The soil borrow material to be used to construct a highway embankment has a wet unit weight of 15.4 kN/m³, a water content of 9%, and the specific gravity of the soil solids is 2.67. The specifications require that the soil be placed in the fill so that the dry unit weight is 17.9 kN/m³ and the water content be held to 20%. a. How many cubic meters of borrow are required to construct an embankment having a 612, 000-m³ net section volume? b. How many gallons of water must be added per cubic meter of borrow material assuming no loss by evaporation? c. If the compacted fill becomes saturated at constant volume, what will be the water content and unit weight?

Principles of Foundation Engineering (MindTap Course List)
8th Edition
ISBN:9781305081550
Author:Braja M. Das
Publisher:Braja M. Das
Chapter16: Soil Improvement And Ground Modification
Section: Chapter Questions
Problem 16.12P
icon
Related questions
icon
Concept explainers
Question
The soil borrow material to be used to construct a highway embankment has a wet unit
weight of 15.4 kN/m³, a water content of 9%, and the specific gravity of the soil solids
is 2.67. The specifications require that the soil be placed in the fill so that the dry unit
weight is 17.9 kN/m³ and the water content be held to 20%.
a. How many cubic meters of borrow are required to construct an embankment having
a 612, 000-m³ net section volume?
b. How many gallons of water must be added per cubic meter of borrow material
assuming no loss by evaporation?
C. If the compacted fill becomes saturated at constant volume, what will be the water
content and unit weight?
Transcribed Image Text:The soil borrow material to be used to construct a highway embankment has a wet unit weight of 15.4 kN/m³, a water content of 9%, and the specific gravity of the soil solids is 2.67. The specifications require that the soil be placed in the fill so that the dry unit weight is 17.9 kN/m³ and the water content be held to 20%. a. How many cubic meters of borrow are required to construct an embankment having a 612, 000-m³ net section volume? b. How many gallons of water must be added per cubic meter of borrow material assuming no loss by evaporation? C. If the compacted fill becomes saturated at constant volume, what will be the water content and unit weight?
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 4 steps with 4 images

Blurred answer
Knowledge Booster
Sediment transport
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781305081550
Author:
Braja M. Das
Publisher:
Cengage Learning
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Principles of Geotechnical Engineering (MindTap C…
Principles of Geotechnical Engineering (MindTap C…
Civil Engineering
ISBN:
9781305970939
Author:
Braja M. Das, Khaled Sobhan
Publisher:
Cengage Learning