 5, what score would you give to each project?
Project 1
Project 2
Project 3
Project 4
Project 5
Now, which project would you choose first?
Why is it important that the weights mirror critical strategic factors?
Transcribed Image Text:If the weight for "Strong Sponsor" is changed from 2 to 5, what score would you give to each project? Project 1 Project 2 Project 3 Project 4 Project 5 Now, which project would you choose first? Why is it important that the weights mirror critical strategic factors?
EX2-7 (Algo) The Custom Bike Company...
The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Following are five projects under
consideration.
Criteria
Weight
Project 1
Project 2
Project 3
Project 4
Project 5
Project 1
Project 2
Project 3
Project 4
Project 5
Strong sponsor
2
2
4
6
=
10
8
Supports business
Which project would you choose first?
strategy
3
3
5
4
2
0
10% of sales from
Urgency new products Competition Fill market gap
1
4
0
2
1
1
7
Using the scoring matrix above, what score would you give to each project?
3
2
5
1
8
5
7
6
10
1
10
1
5
6
6
1
1
Transcribed Image Text:EX2-7 (Algo) The Custom Bike Company... The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Following are five projects under consideration. Criteria Weight Project 1 Project 2 Project 3 Project 4 Project 5 Project 1 Project 2 Project 3 Project 4 Project 5 Strong sponsor 2 2 4 6 = 10 8 Supports business Which project would you choose first? strategy 3 3 5 4 2 0 10% of sales from Urgency new products Competition Fill market gap 1 4 0 2 1 1 7 Using the scoring matrix above, what score would you give to each project? 3 2 5 1 8 5 7 6 10 1 10 1 5 6 6 1 1
Expert Solution
steps

Step by step

Solved in 6 steps with 5 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.