Degarmo's Materials And Processes In Manufacturing
13th Edition
ISBN: 9781119492825
Author: Black, J. Temple, Kohser, Ronald A., Author.
Publisher: Wiley,
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 1, Problem 1P
- The Toyota truck plant in Indiana produces 150,000 trucks per year. The plant runs one eight�hour shift and makes 400 trucks per day. About 1300 people work on the final assembly line. Each truck has about 20 direct labor hours per car in it.
- Assuming the truck sells for $26,000 and workers earn $50 per hour in wages and benefits, what percentage of the cost of the truck is in direct labor?
- What is the production rate of the final assembly line?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
A toy manufacturing uses 51030 rubber wheels per year for its popular dump truck series. The firm makes its own wheels, which it can can produce at a rate of 800 per day. The toy trucks are assembled uniformly ( at a constant rate ) over the entire year. Carrying cost is $ 1.50 per wheel per year. setup cost for the production run of the wheel is $ 47. The firm operatyes 243 days per year. Determine each of the following:
1-Optimal run size
2-Use your final answer from part 1 to determine minimum total annual cost for carrying and setup
3-Cycle time for the optimal run size
4-Run time
A final assembly plant for a certain automobilemodel is to have a capacity of 240,000 units annually.The plant will operate 50 wk/yr, 2 shifts/day, 5 days/wk, and 8.0 hr/shift. It will be divided into three departments: (1) body shop, (2) paint shop, (3) trim-chassis-final department. The body shop welds the car bodies using robots, and the paint shop coats the bodies. Both of these departments are highly auto-mated. Trim-chassis-final has no automation. There are 15.5 hr of direct labor content on each car in this department, where cars are moved by a continuous conveyor. Determine (a) hourly production rate ofthe plant, (b) number of workers and workstations required in trim-chassis-final if no automated stations are used, the average manning level is 2.5, balancing efficiency 1⁄4 93%, proportion uptime 1⁄495%, and a repositioning time of 0.15 min is allowedfor each worker.
A certain Batch manufacturing plant requires one operator to tend to 2 semiautomatic
machines used in production. The plant operates one 10-hour shift per day for 250 days
in a year. The operator is paid $30 per hour with applicable factory labor overhead rate
of 50%. Other pertinent information about the system in include the information
provided below. Determine the hourly cost of the system.
Machine 1
Machine 2
Initial cost
$125,000
$10,000
$5000
$150,000
$5000
$3000
Installation
Yearly maintenance cost
10 years
$5000
SL
years
$10,000
SV
20%
20%
ROR
50%
Applicable MOHR
30%
Chapter 1 Solutions
Degarmo's Materials And Processes In Manufacturing
Ch. 1 - What role does manufacturing play relative to the...Ch. 1 - Arent all goods really consumer goods, depending...Ch. 1 - The Subway sandwich shop is an example of a job...Ch. 1 - How does a system differ from a process? From a...Ch. 1 - Is a cutting tool the same thing as a machine...Ch. 1 - What are the major classifications of basic...Ch. 1 - Casting is often used to produce a...Ch. 1 - In the lost�wax casting process, what happens to...Ch. 1 - In making a gold medal, what do we mean by a...Ch. 1 - How is a railroad station like a station on an...
Ch. 1 - Because no work is being done on a part when it is...Ch. 1 - What forming processes are used to make a paper...Ch. 1 - What is tooling in a manufacturing system?Ch. 1 - It is acknowledged that chipâ€�type machining is...Ch. 1 - Compare Figures 1.1 and 1.16. What are the...Ch. 1 - In a modern safety razor with three or four blades...Ch. 1 - List three purposes of packaging operations.Ch. 1 - Assembly is defined as the putting together of...Ch. 1 - What are the physical elements in a manufacturing...Ch. 1 - In the production system, who usually figures out...Ch. 1 - In Figure 1.8, what do the lines connecting the...Ch. 1 - Characterize the process of squeezing toothpaste...Ch. 1 - It has been said that low-cost products are more...Ch. 1 - Prob. 24RQCh. 1 - If the rolls for the cold-rolling mill that...Ch. 1 - Make a list of service systems, giving an example...Ch. 1 - What is the fundamental difference between a...Ch. 1 - Prob. 28RQCh. 1 - What kind of process is powder metallurgy: casting...Ch. 1 - In view of Figure 1.2, who really determines the...Ch. 1 - What costs make up manufacturing cost (sometimes...Ch. 1 - What are major phases of a product life cycle?Ch. 1 - How many different manufacturing systems might be...Ch. 1 - In general, as the annual volume for a product...Ch. 1 - The Toyota truck plant in Indiana produces 150,000...Ch. 1 - A company is considering making automobile bumpers...Ch. 1 - Many companies are critically examining the...Ch. 1 - We can analogize your university to a...Ch. 1 - What kind of manufacturing system (design) is your...Ch. 1 - What are the major process steps in the assembly...Ch. 1 - What is the relationship between Figures 1.2Â...Ch. 1 - Recently, National Geographic magazine asked the...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, mechanical-engineering and related others by exploring similar questions and additional content below.Similar questions
- In a factory where there are three shifts: The machine overhead cost is found to be £8.20 / hr, the labour overhead cost is found to be £30.20/hr, and the premises overhead cost is found to be £3.50/hr. Using the principle of overhead costing: If a single component takes 23 minutes to manufacture on the milling machine. What is the cost / part? You should include machine costs, labour costs and premises costs in your answer, but you can neglect material and energy costs. Express your answer in £ rounded up to the nearest penny.arrow_forwardthe final answer is 0.5 A production machine operates in a semi-automatic cycle but a worker must attend the machine 100% of the time to load parts. Unloading is accomplished automatically. The worker's cost rate = 37$/hr including applicable labor overhead rate. To produce the parts, the production machine was bought six years ago for installed price of $750,000. At that time it was anticipated that the machine would last 8 years and be used 5000 hours per year. However, it is now in need of major repairs that will cost $166,500. These repairs will be made and as a result, the machine will last three years, operating 4000 hours per year. Applicable overhead rate for the machine = 42%. Cost of the starting parts = 0.12$/pc. The job runs several months so the effect of setup can be ignored. Each cycle, the actual process time = 26s, and time to load the part = 18 s. Automatic unloading takes 4 s. A proposal has been made to install an automatic parts-loading device on the machine. The…arrow_forwardA worker is currently responsible for tending two machines in a machine cluster. The service time per machine is 0.35 min and the time to walk between machines is 0.15 min.The machine automatic cycle time is 1.90 min. If the worker’s hourly rate = $12/hr andthe hourly rate for each machine = $18/hr, determine (a) the current hourly rate for thecluster, and (b) the current cost per unit of product, given that two units are produced byeach machine during each machine cycle. (c) What is the percent idle time of the worker?(d) What is the optimum number of machines that should be used in the machine cluster, ifminimum cost per unit of product is the decision criterion?arrow_forward
- A certain job shop specializes in one-of-a-kind orders dealing with parts of medium-to-high complexity. A typical part is processed sequentially through 10 machines in batch sizes of 1. The shop contains a total of eight conventional machine tools and operates 40 hr/wk of pro duction time. Average time values on each part per machine are: machining time = 0.5 hr, work handling time = 0.3 hr, tool change time = 0.2 hr, setup time = 3 hr, and non operation time = 12 hr. A new programmable machine is being considered that can per form all 10 operations in a single setup. The programming of the machine for this part will require 20 hr; however, the programming can be done off-line, without tying up the machine. Setup time will be just 2 hr because simpler fixtures will be used. Total machining time will be reduced to 80% of its previous value due to advanced tool control algorithms; work han dling time will be the same as for one machine; and total tool change time will be reduced by…arrow_forwardGiven the following data, determine the number of trucks that would be required per shift to haul iron ores from the open pit to the milling plant. Hauling time per shift = 6 hours Truck Capacity = 35 MT rear dump truck Production rate per shift- 18,900 MT Total cycle time = 5.53 min. Assume efficiency of 50 productive minute per hourarrow_forward1. A certain batch of parts is routed through six machines in a batch production plant. The setup and operation times for each machine are given in the table below. Batch size is 200 and the average nonoperation time per machine is15 hr. Determine (a) manufacturing lead time and (b) hourly production rate for operation 4.Machine 1 2 3 4 5 6Setup time (hr) 5 3 6 4 5 3Operation time (min) 3.0 3.3 8.2 3.9 4.5 2.3 a. 6(4.3+200(3.9/60)+15) = 193.8 hours 24.2 days if 8 hour shiftb. 4(60)+200(3.9)/200 =5.1 hourly production for operation 4 2. Suppose the part in the previous problem is made in very large quantities on a production line in which an automated work handling system is used to transfer parts between machines. Transfer time between stations is 30 sec. total time required to setup the entire line is 102 hr. Assume that the operation times at the individual machines remain the same as in the previous problem, Determine (a) manufacturing lead time for a part coming off the line,…arrow_forward
- B: Iraq Glass Industries Company produces two types of products, A and B, each one goes through two production stages. Product A needs 1 working hour in the first phase, and 4 working hours in the second phase, while Product B needs 2 working hours in the first phase, and 3 hours of work in the second stage. If you know that the profit per unit of product A is $60, and the profit per unit of product B is $50. The available weekly working hours in the first stage are 40 hours, and in the second stage are 120 hours. Required: Building a mathematical model that maximizes the company's profitsarrow_forwardConsider a line consisting of only one machine. This machine takes on average 4 minutes (te=4 min) to complete a job and Ca2=Ce2=1. The arrival rate of the parts to this machine is 1/8 part/minutes. Assume that there is enough space for only 5 parts between the machines (Hint: the buffer size, b, is 5.) Compute the expected CT of this production line. CT=_________arrow_forwardA flow-line mass production operation consists of six manual workstations. Work units are moved synchronously and automatically between stations, with a transfer time of 10 secs. The manual processing operations performed at the six stations take 45 sec, 50 sec, 40 sec, 42 sec, 30 sec, and 55 sec, respectively. Determine (a) cycle time for the line, (b) time to process one work until through the six workstations, (c) average production rate, and (d) time to produce 20,000 units.arrow_forward
- An assembly line running at 2000 hours/year is required to meet the annual demand of 50000 units. The total work content time = 45 min and the manning level is 1. Assuming line efficiency of 0.90 and balancing efficiency of 0.80; determine: (a) the number of work station required to meet the annual demand, and (b) the number of workers required to meet the annual demand if repositioning time of 15 sec is considered in part (b).arrow_forwardA company is about to begin production of a new product. The manager of the department thatwill produce one of the components for the product wants to know how often the machine usedto produce the item will be available for other work. The machine will produce the item at a rateof 200 units a day. Eighty units will be used daily in assembling the final product. Assembly willtake place five days a week, 50 weeks a year. The manager estimates that it will take almost a fullday to get the machine ready for a production run, at a cost of $300. Inventory holding costs willbe $10 a year.a. What run quantity should be used to minimize total annual costs?b. How many days does it take to produce the optimal run quantity?c. What is the average amount of inventory?d. If the manager wants to run another job between runs of this item, and needs a minimum of 10days per cycle for the other work, will there be enough time?e. Given your answer to part d, the manager wants to explore options that will…arrow_forwardA 12-station transfer line was designed to operate with an ideal production rate = 50 parts/hour. However, the line does not achieve this rate, since the line efficiency E = 0.60. It costs $75/hour to operate the line, exclusive of materials. The line operates 4000 hours per year. A computer monitoring system has been proposed that will cost $25,000 (installed) and will reduce downtime on the line by 25%. If the value added per unit produced = $4.00, will the computer system pay for 270 itself within one year of operation. Use expected increase in revenues resulting from the computer system as the criterion. Ignore material costs in your calculationsarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Elements Of ElectromagneticsMechanical EngineeringISBN:9780190698614Author:Sadiku, Matthew N. O.Publisher:Oxford University PressMechanics of Materials (10th Edition)Mechanical EngineeringISBN:9780134319650Author:Russell C. HibbelerPublisher:PEARSONThermodynamics: An Engineering ApproachMechanical EngineeringISBN:9781259822674Author:Yunus A. Cengel Dr., Michael A. BolesPublisher:McGraw-Hill Education
- Control Systems EngineeringMechanical EngineeringISBN:9781118170519Author:Norman S. NisePublisher:WILEYMechanics of Materials (MindTap Course List)Mechanical EngineeringISBN:9781337093347Author:Barry J. Goodno, James M. GerePublisher:Cengage LearningEngineering Mechanics: StaticsMechanical EngineeringISBN:9781118807330Author:James L. Meriam, L. G. Kraige, J. N. BoltonPublisher:WILEY
Elements Of Electromagnetics
Mechanical Engineering
ISBN:9780190698614
Author:Sadiku, Matthew N. O.
Publisher:Oxford University Press
Mechanics of Materials (10th Edition)
Mechanical Engineering
ISBN:9780134319650
Author:Russell C. Hibbeler
Publisher:PEARSON
Thermodynamics: An Engineering Approach
Mechanical Engineering
ISBN:9781259822674
Author:Yunus A. Cengel Dr., Michael A. Boles
Publisher:McGraw-Hill Education
Control Systems Engineering
Mechanical Engineering
ISBN:9781118170519
Author:Norman S. Nise
Publisher:WILEY
Mechanics of Materials (MindTap Course List)
Mechanical Engineering
ISBN:9781337093347
Author:Barry J. Goodno, James M. Gere
Publisher:Cengage Learning
Engineering Mechanics: Statics
Mechanical Engineering
ISBN:9781118807330
Author:James L. Meriam, L. G. Kraige, J. N. Bolton
Publisher:WILEY
How Shell and Tube Heat Exchangers Work (Engineering); Author: saVRee;https://www.youtube.com/watch?v=OyQ3SaU4KKU;License: Standard Youtube License