The expected finishing date for the project with 75% probability. * What is the probability of completion of the project in 14.5 months? * What is the probability of completion of the project in 20 months? *
Q: EX: 1.9 Given the estimated activity times below and the network refer to the table and network…
A: Find the Given details below: Activity Immediate predecessor Optimistic Time(To) a(Days)…
Q: c. What is the expected project completion time? (Do not round intermediate calculations. Round your…
A: Expected time is calculated with the help of following formula:
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A:
Q: he project manager of Good Public Relations gathered the data shown in the following table for a new…
A: Below is the solution:-
Q: A completion time (X) is expected to be 52 weeks, with a variance of 64. What is the probability the…
A: This question is related to the topic - Project Management and this topic falls under Operations…
Q: Suppose that the crash cost is $10 million, normal cost is $8 million, normal project time is 10…
A: Project crashing is a method used in project management to increase the project time by decreasing…
Q: d. The partners have decided that shortening the project by two days would be beneficial, as long as…
A:
Q: Consider the following diagram, why is it used and explain what information does it provide to the…
A: The diagram is called the risk impact/probability chart. This diagram uses two dimensions;…
Q: What is the duration of the project? Identify the critical path. How many days can ACTIVITY C be…
A: “Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Project Typhoon has a net present value of $10,000 and a profitability index of 1.01. Project…
A: Net present value (NPV) is the difference between the current value of income and the present value…
Q: a. What is the probability the project will be finished weeks or less? b. What is the probability…
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: MODELLING AND SIMULATION 1. Is it possible to conduct all the orientation activities in a single…
A: Modeling and simulation (M&S) is the utilization of models (e.g., physical, numerical, or…
Q: The following table shows estimates of activity times (in weeks) for a project: Optimistic Most…
A: The critical path is the past that takes a higher time to complete the whole project successfully as…
Q: Assuming that the project is performed by an outside contractor, what is the role of the customer's…
A: Modular design is basically to decompose complex systems into simple modules in order to more…
Q: Exercise regular time acceleration time Normal Cost acceleration cost Precedents A 4 3 900 1000 ---…
A: There are three possible paths AD = 4+6 = 10 B = 8 CE = 4+7 = 11 Normal project duration…
Q: Calculate the probability that the project can be completed in 50 days or less., Calculate the…
A:
Q: What are the steps for the project closure phase?
A: The final phase of the project lifecycle is termed as closure phase of the project. At this stage,…
Q: The following precedence diagram reflects three time estimates in weeks for each…
A: Time Estimates Expected Activity times (=(a+4m+b)/6) Standard Deviation = (b-a)/6 Variance…
Q: Discuss the concept of Project Crashing
A: When abbreviate the duration of a project by lowering the time of one or more tasks, this is known…
Q: Expected length of a project is 37.16 days and the variance of its length is 6.14 days. What is the…
A: Project duration is the total time incurred to finish the project successfully in measured workdays.…
Q: 2. Below the data for a construction project is given. Activity Precedence A 8 14 11 B A 7 15 8 4 6…
A: Given data is
Q: The optimistic duration for a project is 10 weeks. The worst case estimate is 22 weeks, and the most…
A: t( p) = 22 t(o ) = 10 t(m) = 13 expected duration assuming beta distribution is t(e) = (t(o) +…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: When will the project be completed?
A: Project network diagram is the diagram that visually represent the project activities and their…
Q: How can we determine the probability that a project will be completed by a certain date? What…
A: PERT: it stands for Project Evaluation and Review Technique. It shows the network of the project by…
Q: Determine the probability that the project will be completed in 23 weeks, 25 weeks and 27 weeks.
A: Here, The expected activity time or time estimate could be determined using the formula, (Optimistic…
Q: Vhat is the probability that the project will be completed in 15 days if the standard deviation is…
A: Assembly line balancing means when each task is assigned to a workstation that is within an assembly…
Q: What trade-offs are associated with time and cost estimates for a proposed project?
A: Tradeoffs are where one thing decreases to balance the increase of another thing and vice – e –…
Q: Given the project information in the following table, what is the probability of completing the…
A: THE ANSWER IS AS BELOW:
Q: Based on the case below, answer the following questions: The duration for the project is two year.…
A: The question is related to Project Management. The details are given.
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Mean (x) = 40 weeks Desired completion time (μ) = 40 weeks Variance (σ2) = 9 weeks
Q: Define Time–Cost Models and Project Crashing?
A: Project crashing Project crushing refers to the process of reducing the project duration by…
Q: a. Determine the expected project completion time and the variance. b. What is the project's…
A: The critical path is a method to find the shortest duration by which a project can be completed with…
Q: Please Keep in mind that the activity is upto G only. General Foundry's project crashing data are…
A: Below is the solution:-
Q: Develop a project network. Determine the expected project completion time. What is the probability…
A: A project network diagram is a graph that shows how a project's activities should be completed in…
Q: the value of the business case, benefits management plan and the feasibility study to the project…
A: The Value of the Business Case: A Business Case defines the value a project will deliver. Costs and…
Q: b. The probability that the project will require more than 49 weeks. (Round intermediate…
A: A project schedule network represents the sequential and analytical connection between tasks in a…
Q: You have collected the data for a Time-Cost CPM Scheduling model analysis. The time is in days and…
A: Find the Given details below: Activity Predecessor Normal duration (NT) (Days) Normal cost (NC)…
Q: We are planning to develop a room reservation system that is estimated to have 400 story points of…
A: It is very important for organization to take such steps that are helpful in the success of the…
Q: How do we estimate the likelihood of a project being finished by a certain date? In this…
A: Project Evaluation and Review Technique (PERT) is a technique for evaluating and reviewing projects.…
Q: What is the probability that the project will be completed by a specific date?
A: The probability of completing a project by a specific date is the date within which the chances of…
Q: 8- The probability of completing the project in a time greater than the critical path time plus 2…
A: The probability is seen corresponding to z-score under normal distribution is considered in the…
Q: The project manager of a task force planning the construction of a domed stadium had hopedto be able…
A: To solve this question let's first draw the activity diagram and identify the critical path for…
Q: Determine the probability that the project will take less than 42 weeks.
A: Given data is
Q: Crash the project to 25 days. а. b. What will the total crashing cost be? с. What activities will be…
A: Project crashing is a method in project management to speed up the project time by reducing the…
Trending now
This is a popular solution!
Step by step
Solved in 4 steps with 3 images
- Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?O O D 40 4 22:31 photo_2021-02-2... O By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A В CDEF GHIJ Duration 8 28 4 6. 4 5 6 (days) Following C,DEFGH Activity * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? 7. 5,8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)
- ← Consider the following crash data for a project. Times are given in weeks. ACTIVITY A B C D E F How many week(s) of crashing are available for activity E in the table above? Activity E has sweeks of crashing available. What will be the cost of activity E if it is completed in 3 weeks? The cost will be $ NORMAL TIME 4 7 8 3 7 6 CRASH TIME 4 5 3 1 1 3 NORMAL COST ($) 1,400 5,000 5,700 2,400 1,100 2,800 CRASH COST ($) 1,400 6,200 8,700 3,800 5,900 5,200 (s) po TimeChuck’s Custom Boats (CCB) builds luxury yachts to customer order. CCB has landed a contract with a wealthy customer. Relevant data are shown in the table below. The complication is that the customer wants delivery in 32 weeks or he will impose a penalty of $375 for each week his yacht is late. Activity Immediate Predecessor Normal Time (NT) Weeks Crashing Cost 1st Week 2nd Week A ― 9 $410 $415 B A 7 125 -- C A 5 45 45 D B 4 300 350 E C 6 50 -- F D, E 5 200 225 G F 8 -- -- H F 7 85 90 I G 6 90 -- Construct a network diagram for the project Indicate the critical path when normal activity times are used. Develop a crashing schedule. Note: No activity can be crashed more than two weeks. Show breakdown of workmake the project start date 3 Jan 2022 Level the following multi-project operation. Work package Description Duration (weeks) Predecessors Resources A1 Analysis & design – Proj 1 4 - SAD B1 Production – Proj 1 7 A1 PROD C1 Testing – Proj 1 3 B1 TEST D1 Install – Proj 1 2 C1 INSTALL A2 Analysis & design – Proj 2 4 A1 SAD B2 Production – Proj 2 5 A2 PROD C2 Testing – Proj 2 3 B2 TEST D2 Install – Proj 2 1 C2 INSTALL A3 Analysis & design – Proj 3 8 A2 SAD B3 Production – Proj 3 12 A3 PROD C3 Testing – Proj 3 5 B3 TEST D3 Install – Proj 3 3 C3 INSTALL A4 Analysis & design – Proj 4 8 A3 SAD B4 Production – Proj 4 10 A4 PROD C4 Testing – Proj 4 4 B4 TEST D4 Install – Proj 4 2 C4 INSTALL show the schedual before the leveling show the schedual of the project after leveling…
- By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B BThe following table shows the various activities of the development of a new product in your organization. Activity Event Immediate Predecessor(s) Estimates of Activity Duration (Weeks) Optimistic (To) Most Likely (Tm) Pessimistic (Tp) Average (Te) 1 A - 2 3 4 ? 3 2 B A 1 2 3 2 3 C A 1 2.05 4 2.2 4 D B 4 5 6 5 5 E B 3 4 5 4 6 F C 2 3 4 3 7 G D 1.2 2 4 2.2 8 H E,F, G 3 4 6 4.167 9 I H 3 4 5 4 10 J I 2 1 3 1.5 Questions: Draw the PERT network from the given data. (Consider the following activity description with associated cost data shown in Table 1. The cost data represents the total cost and should be considered linear with time. Table 1: Crash Cost Table Activity Immediate Predecessor Normal Duration (days) Normal Cost ($) Crash Duration (days) Crash Cost ($) A --- 5 50 3 150 B --- 4 40 2 200 C B 7 70 5 250 D A, C 2 20 1 50 E A, C 5 125 1 525 F B 10 80 7 290 G D 7 50 3 250 H E, F 6 60 3 180 Reduce the project duration to minimum duration and calculate the cost. Note:- Do not provide handwritten solution. Maintain accuracy and quality in your answer. Take care of plagiarism. Answer completely. You will get up vote for sure.
- Preceding Activity Crashed Cost per week $600 $700 $400 Activity Normal Completion Time (week) Crashed Completion time (week) A 7 5 B 12 10 A 8 2 $800 $300 $500 E C, D 5 4 F E 9 8 D. F 10 10 i. Draw the network diagram linking all the activities in a way that it shows if there exist any preceding activity/activities before starting each of the mentioned activities in the above table, ii. Showing the earliest start time, the earliest finish time, the latest start time and the latest finish time of each of the activities in the project determine the completion time of the project and the critical path. ii. Find the slack time (delay time) of each of the activities, the critical and the non-critical activities. Find the minimum possible completion time of the project by considering the crashed completion times and the minimal total cost of that crashing the project. iv. Need proper handwritten answers. Thank you!for the following project, assume the quantity for the project Equal 37, use LSM to determine the finish date for the project. Productio Activity IPA n Rate Relation [Day/m] A 1 В A 3 FF 2 SS Answer:Consider the following project network and activity times (in days). E Start Finish D F G Activity | A B C D EF G Time 3 5 6 .2 The crashing data for this project are as follows: Time (days) Cost ($) Activity Normal Crash Normal Crash 800 1,200 2,000 A 2 1,400 В 2 1 1,900 3 2,800 1,500 1,800 2,300 E 6 4 2,800 1,000 1,000 F 2 1 600 G 2 1 500 a. Find the critical path and the expected project completion time. b. What is the total project cost using the normal times? Assume that management desires a 12-day project completion time. c. Formulate a linear programming model that can be used to assist with the crashing decisions. d. What activities should be crashed? e. What is the total project cost for the 12-day completion time? 2.