Explanation of Solution

Selecting the project using the preemptive goal programming:

Consider the following variables x1,x2,........,x8,

xi={1      If project i is build0      otherwise

For every project values related to each attribute are tabulated.

The table is given below,

 12345678
ROI20704566703504953801500480
Cost900240335700410190500160
Productivity improvement32201032
Manpower needed181827364264824
Degree of risk32411023

The company has the following goals.

Goal 1: Archive a return on investment of at least $3,250. Thus the constraint formed is,

2070x1+456x2+670x3+350x4+495x5+380x6+1500x7+480x83250

Goal 2: Limit cost to $1300. Thus the constraint formed is,

900x1+240x2+335x3+700x4+410x5+190x6+500x7+160x81300

Goal 3: Archive a productivity improvement of at least 6. Thus the constraint formed is,

3x1+2x2+2x3+x5+3x7+2x86

Goal 4: Limit manpower use to 108. Thus the constraint formed is,

18x1+18x2+27x3+36x4+42x5+6x6+48x7+24x8108

Goal 5: Limit technological risk to a total of 4. Thus the constraint formed is

3x1+2x2+4x3+x4+x5+6x6+2x7+3x84

Hence the linear programming can be formulated as given below,

Minimize z=x1+x2+x3+x4+x5+x6+x7+x8

Subject to the constraints,

2070x1+456x2+670x3+350x4+495x5+380x6+1500x7+480x83250900x1+240x2+335x3+700x4+410x5+190x6+500x7+160x813003x1+2x2+2x3+x5+3x7+2x8618x1+18x2+27x3+36x4+42x5+6x6+48x7+24x8108

3x1+2x2+4x3+x4+x5+6x6+2x7+3x84xi0

Here, it is observed that for these set of constraints, there is no region which is feasible. That is all the constraints cannot be met. Hence e assign a cost value incurred if any of the goal is not meet. So introduce deviational variables as follows

Blurred answer
Students have asked these similar questions
Charlie looked across his desk at Kelvin, who was absorbed in the sheaf of handwritten notes from the meeting. Charlie had asked Kelvin to come his office to discuss the change control meeting that had occurred earlier that day. “So what do you think?” he asked.“I think I was blindsided by a bus!” Kelvin replied. “I thought I had considered all the possible effects of the change in my project plan. I tried to explain this, but everyone acted as if I had threatened their jobs.” “In a way you did,” Charlie stated. “Some people believe that change is the enemy.” “But these changes are important.” “I agree,” Charlie said. “But successful change usually occurs in small steps. What’s your top priority?” “All the items on this list are top priorities,” Kelvin said. “I haven ’t even gotten to the second tier. ” “So what should you do to accomplish these top priorities?” Charlie asked.“I guess I should reprioritize within my top tier, but what then?”“The next step is to build support before the…
The nominal effort and duration of a large size project have been estimated to be 10000 PM and 2 Years. The project cost has been negotiated to be Rs. 500,000,000. The product need to be developed in and delivered in 1 year and 5 months. What should be the new cost to be negotiated?Justify whether the proposed reduction in duration of the project development is possible or not.
As a project your team is given the task of designing a space station consisting of four different habitats. Each habitat is an enclosed sphere containing all necessary life support and laboratory facilities. The masses of these habitats are 1.0 x 106 kg, 2.0 x 106 kg, 3.0 x 106 kg, and 4.0 x 106 kg. The entire station must spin so that the inhabitants will experience an artificial gravity. Your team has decided to arrange the habitats at corners of a square with 1.0 km sides. The axis of rotation will be perpendicular to the plane of the square and through the center of mass. To help decide if this plan is practical, you calculate how much energy would be necessary to set the space station spinning at 1.0 revolution per minute. In your team's design, the size of each habitat is small compared to the size of the space between the habitats and the structure that holds the habitats together is much less massive than any single habitat. how much energy would be necessary to set the space…

Chapter 4 Solutions

Introduction to mathematical programming

Ch. 4.5 - Prob. 1PCh. 4.5 - Prob. 2PCh. 4.5 - Prob. 3PCh. 4.5 - Prob. 4PCh. 4.5 - Prob. 5PCh. 4.5 - Prob. 6PCh. 4.5 - Prob. 7PCh. 4.6 - Prob. 1PCh. 4.6 - Prob. 2PCh. 4.6 - Prob. 3PCh. 4.6 - Prob. 4PCh. 4.7 - Prob. 1PCh. 4.7 - Prob. 2PCh. 4.7 - Prob. 3PCh. 4.7 - Prob. 4PCh. 4.7 - Prob. 5PCh. 4.7 - Prob. 6PCh. 4.7 - Prob. 7PCh. 4.7 - Prob. 8PCh. 4.7 - Prob. 9PCh. 4.8 - Prob. 1PCh. 4.8 - Prob. 2PCh. 4.8 - Prob. 3PCh. 4.8 - Prob. 4PCh. 4.8 - Prob. 5PCh. 4.8 - Prob. 6PCh. 4.10 - Prob. 1PCh. 4.10 - Prob. 2PCh. 4.10 - Prob. 3PCh. 4.10 - Prob. 4PCh. 4.10 - Prob. 5PCh. 4.11 - Prob. 1PCh. 4.11 - Prob. 2PCh. 4.11 - Prob. 3PCh. 4.11 - Prob. 4PCh. 4.11 - Prob. 5PCh. 4.11 - Prob. 6PCh. 4.12 - Prob. 1PCh. 4.12 - Prob. 2PCh. 4.12 - Prob. 3PCh. 4.12 - Prob. 4PCh. 4.12 - Prob. 5PCh. 4.12 - Prob. 6PCh. 4.13 - Prob. 2PCh. 4.14 - Prob. 1PCh. 4.14 - Prob. 2PCh. 4.14 - Prob. 3PCh. 4.14 - Prob. 4PCh. 4.14 - Prob. 5PCh. 4.14 - Prob. 6PCh. 4.14 - Prob. 7PCh. 4.16 - Prob. 1PCh. 4.16 - Prob. 2PCh. 4.16 - Prob. 3PCh. 4.16 - Prob. 5PCh. 4.16 - Prob. 7PCh. 4.16 - Prob. 8PCh. 4.16 - Prob. 9PCh. 4.16 - Prob. 10PCh. 4.16 - Prob. 11PCh. 4.16 - Prob. 12PCh. 4.16 - Prob. 13PCh. 4.16 - Prob. 14PCh. 4.17 - Prob. 1PCh. 4.17 - Prob. 2PCh. 4.17 - Prob. 3PCh. 4.17 - Prob. 4PCh. 4.17 - Prob. 5PCh. 4.17 - Prob. 7PCh. 4.17 - Prob. 8PCh. 4 - Prob. 1RPCh. 4 - Prob. 2RPCh. 4 - Prob. 3RPCh. 4 - Prob. 4RPCh. 4 - Prob. 5RPCh. 4 - Prob. 6RPCh. 4 - Prob. 7RPCh. 4 - Prob. 8RPCh. 4 - Prob. 9RPCh. 4 - Prob. 10RPCh. 4 - Prob. 12RPCh. 4 - Prob. 13RPCh. 4 - Prob. 14RPCh. 4 - Prob. 16RPCh. 4 - Prob. 17RPCh. 4 - Prob. 18RPCh. 4 - Prob. 19RPCh. 4 - Prob. 20RPCh. 4 - Prob. 21RPCh. 4 - Prob. 22RPCh. 4 - Prob. 23RPCh. 4 - Prob. 24RPCh. 4 - Prob. 26RPCh. 4 - Prob. 27RPCh. 4 - Prob. 28RP
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Operations Research : Applications and Algorithms
Computer Science
ISBN:9780534380588
Author:Wayne L. Winston
Publisher:Brooks Cole
Text book image
Fundamentals of Information Systems
Computer Science
ISBN:9781337097536
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning
Text book image
Principles of Information Systems (MindTap Course...
Computer Science
ISBN:9781305971776
Author:Ralph Stair, George Reynolds
Publisher:Cengage Learning