Determine the probability that the project will be completed in 23 weeks, 25 weeks and 27 weeks.
Q: 1- Total project finishing time. 2- Critical path 3- Free float for each task. • 4- If Activity B is…
A: The critical path method is a project management technique that identifies the sequence of tasks…
Q: Identify the critical path in the project. b. Determine the length of the project. Using the data,…
A: The critical path method is a process that helps to identify tasks that are essential for project…
Q: 1- Total project finishing time 2- Critical path, 3- Free float for each task. • 4- If Activity B is…
A: The critical path is the path with the longest duration.
Q: The following six activities constitute an overall bar chart portrayal of 4-month project. Two…
A: This question is related to the topic of Project Management and this topic falls under the…
Q: Given the following network, with activity times in months, determine the earliest and latest…
A: Formula:
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A:
Q: 1- Construct the project network 2- Find the expected duration and variance for each activity 3-…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Provide an example of a possible early project timing problem and an example of a possible late…
A: Introduction:- One of the most typical issues in construction projects is unanticipated…
Q: Draw the project network. Find the critical path and total project duration. Find the Earliest Start…
A: NOTE: AS PER GUIDELINES, WE ARE ONLY ALLOWED TO DO FIRST THREE PARTS OF THE QUESTION. FOR REST…
Q: The expected finishing date for the project with 75% probability. * What is the probability of…
A: THE ANSWER IS AS BELOW:
Q: Discuss the ethical considerations associated with completting a project in the shortest possible…
A: Three things that drive ethical conduct are responsibility, honesty, and respect, which has been…
Q: A completion time (X) is expected to be 52 weeks, with a variance of 64. What is the probability the…
A: This question is related to the topic - Project Management and this topic falls under Operations…
Q: Set up a table and calculate Early Event Times (TE), Late Event Times (TL), Activity Free Slack…
A: THE ANSWER IS AS BELOW:
Q: Critical path and project duration
A: Activity Predecessor Time a - 3 b a 3 c b 2 d b 4 e b 1 f c 2 g e 2 h d,f,g 2 i…
Q: Duration Durations Figure 3. Project Schedule Network (Duration in Days) Q10-11-12 Consider the…
A:
Q: The critical path through a network consists of activities A, B and C where each activity has an…
A: Duration of each critical activity = 10 weeks Total duration of critical path = Duration of A +…
Q: The project detailed in the table below is contracted for delivery in 11 weeks, with a penalty…
A: A project network diagram is a graphic depiction of a project's process. A network diagram is a…
Q: Consider the project given below with the normal and crash costs (in thousands of PhP) and times (in…
A: 1. AOA diagram:
Q: Why might a probabilistic estimate of a project’s completion time based solely on the variance of…
A: Near critical paths might have a larger path variance when compared to the critical path itself,…
Q: The following precedence diagram reflects three time estimates in weeks for each…
A: Time Estimates Expected Activity times (=(a+4m+b)/6) Standard Deviation = (b-a)/6 Variance…
Q: Find the total cost associated with the project as Data is given in Table 1)
A: Given that: Activity Expected Time Standard deviation Cost A 3 0.3 $2,000 B 2 0.5 $3,000…
Q: Discuss the concept of Project Crashing
A: When abbreviate the duration of a project by lowering the time of one or more tasks, this is known…
Q: Find the total duration of the project and critical pa ne the project start date 1/10/2019) by using…
A: Below is the solution:-
Q: An analyst determined that the critical path consists of activities B-D-F. Compute the expected…
A: Here, from the table data, we have the following information, activity ID, optimistic time for each…
Q: How can we determine the probabil ity that a project will be completed by a certain date? What…
A: Introduction: Probability can be defined as the occurrence of random events and which gives us an…
Q: What is the total cost on day 9? What is the total project duration? If activity B is delayed four…
A:
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (x) = 40 weeksDesired completion time (μ) = 40 weeks or…
Q: a) Determine the expected completion time and variance for each activity. b) Determine the total…
A: To calculate the Mean or Expected completion time for each activity is- [tA+4(tM)+tB]/6 Similarly,…
Q: 1. A project was planned using PERT with three-time estimates. The expected completion time of the…
A: Given- Expected completion time (μ)= 40 weeksDesired completion time (x) = 46 weeks or…
Q: How can we determine the probability that a project will be completed by a certain date? What…
A: PERT: it stands for Project Evaluation and Review Technique. It shows the network of the project by…
Q: 1. Draw the network diagram. 2. Calculate the expected duration and variance of each activity. 3.…
A: The project network is the diagram that shows the order of completion of project network activities…
Q: By using Bar chart planning method, find the following: - Total duration for the project activities…
A: ANSWER IS GIVEN BELOW:
Q: snip
A: Given, First path ( X1) , Length= 10 days Variance= 2 days Second path ( X2), Length= 11 days…
Q: Activity Preceding activity Activity duration A - 6 B - 3 C - 1 D A, B 2 E A, C 5…
A: Given data is
Q: 3- The value of the variance of the critical path in the project is
A: Variance = square of sum standard deviations of critical activities Standard deviation = (b-a)/6
Q: a. Determine the expected project completion time and the variance. b. What is the project's…
A: The critical path is a method to find the shortest duration by which a project can be completed with…
Q: Given the following network, with activity times in weeks, determine the earliest and latest…
A: Solution Activity Duration Earliest Start Time Earliest Finish Time Latest Start Time Latest…
Q: Find the project's total duration and described the completion of the project activities after the…
A: ANSWER IS AS FOLLOWS:
Q: The company wants to implement the new project. The following are the activities required to 3.…
A:
Q: The project length is weeks.
A: Project management is the management in which different types of skills, techniques, and knowledge…
Q: What is the probability of completion of the project before week 42
A:
Q: What is the probability that the project will be completed by a specific date?
A: The probability of completing a project by a specific date is the date within which the chances of…
Q: Determine the probability that the project will take less than 42 weeks.
A: Given data is
Q: a. Calculate the expected time and variance for each activity. . Calculate the activity slacks and…
A: D(duration)=given in the question as normal time ES (Early start)= The first activity from where the…
Q: Crash the project to 25 days. а. b. What will the total crashing cost be? с. What activities will be…
A: Project crashing is a method in project management to speed up the project time by reducing the…
Q: 1- Total project finishing time. 2- Critical path 3- Free float for each task. 4- If Activity B is…
A: The critical path method is a project management technique that identifies the sequence of tasks…
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- 8 EARNED VALUE ANALYSIS The following project is reported to be at the end of its 8 week. Find the cost and schedule variances. Also find the CPI, SPI, CSI, ETC and EAC for the project. Find the condition of the project at the this reporting period. PV AC Budget ($) Duration Actual Cost % D-8 Activity Predecessor (s) (week) ($) Complete 300 400 A 3 100 A3 В 4 200 180 100 B:4 C 7 250 300 90 A 8 600 400 50 400 200 В 40 150 180 F В 4 100 G C 4 100 200 40 500 H D, E 2 300 F, G 3 J H, I 1 100 ㅇ CO 프 (-)Th e dean of the business school wants to start off eringthis program starting 32 weeks from now. Using the informationprovided in Problem 15,(a) Calculate the probability of the program starting ontime.(b) If the dean needs a 95 percent probability of being doneon time, how long can the expected project duration be?Ssus and the management at yankee Itd. Want an expected time and variance for pest control activity and for that optimistic time was 2 weeks , pessimistic time was 8 weeks and most likely time is 4 weeks ?
- The following project has a critical path of ACD with an expected duration of 10 weeks and a standard deviation of 2 weeks. Given the cost data below. What is the P95 estimate of the cost of the project, Мean Stdh. Dev. Activity Predecessors Cost ($K) Cost ($K) none A 4 1.5 A 7. 2.75 B,C 2 0.5 O 19.6 O 8.4 22.8 O 24.2 O 14.6By using Bar chart planning method, find the following: - Total duration for the project activities shown below - The project completion date (assume the start date is 1/3/2012 Activity A CDEFGHI J Duration 85 2846 7 45 6 (days) Following Activity C,D EFGHIJJ * If the project shown above had a delay of (4 days after (13working days), what would its new delivery date be? B BUsing PERT, Adam Munson was a ble to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project va riance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- Case Study 1: Project Management – Decision Trees A local toy manufacturer has three different mechanisms that can be installed in a doll that it sells. The different mechanisms have three different setup costs (overheads) and variable costs and, therefore, the profit from the dolls is dependent on the volume of sales. The anticipated payoffs are as follows: Light Demand Moderate Demand Heavy Demand Probability 0.25 0.45 0.3 Wind-up action $325,000 $190,000 $170,000 Pneumatic action $300,000 $420,000 $400,000 Electrical action -$400,000 $240,000 $800,000 What is the ultimate objective in the use of decision trees to product design? How is this objective accomplished? Draw the decision tree. What is the EMV of each decision alternative? Which action should be selected?The project described in the following table has just begun. It is scheduled to be completed in 11 weeks.Use Table B1 and Table B2. Activity Estimated Time(weeks) Standard Deviation(wks.) 1-2 4 0.70 2-4 6 0.90 1-3 3 0.62 3-4 9 1.90 a. If you were the manager of this project, would you be concerned? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) because the probability of finishing on schedule is only about . b. If there is a penalty of $5,000 a week for each week the project is late, what is the probability of incurring a penalty of at least $5,000? (Round your intermediate calculations to 2 decimal places and "Probability" values to 4 decimal places.) Probability Have worked this with various formulas and all come back wrong. Where am I making a mistakeUsing PERT, Adam Munson was able to determinethat the expected project completion time for the construction ofa pleasure yacht is 21 months, and the project variance is 4.a) What is the probability that the project will be completed in17 months?b) What is the probability that the project will be completed in20 months?c) What is the probability that the project will be completed in23 months?d) What is the probability that the project will be completed in25 months?e) What is the due date that yields a 95% chance of completion?
- The following information has been computed from aproject:Expected total project time = T = 62 weeksProject variance (s2p ) = 81What is the probability that the project will be completed18 weeks before its expected completion date?IFS233 Donell Consulting recently completed an IT training platform implementation with a public firm. The project concluded after the completion of a testing, piloting and sign-off from the project stakeholders. Though completed, the project manager was reviewing their notes, in which they listed all the important occurrences that were recorded during various project phases: ● The pilot of the training platform is about to begin, and the COO of the firm has informed the project team that they want an additional 1000 staff trained and included, and the firm will be increasing budget accordingly. The new systems analyst replacement just found an issue with the way in which the training platform is recording information inputted from users. Apparently, it does note read or collate all the metadata produced during user inputs, and only considers metadata that leads to a complete sequence of inputs. This is going to cause issues in how we record the users' activities as the client wants to…Stinnett Transmissions, Incorporated, has the following estimates for its new gear assembly project: Price $1,220 per unit; variable costs = $3.75 million; quantity = 90,000 units. Suppose the company believes all of its estimates are accurate only to within ±15 percent. What values should the company use for the four variables given here when it performs its best-case scenario analysis? What about the worst-case scenario? Pls don't copy answer i give up vote