Virginia College promotes a wide variety of executive- training courses for firms in the Arlington, Virginia, region. Director Wendy Tate believes that individually written letters add a personal touch to marketing. To prepare letters for mailing, she conducts a time study of her secretaries. On the basis of the observations shown in the following table, she wishes to develop a time standard for the whole job.
The college uses a total allowance factor of 12%. Tate decides to delete all unusual observations from the time study. What is the standard time?
aDisregard–secretary stopped to answer the phone.
bDisregard–interruption by supervisor.
To determine: The standard time for the operation.
Introduction: Time study is the basis that helps set the standard time; it would time a sample of the performance of the worker.
Answer to Problem 23P
Thestandard time is calculated as 5.4 minutes.
Explanation of Solution
Given information:
The allowance factor is given as 12%. The observed time and performance rating for each element is given as follows:
Element | Performance rating | Observation (minutes) | |||||
1 | 2 | 3 | 4 | 5 | 6 | ||
Typing letter | 85 | 2.5 | 3.5 | 2.8 | 2.1 | 2.6 | 3.3 |
Typing envelope | 100 | 0.8 | 0.8 | 0.6 | 0.8 | 3.1a | 0.7 |
Stuffing envelope | 95 | 0.4 | 0.5 | 1.9a | 0.3 | 0.6 | 0.5 |
Sealing and sorting | 125 | 1 | 2.9b | 0.9 | 1 | 4.4b | 0.9 |
a refers to the secretary stopping to answer the phone
b refers to the interruption by a supervisor
Formulae to calculate standard time:
Calculate standard time:
Element | Performance rating | Observation (minutes) | Average time | Normal time | |||||
1 | 2 | 3 | 4 | 5 | 6 | ||||
Typing letter | 85% | 2.5 | 3.5 | 2.8 | 2.1 | 2.6 | 3.3 | 2.8 | 2.38 |
Typing envelope | 100% | 0.8 | 0.8 | 0.6 | 0.8 | 3.1a | 0.7 | 0.74 | 0.74 |
Stuffing envelope | 95% | 0.4 | 0.5 | 1.9a | 0.3 | 0.6 | 0.5 | 0.46 | 0.437 |
Sealing and sorting | 125% | 1 | 2.9b | 0.9 | 1 | 4.4b | 0.9 | 0.95 | 1.1875 |
Excel worksheet:
Calculate the average time for typing letters:
The average time is calculated by taking an average of the observation given, which is summation of 2.5, 3.5, 2.8, 2.1, 2.6, and 3.3 and dividing the result by 6. Hence, the average is 2.8 minutes.
Calculate the average time for typing envelope:
The average time is calculated by taking an average of the observation given, which is summation of 0.8, 0.8, 0.6, 0.8, and 0.7 and dividing the result by 5. Hence, the average is 0.74 minutes.
Note: The observation with (Xa) should not be considered while calculating the average time.
Calculate the average time for stuffing envelope:
The average time is calculated by taking an average of the observation given, which is summation of 0.4, 0.5, 0.3, 0.6, and 0.5 and dividing the result by 5. Hence, the average is 0.46 minutes.
Note: The observation with (Xa) should not be considered while calculating average time.
Calculate average time for sealing and sorting:
The average time is calculated by taking an average of the observation given, which is summation of 1.0, 0.9, 1.0, and 0.9 and dividing the result by 4. Hence, the average is 0.95 minutes.
Note: The observation with (Xa and Xb) should not be considered while calculating average time.
Calculate normal time for typing letter:
Normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 2.8 minutes, and performance rating is given as 85%. Hence, the normal time is 2.38 minutes.
Calculate normal time for typing envelope:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.74 minutes, and performance rating is given as 100%. Hence, the normal time is 0.74 minutes.
Calculate normal time for stuffing envelope:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.46 minutes, and performance rating is given as 95%. Hence, the normal time is 0.437 minutes.
Calculate normal time for sealing and sorting:
The normal time is calculated by multiplying the average time and performance rating. The average time is calculated as 0.95 minutes, and performance rating is given as 125%. Hence, the normal time is 1.1875 minutes.
Calculate the total normal time:
The normal time is calculated by adding the normal time for typing letter, typing envelope, stuffing envelope, and sealing and sorting.
Hence, the total normal time is 4.75 minutes.
Calculate the standard time:
The standard time is calculated by dividing the normal time with the value attained by subtracting the allowance factor from 1. The normal time is calculated as 4.75 minutes and the allowance factor is calculated as 12%
Hence, the standard time is 5.4 minutes.
Want to see more full solutions like this?
Chapter 10 Solutions
Principles Of Operations Management
- Racks Company has developed the following standards for one of its products: Direct materials 12 kilograms @ $14 per kg Direct labour 3 hours @ $18 per hour Variable overhead 3 hours @ $ 8 per hour The following activities occurred during the month of October: Materials purchased 10,000 kilograms at $13.60 per kg Materials used 9,000 kilograms Units produced 800 units Direct labour 2,500 hours at $19.00 per hour Actual variable overhead $22,000 The company records materials price variances at the time of purchase. Racks Company's materials price variance would be Racks Company's materials usage variance would be Racks Company's labour rate variance would be Racks Company's labour efficiency variance would be Who would NOT be responsible for an unfavourable material usage variance caused by poor quality material?arrow_forwardDevelop a Ghantt Chart in excel based on the following information Start Date End Date Duration(Days) 1/18/22 5/1/22 103 1/18/22 1/25/22 7 1/19/22 1/22/22 3 1/21/22 1/23/22 2 1/22/22 1/23/22 1 1/23/22 1/24/22 1 1/28/22 2/28/22 31 1/28/22 2/8/22 11 2/8/22 2/14/22 6 2/15/22 2/17/22 2 2/17/22 2/19/22 2 2/19/22 2/20/22 1 2/21/22 2/23/22 2 2/24/22 2/25/22 1 2/26/22 2/27/22 1 2/27/22 2/28/22 1 2/28/22 2/28/22 0 3/1/22 3/25/22 24 3/2/22 3/7/22 5 3/8/22 3/11/22 3 3/12/22 3/15/22 3 3/16/22 3/23/22 7 3/24/22 3/25/22 1 3/26/22 4/15/22 20 3/27/22 4/5/22 9 4/6/22 4/15/22 9 4/16/22 4/30/22 14 4/17/22 4/22/22 5 4/23/22 4/26/22 3 4/27/22 5/1/22 4arrow_forwardWhy is it necessary to include units when reportingscientific measurements?arrow_forward
- Observations (mins) Day 1 2 3 4 5 6 1 21 30 22 25 31 30 2 23 29 17 32 28 31 3 22 28 33 26 32 31 4 33 30 22 35 29 30 5 35 27 36 28 31 27 6 27 32 30 35 32 32 7 35 32 28 35 35 27 8 26 30 31 37 39 31 9 36 36 34 39 31 25 10 26 42 35 35 27 37 The patient surveys indicate that they are willing to wait between 15 and 35 minutes before seeing Dr. Patel. Calculate the process capability index and capability ratio at the three-sigma level and interpret your results.arrow_forwardAs part of an insurance company’s training program, participants learn how to conduct an analysis of clients’ insurability. The goal is to have participants achieve a time in the range of 30 to 45 minutes. Test results for three participants were the following: Armand, a mean of 36.0 minutes and a standard deviation of 3.0 minutes; Jerry, a mean of 34.0 minutes and a standard deviation of 2.0 minutes; and Melissa, a mean of 37.5 minutes and a standard deviation of 1.7 minutes. a.Compute process capability for the participants and determine whether each is capable. (Do not round intermediate calculations. Round your answers to 2 decimal places.) Melissa ? Cp what is itarrow_forwardAs part of an insurance company’s training program, participants learn how to conduct an analysis of clients’ insurability. The goal is to have participants achieve a time in the range of 30 to 45 minutes. Test results for three participants were the following: Armand, a mean of 36.0 minutes and a standard deviation of 2.0 minutes; Jerry, a mean of 37.0 minutes and a standard deviation of 2.0 minutes; and Melissa, a mean of 37.5 minutes and a standard deviation of 2.6 minutes. a.Compute process capability for the participants and determine whether each is capable, given 4-sigma quality standards. (Do not round intermediate calculations. Round your answers to 2 decimal places.)arrow_forward
- A library administrator wants to determine the proportion of time the circulation clerk is idle. The following information was gathered randomly by using work sampling: Day Number of TimesClerk Busy Number of TimesClerk Idle Total Number ofObservations Monday Tuesday Wednesday Thursday Friday Saturday 8 7 9 7 8 6 2 1 3 3 2 4 10 8 12 10 10 10 If the administrator wants a 95 percent confidence level and a degree of precision of +- 4 percent, how many more observations are needed?arrow_forwardCose 27: Housekeeping Guest Satafaction Scores 81 Case 27 Housekeeping Guest Satisfaction Scores Case Type: Head Case Main Subjects: Motivation, Rewards • Shakia Andrews, Executive Housekerper Who's Who: hakia was desperate. The guest satisfaction scores for the Housekeeping department have Sbeen extremely low for the past year. Though the Housekeeping management has been in place for several years, nearly all of the guestroom attendants have been employed by the Royal Hotel for less than two years. Shakia was ot sure what had caused the perceived level of service and cleanliness to suffer. 1. Why are the guest servine scores for the Housekeeping department usually low? 2 Housekeeping managers often valize that probably the hardest part of their job is to moti- vate their staff. Explain. 3. Where should Shakia begin to raise the guest satisfactions scores? 4. To maintain the comnitment of housekeepers, identify creative intrinsic' and extrinsic rewards Notes Intrinsie rewards are…arrow_forwardA Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of a ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers performing this task five times. The observations were made in an air-conditioned, well-lit training facility, at ground level, with all tools and equipment clean and readily available. Observation: 1 2 3 4 5 Task time (seconds): 82 74 80 88 76 (a) What is the actual average time for this task? (b) What is the normal time for this task if the employee worked at a 10% faster pace than is typical for adequately trained workers? (c) What is standard time for this task if allowances sum to 12%? (d) If the analyst then thought more carefully about his experiment and decided that the allowances needed to be increased to match the real (outside, not…arrow_forward
- Virginia College promotes a wide variety of executive training courses for firms in the Arlington, Virginia, region. Director Wendy Tate believes that individually typed letters add a personal touch to marketing. To prepare letters for mailing, she conducts a time study of her secretaries. On the basis of the observations shown in the following table, she wishes to develop a time standard for the whole job. Performance Observation (minutes per cycle) Element Rating 1 2 3 4 6 Typing letter Typing envelope Stuffing envelope 85% 2.5 3.5 2.8 2.1 2.6 3.3 100 % 0.8 0.8 0.6 0.8 3.1* 0.7 95% 0.4 0.5 1.9* 0.3 0.6 0.5 Sealing, sorting 125% 1.0 2.9^ 0.9 1.0 4.4^ 0.9 * Disregard-secretary stopped to answer the phone * Disregard-interruption by supervisor The college uses a total allowance factor of 12%. Tate decides to delete all unusual observations from the time study. The standard time for this process = minutes (round your response to two decimal places).arrow_forwardFormulate a general pattern of job description and job specifications. 1. Personnel Manager JOB DESCRIPTION: JOB SPECIFICATION: 2.Computer Programmer JOB DESCRIPTION: JOB SPECIFICATION:arrow_forward15-19 A new president at Big State University has made student satisfaction with the enrollment and registration process one of her highest priorities. Students must see an advisor, sign up for classes, obtain a parking permit, pay tuition and fees, and buy textbooks and other supplies. During one registration period, 10 students every hour are sampled and asked about satisfaction with each of these areas. Twelve different groups of students were sampled, and the number in each group who had at least one complaint is as follows: 0, 2, 1, 0, 0, 1, 3, 0, 1, 2, 2, 0. Develop upper and lower control limits (99.7%) for the proportion of students with complaints.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.