Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN: 9781337788281
Author: James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher: Cengage Learning
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 20, Problem 5C
Initial Direct Costs
Efland Company leases equipment to Orange Company. Efland incurred the following costs associated with the lease:
- Advertising to find a lessee—$20,000
- Commissions for the salesperson—$25,000
- Negotiating fees to sign the contract—$10,000
- Payment to an existing lessee to terminate its lease early—$30,000
- General overhead associated with the leased asset—$10,000
Required:
- 1. Explain what initial direct costs are.
- 2. Indicate precisely how Efland should account for initial direct costs if this lease is (a) an operating lease, (b) a sales-type lease, and (c) a direct financing lease.
- 3. Which of the above amounts should Efland consider initial direct costs?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
In a cost center, the manager has responsibility and authority for making decisions that affect
a. costs
b. investments in assets
c. both costs and revenues
d. revenues
Keating Co. is considering disposing of equipment with a cost of $68,000 and accumulated depreciation of $47,600. Keating Co. can sell the equipment through a broker for $27,000 less 8% commission. Alternatively, Gunner Co. has offered to lease the equipment for five years for a total of $46,000. Keating will incur repair, insurance, and property tax expenses estimated at $10,000 over the five-year period. At lease-end, the equipment is expected to have no residual value. The net differential income from the lease alternative is
a. $11,160
b. $7,812
c. $16,740
d. $13,392
If sales are $828,000, variable costs are 68% of sales, and operating income is $278,000, what is the contribution margin ratio?
a. 64%
b. 36%
c. 68%
d. 32%
Shantal Company is installing a new equipment and incurred the following costs:
Cost of equipment per supplier’s invoice
2,500,000
Initial delivery and handling cost
200,000
Cost of site preparation
600,000
Consultants used for advance on the acquisition of equipment
700,000
Interest charged paid to supplier for deferred credit
200,000
Estimated dismantling cost to be incurred as required by contract
300,000
Operating losses before commercial production
400,000
Group of answer choices
4,300,000
4,000,000
4,200,000
4,500,000
Please assits with this cost accounting question
Contract Masters Ltd has entered into a contract with Creative Dealers Ltd. for the construction of a new branch office. The contract began on March 1, 2022 and was completed on December 28 2022. The total value of the contract was $12,000,000. On December 30, 2022, an engineer inspected the project and issued a final certificate for work done. The following information is available with regards to the contract: $Site labour costs 3,120,000 Materials direct to site 2,000,000Materials returned 30,500 Materials from store and workshops 500,000 Maintenance of plant and use 980,000 Direct expenses 1,090,000 General overheads 750,000 Materials…
Chapter 20 Solutions
Intermediate Accounting: Reporting And Analysis
Ch. 20 - Prob. 1GICh. 20 - List four potential benefits to the lessor of...Ch. 20 - Prob. 3GICh. 20 - What is a substitution right, and when does that...Ch. 20 - Prob. 5GICh. 20 - List the five criteria used to determine if a...Ch. 20 - Prob. 7GICh. 20 - Prob. 8GICh. 20 - Describe briefly the procedures followed by the...Ch. 20 - Owens Company leased equipment for 4 years at...
Ch. 20 - Describe the difference between how a lessee would...Ch. 20 - Prob. 12GICh. 20 - What is the basic difference between the...Ch. 20 - Why are compound interest concepts appropriate and...Ch. 20 - Describe briefly the accounting procedures...Ch. 20 - Prob. 16GICh. 20 - Prob. 17GICh. 20 - Which of the following should be included by the...Ch. 20 - East Company leased a new machine from North...Ch. 20 - Prob. 3MCCh. 20 - Fox Company, a dealer in machinery and equipment,...Ch. 20 - Fox Company, a dealer in machinery and equipment,...Ch. 20 - In the third year of a 6-year finance lease, the...Ch. 20 - Prob. 7MCCh. 20 - At its inception, the lease term of Lease G is 65%...Ch. 20 - Rent received in advance by the lessor for an...Ch. 20 - On August 1, 2019, Kern Company leased a machine...Ch. 20 - Next Level Keller Corporation (the lessee) entered...Ch. 20 - Use the information in RE20-1. Prepare the journal...Ch. 20 - Next Level Garvey Company (the lessee) entered...Ch. 20 - Use the information in RE20-3. Prepare the journal...Ch. 20 - Use the information in RE20-3. Prepare the journal...Ch. 20 - Montevallo Corporation leased equipment from Folio...Ch. 20 - Use the information in RE20-6. However, assume...Ch. 20 - Use the following information to decide whether...Ch. 20 - Use the information in RE20-3. Prepare the journal...Ch. 20 - Determining Type of Lease and Subsequent...Ch. 20 - Lessee Accounting with Payments Made at Beginning...Ch. 20 - Lessee Accounting Issues Sax Company signs a lease...Ch. 20 - Lessee Accounting for Finance Lease On January 1,...Ch. 20 - Prob. 5ECh. 20 - Lessor Accounting Issues Ramsey Company leases...Ch. 20 - Lessor Accounting with Receipts at End of Year...Ch. 20 - Lessor Accounting with Unguaranteed Residual Value...Ch. 20 - Lessor Accounting with Guaranteed Residual Value...Ch. 20 - Determining Type of Lease and Subsequent...Ch. 20 - Guaranteed and Unguaranteed Residual Values...Ch. 20 - Lessor Accounting Issues Rexon Company leases...Ch. 20 - Lessee and Lessor Accounting Issues Diego Leasing...Ch. 20 - Lessee and Lessor Accounting Issues The following...Ch. 20 - Lease Income and Expense Reuben Company retires a...Ch. 20 - Determining Type of Lease and Subsequent...Ch. 20 - Determining Type of Lease and Subsequent...Ch. 20 - Accounting for Leases by Lessee and Lessor Scupper...Ch. 20 - Lessee Accounting Issues Timmer Company signs a...Ch. 20 - Sales-Type Lease with Guaranteed Residual Value...Ch. 20 - Sales-Type Lease with Unguaranteed Residual Value...Ch. 20 - Sales-Type Lease with Receipts at End of Year...Ch. 20 - Initial Direct Costs and Related Issues On January...Ch. 20 - Various Lease Issues for Lessor and Lessee Lessee...Ch. 20 - Prob. 10PCh. 20 - Various Lease Issues Farrington Company leases a...Ch. 20 - Comprehensive Landlord Company and Tenant Company...Ch. 20 - Prob. 1CCh. 20 - Identified Asset A customer enters into a 3-year...Ch. 20 - Prob. 3CCh. 20 - Types of Leases On January 1, Hazard Company, a...Ch. 20 - Initial Direct Costs Efland Company leases...Ch. 20 - Prob. 6C
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- An equipment lease that specifies a payment of $1,000 per month plus $5 per machine hour used is an example of a a.fixed cost b.variable cost c.step cost d.mixed cost e.none of thesearrow_forwardA Company is trying to decide which one of two contracts it will accept. The costs and revenues associated with each are listed below: Contract revenue Materials Contract X Contract Z $ 260,000 $ 200,000 10,000 10,000 Labor costs 88,000 120,000 Depreciation on 8,000 10,000 equipment Cost incurred for 1,500 1,500 consulting advice Allocated portion of overhead 5,000 3,000 The equipment was purchased last year and has no resale value. Which of these amounts is relevant for the selection of one contract over another? OA. Contract revenue and labor costs OB. Materials, consulting advice, and allocated overhead OC. Cost of consulting advice and allocated overhead OD. Contract revenue, labor costs, depreciation on equipment and allocated portion of overhead OE. None of the abovearrow_forwardOn September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical wirings and install a new generator for a total consideration of P10M. The remodeling and the installation single performance obligation treated as a satisfied over time. The expected contract costs Generator LO as follows: Other costs Expected total contract costs 2,500,000 4,000,000 6,500,000 VERSITY Additional information: • ABC Co. uses the cost-to-cost method in measuring its progress towards the complete satisfaction of the performance obligation. • ABC Co. incurs total costs of P4,000,000 in 20x1, including the cost of the generator. The customer obtains control of the generator when it is delivered to the site in December 20x1. However, the generator will not be installed until March 20x2. • • ABC Co. regards the cost of the generator as significant in relation to the expected total contract costs-eating during examinations, quizzes or plagiarism in connection . Although ABC Co.…arrow_forward
- Use the following information for the next three questions: In 20x1, Friedland Co. entered into a contract with a customer for the construction of a building. The contract price is a fixed fee of P12,000,000. Information on the contract is shown below: 20x1 20x2 Costs incurred per year Estimated costs to complete 3,920,000 5,080,000 5,880,000 1,000,000arrow_forwardLong-term Contracts Clorad Corp. contracts with a customer to construct a building. It appropriately determines that it has one performance obligation which is satisfied over time. Using the following information for Year 1, compute Clorad's (a) total estimated costs for the contract, (b) revenue to date, and (c) gross profit recognized. Year 1 (of 4-year project): Construction costs incurred during the year $174,000 Estimated costs to complete the contract 426,000 Partial billings to customers 100,000 Collections from customers 25,000 Total contract price 1,000,000 (a) Total estimated costs for the contract $ (b) Revenue to date $ (c) Gross profit recognized $arrow_forwardThe Heart Co. has just completed a 4-year contract to which the following relate: Labor and Materials costs 1,800,000 Machinery Cost Initial Design Costs Disposal proceeds of machinery 50,000 600,000 100,000 According to IFRS 15, What are the total contract cost?arrow_forward
- Required: Calculate the following: a. estimated total cost of completion, b. estimated profit on completion, c. estimated profit to date. Lim Construction is building Univ tower Near Unicity, Sibu. The date of commencement of construction is 1 January 2021 and the date of completion is on 31 December 2026. During the year ending 31 December 2021, the following information reported: RM Contract price Plant sent to site Purchasing of materials Wages paid Direct expenses Overhead incurred 13,000,000.00 2,000,000.00 3,000,000.00 1,500,000.00 1,000,000.00 500,000.00 At the end of December 2021, the following available: 1. Material unused on site amounted RM1,000,000.00 2. Wages owing RM500,000.00 3. Value of work certified RM6,000,000.00 4. Cost of work done but not yet certified amounted to RM500,000.00 5. Plant at site RM1,500,000.00arrow_forwardOn September 1, 20x1, ABC Co. enters into a contract with a customer to remodel a plant's electrical wirings and install a new generator for a total consideration of P10M. The remodeling and the installation single performance obligation treated as a satisfied over time. The expected contract costs Generator are LOU an as follows: 2,500,000 4,000,000 6,500,000 SALL Other costs Expected total contract costs VERSITY Additional information: • ABC Co. uses the cost-to-cost method in measuring its progress towards the complete satisfaction of the performance obligation. • ABC Co. incurs total costs of P4,000,000 in 20x1, including the cost of the generator. • The customer obtains control of the generator when it is delivered to the site in December 20x1. However, the generator will not be installed until March 20x2. • ABC Co. regards the cost of the generator as significant in relation to the expected total contract costs-eating during examinations, quizzes or plagiarism in connection •…arrow_forwardConstruction Contract: Graded Question #1: George Co. enters into a contract to build an apartment for Jungle Co. for a fixed fee of P20,000,000. At contract inception, George Co. assesses its performance obligations in the contract and concludes that it has a single performance obligation that is satisfied over time. George Co. determines that the measure of progress best depicts its performance in the contract is input method based on costs incurred. George estimates that the total contract costs would amount to P16,000,000 over the construction period. George incurs contract costs of P2,000,000 during the year. How much revenue is recognized for the year?arrow_forward
- Use the following information for the next two questions: Bass Co. appropriately uses the cost-to-cost method in measuring construction contract with a customer. its progress on Information on this contract, which was completed in 20x3, is a shown below: 20x1 20x2 20x3 20,000,000 20,000,000 20,000,000 Transaction price Profit each year Costs incurred each year (200,000) 8,200,000 400,000 1,400,000 3,600,000 (AICPA - Adapted) 1. 10. How much are the contract costs incurred in 20x2? a. 5,800,000 b. 6,200,000 c. 6,600,000 d. 10,200,000 11. How much are the estimated additional costs to complete as of December 31, 20x2? a. 5,400,000 b. 6,800,000 c. 7,200,000 d. 8,600,000arrow_forwardBUILDING COMPANY provided the following information about one of it's construction contracts (CONTRACT XY): Cost incurred to date: $500,000 Cost to complete: $2,500,000 Contract price = Total Cost Plus $1,000,000 Amount paid to date by client: $100,000 How much revenue should BUILDING COMPANY recognize on CONTRACT XY? How much PROFIT/LOSS should BUILDING COMPANY recognize on CONTRACT XY? %3Darrow_forwardComputing Revenue and Gross Profit on Long-term Construction Contract Supplier Corp. enters into a government contract during the year to provide computer equipment for $1,800,000. The contract consists of a single performance obligation to provide specified equipment in three years. Total costs estimated by Supplier Corp. for the contract are $1,260,000. The equipment is highly specialized and has no alternative uses. As negotiated in the contract, any costs incurred by Supplier Corp. plus a specified profit margin will be paid to Supplier Corp. in the event of a contract cancellation. Actual costs incurred during the first year of the contract were $576,000 including unexpected cost overruns of $72,000 due to labor inefficiencies. Assume that at the end of the second year of the contract, the estimate of total costs has increased to $1,350,000 million due to an increase in cost of materials. Actual costs incurred to date are $1,012,500, excluding year one inefficiencies. a. Calculate…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning
Accounting for Finance and Operating Leases | U.S. GAAP CPA Exams; Author: Maxwell CPA Review;https://www.youtube.com/watch?v=iMSaxzIqH9s;License: Standard Youtube License